Presentation is loading. Please wait.

Presentation is loading. Please wait.

Middlebelt Transport and Storage Tunnel (MTST) Project

Similar presentations


Presentation on theme: "Middlebelt Transport and Storage Tunnel (MTST) Project"— Presentation transcript:

1 Middlebelt Transport and Storage Tunnel (MTST) Project
July 25, 2016 Middlebelt Transport and Storage Tunnel (MTST) Project Progress Summary Presented By: Jim Nash, Water Resources Commissioner Joel Brown, PE, Project Engineer Evergreen-Farmington Sewage Disposal System Office of the Oakland County Water Resources Commissioner

2 Introduction Project Purpose and Overview Completed Work Current Work
Middlebelt Road Traffic Impacts Residential Well Impact Status Remaining Work Remaining Construction Schedule

3 Project Purpose and Overview

4 Project Overview Participants
Owner: Participating Communities: Engineer: Contractor:

5 Project Overview Project Purpose-Reduce SSOs

6 Project Overview Project Purpose
Sewer System Upgrades Required to Comply with Michigan Department of Environmental Quality SSO Regulations (Reduce SSOs) Data Collection, Modeling, LTCAP Developed 2004 WRC and communities enter ACO with the MDEQ Middlebelt Transport and Storage Tunnel

7 Project Overview Evergreen – Farmington Sewage Disposal System
Hills Farmington

8 Project Overview MTST Location
9-foot Dia. MTST Diversion Chambers Farmington Hills Farmington

9 Project Overview Diversion Chamber Function-Dry Weather Flow
Existing Farmington Interceptor Middlebelt Tunnel

10 Project Overview Diversion Chamber Function-Wet Weather Flow
Existing Farmington Interceptor Middlebelt Tunnel

11 Project Overview Original MTST Route-Plan View
Recovery Shaft Manhole TS-5 & DC-2 Flow Manhole TS-4 Manhole TS-3 Manhole TS-2 & DC-1 Existing Farmington Interceptor Existing 18-inch Sanitary Sewer TS-1 Launch Shaft

12 Project Overview Original MTST Route-Profile View
Manhole TS-5 & DC-2 Manhole TS-4 Manhole TS-3 90 feet deep Manhole TS-2 & DC-1 TS-1 Farmington Interceptor 15-20 feet deep 9 feet Middlebelt Transport and Storage Tunnel 7,566 feet long under Middlebelt Road from I-696 north to 13 Mile Road

13 Project Overview Revised MTST Route-Plan View
Recovery Shaft TS-5A & DC-2 Flow Manhole TS-4 at Utley Street Manhole TS-2 & DC-1 Dewatering Location Existing Farmington Interceptor Existing 18-inch Sanitary Sewer Launch Shaft TS-1

14 Project Overview Revised MTST Route-Profile View
Recovery Shaft TS-5A & DC-2 Manhole TS-4 80 feet deep Manhole TS-2 & DC-1 TS-1 Farmington Interceptor 15-20 feet deep 9 feet Middlebelt Transport and Storage Tunnel 5,930 feet long under Middlebelt Road from I-696 north to Chenwood Ct.

15 Middlebelt Tunnel Revised Alignment
*Performing Additional Projects to Maintain Hydraulic Equivalent

16 Completed Work

17 TS-1 Lauching Shaft TS-1 Shaft Complete July 2015

18 Tunnel Boring Machine (TBM) Assembly

19 TBM Launch

20 Muck Operations Mining to TS-5A Complete on June 10, 2016

21 Primary Liner Installation

22 Current Work

23 TS-5A Recovery Shaft Installation

24 DC-2 Shaft

25 Middlebelt Traffic Impacts

26 No through access on Middlebelt
Middlebelt Closures X TS-5A and DC-2 construction February 2016 through November 2016 Local access only closure Road closure signs notify of police enforcement Chenwood Ct. No through access on Middlebelt X Road closure Wellington St. X X Middlebelt Rd.

27 Middlebelt Road Traffic Controls
In the process of devising additional traffic control devices to further limit cut-through traffic around hard closure.

28 Residential Well Impact Status

29 Residential Well Impact Status
Dewatering with four pumping wells southwest of 12 Mile and Middlebelt Level dropped close to 55 feet below ground surface Currently 0 no-water situations Stress we have all contractors on board for rapid response to address any water issue. Working with our insurance agent to cover unforeseen impact costs.

30 Remaining Work

31 Hobas Pipe Installation

32 Manhole Structures TS-2 and TS-4

33 Remaining Construction Schedule

34 Remaining Construction Schedule

35 Questions


Download ppt "Middlebelt Transport and Storage Tunnel (MTST) Project"

Similar presentations


Ads by Google