1 GC Startup

2 H2 Generator Startup Front Back 2 4 Power up generator
Press the “Start” button on the front panel Once 90 PSI is reached for Actual Press the “Open” button

3 Compressed Air Input valve
Turned on compressed air supply and adjust to 120 to 150 psi (not shown) Turn on air dryer (plug in or turn on switch / not shown) Open input valve Allow system to equilibrate for 10 minutes

4 Compressed Air Output valve Regulator Post-Dryer valve
Open Post-Dryer valve Adjust regulator to 90 PSI Open output valve

5 Power on GC Turn on Power Switch

6 Power on GC Click on “Log In” Click on “FID”

7 Power on GC Click on “Ignite”
You should hear a small pop from the top of the GC. The Set and Actual should be the same when the FID is running.