Download presentation
Presentation is loading. Please wait.
1
SPL RF coupler: integration aspects
V.Parma, TE-MSC with contributions from WG3 members: Th.Renaglia, U.Wagner, P.Coelho, N.Bourcey, A.Vandecraen Review of SPL coupler, CERN 16th-17th March 2010
2
β=1 cryo-module in SPL layout (drwg SPLLJL__0014)
3
Cryogenic scheme (under discussion)
4
Cavity/coupler assy Part of interest Double-walled-tube
5
Coupler integration functionalities (non-exhaustive list)
Functionality Requirement Comment RT/atm. to 2K/vacuum penetrations minimise static HL; leak-tight penetration (o-ring); mechanical decoupling from vacuum vessel (if not a support); - Optimise thermal design Isolation between coupler and beam vacua leak tight window vacuum gauge outside cryostat - Single ceramic window for HP RF Gas cooling of double-walled tube (5 K-300 K) cryostat feedthrough of cooling line: leak-tight avoid atm. moisture (T>dew point) - externally-mounted manual valves (presetting); - Heater for control (Ofelia’s talk) Coupler maintenance Maintenance-free No in-situ intervention Coupler as support (option under study) support/position cavities; coupler flange mechanically fixed to vacuum vessel; fix longitudinal position of cavities; mechanical support of thermal shield - impact of gas cooling on position (Ofelia’s talk); - Vacuum vessel as mechanical reference
6
Transversal position of cavities inside cryostat
BUDGET OF TOLERANCE (preliminary) Step Sub-step Tolerances (3σ) Total envelopes Cryo-module assembly Cavity and He vessel assembly ± 0.1 mm (TBD) Positioning of the cavity w.r.t. beam axis ± 0.5 mm Supporting system assembly ± 0.2 mm (TBD) Vacuum vessel construction Transport and handling (± 0.5 g any direction) N.A. Stability of the cavity w.r.t. beam axis ± 0.3 mm Testing/operation Vacuum pumping Cool-down RF tests Warm-up Thermal cycles
7
Possible supporting schemes
“standard” supporting scheme RF coupler Invar longitudinal positioner Inertia beam Fixed support Sliding support External supports (jacks)
8
Possible supporting schemes
“standard” supporting scheme RF coupler Invar longitudinal positioner Inertia beam Fixed support Sliding support External supports (jacks)
9
Possible supporting schemes
Coupler supporting scheme RF coupler + longitudinal positioner + vertical support Intercavity support structure External supports (jacks)
10
Coupler position: top ...? Contras:
Interferes with bi-phase tube move sideways Waveguides/coupler more exposed to personnel/handling (damage, breaking window?) Pros: Easier connection of waveguides Easier access (needed?)
11
Coupler position: ...or bottom?
Contras: Space needs for waveguides under cryostat If coupler not a support (bellows) support on top, i.e. centered tube not possible Pros: Centered bi-phase tube symmetry Waveguides/coupler protected
12
RF coupler assembly constraints
Defines minimum diameter of “pipeline” type vessel: Lenght of double-walled tube Integration of thermal shield Note: drwgs for information only (concept not final)
13
Mid plane symmetry
14
Need guiding? Layout Equivalent sketch No - If sag small enough
- If strenght OK - isostatic l Yes - couple cavities - hyperstatic inter-cavity guides 2l mid cavities most critical: sag reduces only to ½
15
Mass loads on internal supports (preliminary)
Description Load Comment Cavity/he vessel/tuner ~2.0 kN per assembly (x 8 per cryomodule) Piping/thermal shield/MLI 0.8 kN equally shared on coupler tube Transport accelerations ± 0.5 g each direction
16
Max sag: “to guide or not to guide?”
Stiffening of coupler/cavity assembly necessary Guiding between cavities is most probably necessary
17
“standard” supporting
Max. sag minimized at a/L=0.20. A 3rd central support seems mandatory
18
comparing solutions A) Coupler supporting scheme
B) “standard” supporting scheme Pros Contras Design simplicity Vacuum vessel: Stiffness (thickness, stiffeners) Dim. stability Precision machining Cost Single cavity adjustment at assy Positioning stability (thermal, weld relieving...) Inter-cavity guiding Mid cavities guiding sufficient? Pros Contras Cavities mechanical isolation from external perturbations: dim. changes (thermal, weld relieving), vibrations... Design complexity Vacuum vessel simplicity: Reduced machining precision reduced thickness Central support needed (?) Complex cavity adjustment at assy
19
Summary Coupler length (double-walled tube) sets minimum diameter of cryo-module Coupler could be used as cavity support and is an interesting option Vacuum vessel become of paramount importance for mechanical positioning/stability Guiding between cavities probably needed (relieve cantilever) In case of “standard” supporting solutions, coupler design considerations still valid mechanical decoupling with bellows
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.