1 The Republic of the Union of Myanmar Ministry of Electric Power
Electricity Supply Enterprise Kachin State Office Priorities and Detailed Description of Electrification Plan For Kachin State Date -21.Oct.2015

2 Priority Electrification Project List for Kachin State
National Electrificatiion Plan all real excitied in Kachin State. There are (132) Villages which are within 2 Miles From the Exciting Line and are needed to implement for Electrification from National Electrification Plan Project; In Fiscal year (13) villages from Fund of Kachin State Government and In fiscal year (112) villages are also from Fund of Kachin State Government . Electrification are now Implementing Only ( 7) villages are Left. So; As these ( 7) villages are intend to implement With the fund of 2016 – 2017 Fiscal year by Capital Fund of Kachin State Government . Now a day ; some of Substation are fully load. So 66kV & 33 kV Substation are needed to be promoted to higher Capacity and to be Implement new substation at the Load center of each District .

3 Present Location Map of Kachin State

4 List of Electrificied Villages from the National Grid in Kachin State
Sr No District Township No; Villages No; House Hold No ; Population Electrificied Villages Remark 1 Myitkyinar 44 8778 53296 28 2 Winemaw 99 11676 70053 43 Myitkyinar District 143 20454 123349 71 3 Moehnyin 117 21138 119053 90 4 Hopin 27 4599 26226 23 5 Moegaung 73 19354 114139 Kaming 7 2508 14498 Moehnyin District 224 47599 273916 186 6 Bamaw 77 12119 67721 31 Shwegu 7280 55884 30 8 Moemauk 106 7021 37638 59 9 Mansi 234 12190 68969 13 Bamaw District 516 38610 230212 133 Kachin State 883 106663 627477 390

5 Present Location Map of Myitkyinar District
Myitykyinar Town ship No. of Villages Nos Household Population Electrified Villages - 28 Winemaw Town ship No. of Villages Nos Household Population Electrified Villages

6 Present Location Map of Moehnyin District
Moehnyin Town ship No. of Villages Nos Household Population Electrified Villages - 90 Hopin Town ship No. of Villages Nos Household Population Electrified Villages - 23 Moegaung Town ship No. of Villages Nos Household Population Electrified Villages - 71 Kamaing Town ship No. of Villages Nos Household Population Electrified Villages - 2

7 Present Location Map of Bahmaw District
Bamaw Town ship No. of Villages Nos Household Population Electrified Villages - 31 ShweguTown ship No. of Villages Nos Household Population Electrified Villages - 30 Moemauk Town ship No. of Villages Nos Household Population Electrified Villages - 59 Mansi Town ship No. of Villages Nos Household Population Electrified Villages - 13

8 66/33/11kV substation and HV ;MV line for Kachin State
The additional electrification statement due to Extention and upgrading 66/33/11kV substation and HV ;MV line for Kachin State Ser ial Township To be constructed The effective area( within 10 Miles effctive Area) Estimated cost (million kyats) Remark Substation 66kV line (mile) 33kV line (mile) Total villages Household population Material Installation 1 Mohnyin 66/11kV 10 MVA - 16 2120 11442 351 11 362 Replacement ( 5 to 10 MVA) 2 Moegaung 27 2749 13425 41.5 Upgrate ( ) MVA 3 Shwegu 5 MVA 9 1012 4350 120 131 ( 3 to 5 MVA) 4 Bahmaw(Sin Khan) 0.6 10 1759 7823 174.08 Extention 5 Mohnyin(Mawhan) 8 2292 13084 6 Waimaw 3260 17358 171.44 7 Mohnyin(Nyaungbin) 33/11kV 3 MVA 1466 9306 610 134.46 744.46 1.2 94 14658 76788 717.56 Remark – 66/11 kV ; 5 MVA X’mer of Moehnyin Substation is intend to reuse for Mawhan Substation

9 Electrification & Implementation plan of kachin State

10 Electrification Plan for Kachin State
Within 2 Miles From Existing 11kV Distribution Line No Township Name of Village To be Electrified No of House House hold Popu lation To be constructed ( withiin 2 Miles Effctive Arae) Estimated cost (Mil Kyates)  Task by regional Cost for 11 kV Line 11/0.4 kV Transformer 400 V Lines (Miles) Estimat ed Cost (Mil Kyats) mile Material Purchase Transp ort Cost Constr uction Total KVA Transport Costl Construction Cost 1 Shwegu Pu Khaing 66 334 2 47.82 4.0 7.66 59.476 160 13.244 0.5 0.8 14.544 74.02 1.5 Moemauk Lon jar 44 212 0.4 9.56 1.53 50 9.803 11.103 45.389 3 Dotphon yann Naungpaing 22 118 23.908 2.0 3.830 29.738 40.841 4 Chiphwe Nann Owe 6 31 0.2 9,0788 5 Narmawzoupt 16 109 Lae law 14 74 11.95 1.0 1.92 14.869 25,972 7 Aww Chate 8 0.3 13.617 176 928 6.9 164.96 10.2 26.43 460 72.06 3.5 5.6 81.162 10

11 Electrification Plan for Villages of Bamaw District
(Within 2 miles from Existing 11 kV Distribution Line) Dotphonyann Town ship No. of Villages Nos Household Estimated Cost (mil kyats) Naung Pain ShweguTown ship No. of Villages Nos Household Estimated Cost (mil kyats) MoemaukTown ship No. of Villages Nos House hold Estimated Cost (mil kyats) Lone Jar Pu Khai

12 Electrification Plan for Villages of Myitkyinar District
(Within 2 miles from Existing 11 kV Distribution Line) ChiphweTown ship No. of Villages Nos Household Estimated Cost (mil kyats) Chiphwe Lae law Naa Owe Aww Chate Narmaw Zoupt Chiphwenge Hydro Power Plant ( 99 MW x 4)

13 The Statement of Fiscal Yearly Budjet and Electrified Connection for Kachin State
Sr, No Fiscal Year State Capital Budget for ESE (mil Kyats) State Capital Budget for DRD (mil Kyats) Electrified Connection On Grid Off Grid Total Cost for 11kV Line & 11/0.4 Tr Total Cost for 400V Line Total Village (Nos) Consumer (Nos) 1 Estimate (BE+RE) 1172 171 16587 77 5860 2 Estimate (BE+RE) 1641.2 140 13320 206 11330 3 Budget Estimate (BE) - 60 5580 21 1785 Grand Total 2813.2 371 35487 304 18975

14 Main Materials List Transported to Bahmo District Office,kachin State
( 3 Villages within 2 mile from exciting 11 kV Line) Sr No Description Unit Quantities Transported Site 1 11/0.4 kV ,100 kVA Transformer 3 Bamow District , PMO Office 2. 10 meter Concrete Pole ( Transformer + Line) 159 Disconnecting Switch;Lightening Arresstor and Drop Out Fuse Set 4 ASCR 95 sqmm Ton 7.82 5 Disc Insulator with Tension Fitting 102 6 Pin Insulator with Spindle 459 7 Other Line Materials( Channel, Angle,Clamp ; etc)

15 ( 4 Villages within 2 mile from exciting 11 kV Line
Main Materials List Transported to Myitkyinar District Office, Kachin State ( 4 Villages within 2 mile from exciting 11 kV Line Sr No Description Unit Quantities Transported Site 1 11/0.4 kV ,100 kVA Transformer 4 Myitkyinar District , PMO Office 2. 10 meter Concrete Pole ( Transformer + Line) 166 3 Disconnecting Switch;Lightening Arresstor andDrop Out Fuse Set ASCR 95 sqmm Ton 8.05 5 Disc Insulator with Tension Fitting 105 6 Pin Insulator with Spindle 473 7 Other Line Materials( Channel, Angle,Clamp ; etc)

16 THANK YOU