Download presentation
Presentation is loading. Please wait.
Published byMyrtle Simmons Modified over 6 years ago
1
Middlebelt Transport and Storage Tunnel (MTST) Project
July 25, 2016 Middlebelt Transport and Storage Tunnel (MTST) Project Progress Summary Presented By: Jim Nash, Water Resources Commissioner Joel Brown, PE, Project Engineer Evergreen-Farmington Sewage Disposal System Office of the Oakland County Water Resources Commissioner
2
Introduction Project Purpose and Overview Completed Work Current Work
Middlebelt Road Traffic Impacts Residential Well Impact Status Remaining Work Remaining Construction Schedule
3
Project Purpose and Overview
4
Project Overview Participants
Owner: Participating Communities: Engineer: Contractor:
5
Project Overview Project Purpose-Reduce SSOs
6
Project Overview Project Purpose
Sewer System Upgrades Required to Comply with Michigan Department of Environmental Quality SSO Regulations (Reduce SSOs) Data Collection, Modeling, LTCAP Developed 2004 WRC and communities enter ACO with the MDEQ Middlebelt Transport and Storage Tunnel
7
Project Overview Evergreen – Farmington Sewage Disposal System
Hills Farmington
8
Project Overview MTST Location
9-foot Dia. MTST Diversion Chambers Farmington Hills Farmington
9
Project Overview Diversion Chamber Function-Dry Weather Flow
Existing Farmington Interceptor Middlebelt Tunnel
10
Project Overview Diversion Chamber Function-Wet Weather Flow
Existing Farmington Interceptor Middlebelt Tunnel
11
Project Overview Original MTST Route-Plan View
Recovery Shaft Manhole TS-5 & DC-2 Flow Manhole TS-4 Manhole TS-3 Manhole TS-2 & DC-1 Existing Farmington Interceptor Existing 18-inch Sanitary Sewer TS-1 Launch Shaft
12
Project Overview Original MTST Route-Profile View
Manhole TS-5 & DC-2 Manhole TS-4 Manhole TS-3 90 feet deep Manhole TS-2 & DC-1 TS-1 Farmington Interceptor 15-20 feet deep 9 feet Middlebelt Transport and Storage Tunnel 7,566 feet long under Middlebelt Road from I-696 north to 13 Mile Road
13
Project Overview Revised MTST Route-Plan View
Recovery Shaft TS-5A & DC-2 Flow Manhole TS-4 at Utley Street Manhole TS-2 & DC-1 Dewatering Location Existing Farmington Interceptor Existing 18-inch Sanitary Sewer Launch Shaft TS-1
14
Project Overview Revised MTST Route-Profile View
Recovery Shaft TS-5A & DC-2 Manhole TS-4 80 feet deep Manhole TS-2 & DC-1 TS-1 Farmington Interceptor 15-20 feet deep 9 feet Middlebelt Transport and Storage Tunnel 5,930 feet long under Middlebelt Road from I-696 north to Chenwood Ct.
15
Middlebelt Tunnel Revised Alignment
*Performing Additional Projects to Maintain Hydraulic Equivalent
16
Completed Work
17
TS-1 Lauching Shaft TS-1 Shaft Complete July 2015
18
Tunnel Boring Machine (TBM) Assembly
19
TBM Launch
20
Muck Operations Mining to TS-5A Complete on June 10, 2016
21
Primary Liner Installation
22
Current Work
23
TS-5A Recovery Shaft Installation
24
DC-2 Shaft
25
Middlebelt Traffic Impacts
26
No through access on Middlebelt
Middlebelt Closures X TS-5A and DC-2 construction February 2016 through November 2016 Local access only closure Road closure signs notify of police enforcement Chenwood Ct. No through access on Middlebelt X Road closure Wellington St. X X Middlebelt Rd.
27
Middlebelt Road Traffic Controls
In the process of devising additional traffic control devices to further limit cut-through traffic around hard closure.
28
Residential Well Impact Status
29
Residential Well Impact Status
Dewatering with four pumping wells southwest of 12 Mile and Middlebelt Level dropped close to 55 feet below ground surface Currently 0 no-water situations Stress we have all contractors on board for rapid response to address any water issue. Working with our insurance agent to cover unforeseen impact costs.
30
Remaining Work
31
Hobas Pipe Installation
32
Manhole Structures TS-2 and TS-4
33
Remaining Construction Schedule
34
Remaining Construction Schedule
35
Questions
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.