Download presentation
Presentation is loading. Please wait.
Published byAdrian King Modified over 6 years ago
1
Anthony Alvarado, PE, CFM National Hydraulic Engineering Conference
Highways in Steep Canyons: SRH-2D Modeling and GIS-Automated Revetment Design John Hunt, PE Anthony Alvarado, PE, CFM Will DeRosset, PE Brian Varrella, PE, CFM National Hydraulic Engineering Conference Portland, Oregon August 2016
2
Overview US 34 through Big Thompson Canyon Introduction and Background
Hydraulic Analysis using SRH-2D Road Embankment Stability Design Scour Evaluation in Support of Design Summary of Findings
3
Big Thompson Watershed
78 mile long river with over 6,600 feet of fall 832 square mile watershed Starts in Rocky Mountain National Park Flows through Estes Park, Big Thompson Canyon, and Loveland
4
Flood of September 2013 Large frontal system, extended period of steady rainfall Generally lower peak discharge rates than previous flood of record (half as much as flood) Much longer duration of high flows than 1976 Peak flow roughly equal to 100-year flood in many locations Q2013 = 15,500 cfs vs Q100=15,449 cfs
5
September 2013 Big Thompson Flood Damage
6
US 34 Permanent Repair - Hydraulic Design Challenges
100-year design flood Floodway compliance Road Embankment Stability Access Bridges US 34 Bridges
7
Achieving Required Road Embankment Stability
Challenges Steep longitudinal profile of river Combined with high flood discharges Leads to extreme velocities and shear stresses Large boulders were transported by the flood in some reaches 4-ft D50 riprap was removed from wall toes Slope range 1.5% to 5%
8
Extreme Erosive Power of a Canyon Flood
9
Embankment Stability Design
Design Concepts Shift the road onto bedrock Used only in limited locations due to high cost Walls or other vertical treatments Where encroachment into floodplain is constrained Armor the embankment slope Primary treatment used
10
Extent of Design-Level 2D Modeling
Roughly 8 miles of detailed SRH-2D model Drake The Narrows Total extent of design-level modeling = 8 miles Divided into many segments for run time concerns
11
Design Use of Model Results
Riprap sizing for embankment protection Scour evaluation for toe depth of revetment Stability impacts of access bridge designs Opposite bank stability impact assessment
12
Sample of Model Results
13
Sample of Model Results
14
Calculating Required Size of Loose Riprap
Contours of Required Riprap D50 from SMS Data Calculator Red = 4 ft D50 Yellow = 3 ft D50 HEC-23 Design Guide 4 Eqn 4.1 Green = 2 ft D50 Blue = 1 ft D50 or less
15
Embankment Stability Design Loose Riprap
16
Embankment Stability Design Lift-Placed Matrix Riprap
17
Determining Toe Depth Requirements
Contraction scour Bendway scour Wall scour Never less than 5 feet below channel thalweg Bedrock considerations
18
Scour Calculations Semi-Automated with GIS
Using ArcView ModelMaker Import solution shape files from SMS 2-D Water surface elevation Depth Velocity Use ModelMaker to develop properties across XSEC lines Discharge Hydraulic Depth Average Water Surface Average Velocity
19
Contraction Scour Automation
HEC-18 Live-Bed Contraction Scour Equation (Eqn. 6.2)
20
Bendway Scour Automation
HEC-23 Scour at Protected Bendways (Eq. 4.5)
21
Summary of Findings River canyon environments pose major stability threat to parallel highways Steep longitudinal slopes lead to extreme flood velocities and shear stresses Two-dimensional modeling is justified Innovative embankment protection methods are needed Long canyons call for automation within SMS and GIS
22
Manager-River Engineering National Hydraulic Engineering Conference
THANK YOU ! John Hunt, PE Manager-River Engineering (mobile) National Hydraulic Engineering Conference Portland, Oregon August 2016
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.