CE 332 – Construction Engineering and Management

Similar presentations


Presentation on theme: "CE 332 – Construction Engineering and Management"— Presentation transcript:

1 CE 332 – Construction Engineering and Management
MS Project - Recitation

2 CE 332 - Construction Engineering and Management
METU MICROSOFT PROJECT Microsoft Project is a project management software, developed and sold by Microsoft, which is designed to assist a project manager in; 1) Developing a plan 2) Assigning resources to tasks 3) Tracking progress 4) Managing the budget 5) Analyzing workloads The first commercial version of Project was released in 1984. Microsoft Project 95 was the first to use common Office menus. Then 1998 (v9.0), 2000 (v10.0), 2003 (v11.0), 2007 (v12.0), 2010 (v14.0), 2013 (v15.0) versions were released. Last version is released in 2016.

3 RECITATION PROBLEM CE 332 - Construction Engineering and Management
METU RECITATION PROBLEM Activity Number Activity Description Duration (weeks) Dependence Resource Demand 1 Set up site - 2 Excavate left abutment 6 Excavator 3 Excavate left pier 4 Excavate right pier 5 Excavate right abutment Piledriving to right pier 7 Foundations left abutment 8 Concrete team for foundations Foundations left pier 9 Foundations right pier 10 Foundations right abutment 11 Concrete left abutment Concrete team for abutments and piers 12 Concrete left pier 13 Concrete right pier 14 Concrete right abutment 15 Place beams left span 11,12 Crane 16 Place beams centre span 12,13 17 Place beams right span 13,14 18 Clear site 15,16,17

4 RECITATION PROBLEM The project is planned to start at June 1, 2017.
CE Construction Engineering and Management METU RECITATION PROBLEM The project is planned to start at June 1, 2017. There are no holidays in the work schedule (there will be no holidays on Saturdays, or Sundays, or on official holiday dates). Develop two schedules for a bridge construction project by assuming; a) There are no resource-constraints (unlimited number of resources). b) The availability of each resource is one.

5 STEP 1: Download MS Project 2016 & Install it to the computer
CE Construction Engineering and Management METU SOLUTION STEPS STEP 1: Download MS Project 2016 & Install it to the computer Download Link: 60-day trial version

6 STEP 2: Create project calendar
CE Construction Engineering and Management METU SOLUTION STEPS STEP 2: Create project calendar Project → Change Working Time → Create New Calendar

7 STEP 2: Create project calendar
CE Construction Engineering and Management METU SOLUTION STEPS STEP 2: Create project calendar Details → Select Day → Set day(s) to these specific working times

8 STEP 3: Edit project information
CE Construction Engineering and Management METU SOLUTION STEPS STEP 3: Edit project information Project → Project Information

9 STEP 4: Enter activity names
CE Construction Engineering and Management METU SOLUTION STEPS STEP 4: Enter activity names

10 STEP 5: Enter duration of the activities
CE Construction Engineering and Management METU SOLUTION STEPS STEP 5: Enter duration of the activities

11 STEP 6: Choose task calendar
CE Construction Engineering and Management METU SOLUTION STEPS STEP 6: Choose task calendar

12 STEP 7: Choose automatically scheduled task for each activities
CE Construction Engineering and Management METU SOLUTION STEPS STEP 7: Choose automatically scheduled task for each activities

13 STEP 8: Enter predecessors
CE Construction Engineering and Management METU SOLUTION STEPS STEP 8: Enter predecessors

14 STEP 9: Define resources
CE Construction Engineering and Management METU SOLUTION STEPS STEP 9: Define resources Resource → Choose resource sheet view

15 STEP 9: Define resources
CE Construction Engineering and Management METU SOLUTION STEPS STEP 9: Define resources Add resource names → Define initials → Define availability

16 STEP 10: Assign resources to the related activities
CE Construction Engineering and Management METU SOLUTION STEPS STEP 10: Assign resources to the related activities Return to Gantt chart view

17 Project Completion Date: Project → Project Information → Statistics
CE Construction Engineering and Management METU SOLUTION STEPS STEP 11: Take reports Project Completion Date: Project → Project Information → Statistics

18 Schedule Outputs: Report → New Report → Table
CE Construction Engineering and Management METU SOLUTION STEPS STEP 11: Take reports Schedule Outputs: Report → New Report → Table

19 SOLUTION STEPS STEP 11: Take reports Outline Level → All Subtasks
CE Construction Engineering and Management METU SOLUTION STEPS STEP 11: Take reports Outline Level → All Subtasks Select Fields → Choose necessary data

20 SOLUTION STEPS STEP 11: Take reports
CE Construction Engineering and Management METU SOLUTION STEPS STEP 11: Take reports Resource Graph: Resource Graph View → Print (or Print Screen) Scroll mouse or use keyboard arrows to see resource graph of each resource


Download ppt "CE 332 – Construction Engineering and Management"