1 Interstate 15 North Phase 4 Cost Risk Assessment 9/03/2015

2 Background: I-15 North Environmental Document, Purpose & Project Elements
I-15 North Environmental Assessment –FONSI issued May 2007 Purpose: Improve Safety, Operations & Access Decrease Congestion Reduce Travel Times Accommodate Projected Traffic Elements Increase Capacity Interchange and ramp improvements Freeway Management System Planning/NEPA/PE cost to date $ 8 million includes all phases except some of Phase 1 (Design Build) Design Cost

3 Background: I – 15 North Phase 1 (Constructed)
Widened I-15 to ten lanes from US 95 (Spaghetti Bowl) to Lake Mead Widened I-15 to eight lanes from Lake Mead Boulevard to Craig Road Reconfigured Lake Mead Interchange – realignment of the on-ramps and off-ramps Added Auxiliary Lanes Completed 2010, $ 270 million Cost to Construct via Design Build (DB). The DB Project included DB design cost as well as construction costs

4 Background: I-15 North Phase 2 (Package A & B)
Package A to advertise in Federal Fiscal Year (FFY) The estimated cost to construct is between $ 38.7 to $ 40.2 million Design Bid Build. Includes: Widen I-15 from 4 to 6 lanes for 4.8 miles Add Aux. Lanes between interchanges Restore pavement condition Widen & Seismic Retrofit 4 Bridges over the UPRR Landscape and Aesthetic Improvements Package B -ITS completed construction in 12/2013 at a cost $ M

5 Background: I-15 North Phase 3
Project Design to resume 2016 Construction Packaging to be determined Cost of Construction estimated to be between $ 75- $ 85 M First Construction Package to Advertise FFY 2019 Project elements Widen I-15 from 4 to 6 lanes (4.6 miles) Possible new interchange between Speedway and Apex Restore pavement condition Landscape and Aesthetic Improvements

6 Overview: I-15 North Phase 4
Improve I-15 and CC 215 Beltway System to System Interchange Two concepts under consideration (Three level & Two level) Improve freeway safety and operations, and local connectivity by providing a new interchange Construction Packaging To be determined by March 2016 First Construction Package FFY 2018 Cost of Construction estimated to be between $ $ M

7 I-15 North Phase 4 – Site Review

8 I-15 North Phase 4 – Site Review

9 I-15 North Phase 4 – Site Review

10 I-15 North Phase 4 – Site Review

11 I-15 North Phase 4 – Previous CRA
Cost Risk Assessment on 9/15/14 Looked at previous 3-Level alternative Key Project Schedule Risks Utility Relocations Preliminary engineering/scoping takes longer than expected Delay to start of preliminary engineering scoping Deep Foundations Other large events in the area Key Project Cost Risks Addition ROW may be required to provide 12’ wide maintenance access along EB CC 215 to SB I- 15 ramp Differing site conditions caliche UPRR coordination delays construction start

12 I-15 North Phase 4 – Previous CRA
Cost Risk Assessment on 9/15/14 Cost and Schedule Base Cost - $ M, Pre-Response 70th percentile - $ M, Post-Response 70th percentile - $ M, Project Cost Range - $ M to M Base Completion Date – Dec 2021, Pre-Response 70th percentile – Apr 2023, Post-Response 70th – Dec 2022, Project Completion Date Range - May 2022 to May 2023

13 I-15 North Phase 4 – Crash History

14 I-15 North Phase 4 – Local Access

15 I-15 North Phase 4 – Utilities

16 I-15 North Phase 4 – Utilities

17 I-15 North Phase 4 – Drainage Existing

18 I-15 North Phase 4 – Drainage Future Conditions

19 I-15 North Phase 4 – Bridges

20 I-15 North Phase 4 – Structures
Existing Structures G-961S and G-961N (cast in place box girder structures) will be widened in Phase 2 and it is not presently anticipated that they will need to be widened again in Phase 4. However, there is sufficient width between the two bridges for additional capacity (HOV lanes). G-961R (ES2) (cast in place post tensioned box) widening proposed both alternatives, there are no factor that would preclude the use of the same structure at this location. I-2499 (TP) (cast in place post tensioned box girder) and it’s present width would accommodate one addition lane. Widening proposed in both alternatives, there are no known factors that would preclude the use of the same structure type. G2568E and G2568W (post tensioned box girder structures). The width of these structures will accommodate an additional lane in each direction. Widening of G2568W (UP1) is proposed as part of the Phase 4 project Existing Box Culverts Local drainage throughout the area of the proposed interchange is accomplished by several large box culverts. The proposed configuration of the interchange may create the need to lengthen some of the culverts and/or provide new ones Proposed Bridges The possibility of large flyover ramp structures is anticipated to complete the system interchange in both alternatives. Due to the required geometric curvature, structures of this type are most often constructed with steel plate girders. The use of cast-in-place concrete box girders is a possibility; however, the difficulty of providing the needed falsework is generally prohibitive. At the other bridge locations, there are no identifiable conditions that would preclude the use of post-tensioned, cast-in-place concrete box girder bridges, which are NDOT’s preferred structure type

21 I-15 North Phase 4 – Pavement
I -15 Pavement The I-15 North Phase 2 – Is adding lanes and resurfacing the I-15 pavement Mill and Overlay with 3” Plantmix Bituminous & ¾” PB Open-Grade Widening and replacement areas - 10” Plantmix Bituminous & ¾” PB Open-Grade with 16” Type 1 Class B Aggregate Base CC 215 Pavement Most of the facilities on CC 215 will be removed and replaced due to realignment Main Beltway was constructed with 11” PCCP Range Road and directional ramps Plantmix Bituminous Surfacing – Typically 6”

22 I-15 North Phase 4 – Geotechnical
Native soils Surface fill - Sands & gravels of varying depths (1’ to 4’). Removal, testing, and re-compaction (if suitable) Native clay soils have low to high expansion potential. Highly expansive soils should be removed and replaced Caliche Significant layers of moderately hard caliche were encountered in some borings The summaries of caliche indicate a few thin layers near the surface with thickness of one to two feet Deeper layers, 30 to 100 feet deep, varied greatly in thickness Rock excavation & heavy duty excavation excavation/ripping techniques should be anticipated in areas with appreciable grading or relatively deep excavations High Sulfate content Sulfate resistant cement is recommended Corrosion reduction methods should be implemented for buried pipes Ground Water not reported on any of the boring logs with depths up to 100’ No know fissures or faults in immediate vicinity of the project Spread footings and drilled shaft foundations are generally found to be suitable

23 I-15 North Phase 4 – Landscape Architecture
General North Las Vegas Community Gateway as per the I-15 Landscape and Architecture Corridor Plan Up to 3% of overall construction budget for landscape and aesthetics Landscape – Dynamic Desert Metropolis Plants need to be drought tolerant with a cold hardy factor as low as 20 degrees F Landscape Materials – plant material from Mojave Desert , Sonoran Region and other dry land environments Aesthetics Bridge treatments, wall aesthetics, sculptural elements and color spectrums designed to be unique but unified with I-15 Corridor Master Plan

24 I-15 North Phase 4 – Environmental
General Environmental Assessment (EA) in May 2007 for the I-15 Improvements, US- 95 to Apex (FHWA-NV-EA 06-01) concluded with a Finding of No Significant Impact (FONSI) Reevaluation Generally required when there has been a time lag or changes Changes to: Project scope or concept Study area conditions Regulatory requirements Local priorities NDOT has implemented a series of questions & established a template to prepare a written reevaluation of a NEPA document Why? - Any design alternative developed resulting in improvements to areas outside the 2007 right-of-way or that may result in impacts not studied in the 2007 EA may require a written reevaluation

25 I-15 North Phase 4 – Alternatives
Alternatives - # 1(3-Level) & # 2(2-Level) Alternative #1 Preliminary Cost Estimate - $ 140 Million Alternative # 2 Preliminary Cost Estimate - $ 126 Million Design is at conceptual level for both alternatives Common Assumptions Tropical Parkway Connector will be constructed Range Road is not a thru Street; access is restricted within the National Guard property Centennial Parkway will be extended to Speedway

26 I-15 North Phase 4 – Alternative 1

27 I-15 North Phase 4 – Alternative 1 2035 Traffic Forecasts

28 I-15 North Phase 4 – Alternative 1 Structures

29 I-15 North Phase 4 – Alternative 1 Structures

30 I-15 North Phase 4 – Alternative 1
Advantages Minimal utilities relocation Some utilization of existing roadways Some ROW acquisition & construction could be deferred until Centennial Pkwy is constructed Disadvantages Higher cost of bridges, embankments & walls due to 3-level configuration Multiple heavy turning movements & diversion of Centennial traffic onto Range

31 I-15 North Phase 4 – Alternative 2

32 I-15 North Phase 4 – Alternative 2 2035 Traffic Forecasts

33 I-15 North Phase 4 – Alternative 2 Structures

34 I-15 North Phase 4 – Alternative 2 Structures

35 I-15 North Phase 4 – Alternative 2
Advantages Lower cost of bridges, embankments & walls due to 2-level configuration Straight alignment of Centennial without heavy turning movements Stakeholders support Centennial being favored Disadvantages Utilities relocation cost at Range Road to accommodate bridge foundations ROW acquisition cost for Range Rd relocation & Tropical Pkwy Extension

36 I-15 North Phase 4 – Right of Way Existing

37 I-15 North Phase 4 – Right of Way Alternative 1

38 I-15 North Phase 4 – Right of Way Alternative 2

39 I-15 North Phase 4 – Right of Way Summary
Alternative 1 Bureau of Land Management (BLM) – SF State of Nevada (National Guard) – SF Private Property – SF Alternative 2 Bureau of Land Management (BLM) – 444 SF State of Nevada (National Guard) – 8881 SF Private Property – SF

40 I-15 North Phase 4 – Other Projects
Sheep Mountain Parkway CLV, in cooperation with the CNLV, NDOT, and RTC, has proposed the preservation of a corridor for future development of this multimodal transportation facility. The proposed 22-mile-long corridor, located to the north of CC215 in the northern Las Vegas Valley Presently, it is not anticipated that this facility will be warranted until the 2040 – 2050 horizon years.

41 I-15 North Phase 4 – Other Projects
I-11 and Intermountain West Corridor Study I-11 and Intermountain West Corridor Study Is envisioned to be a continuous high-capacity trade corridor extending from Nogales, Arizona to Las Vegas and potentially on towards Canada Alternatives include a south-west route utilizing the I-215 Bruce Woodbury Beltway, a central route utilizing US 95, and an east-north route utilizing I-15, CC215, and a new alignment to be determined to the east of the valley If the east-north route alternative, is determined to be the preferred route, this would redistribute traffic and add a significant new component through the I- 15/CC215 interchange

42 I-15 North Phase 4 – Other Projects
I-11 and Intermountain West Corridor Study Is envisioned to be a continuous high-capacity trade corridor extending from Nogales, Arizona to Las Vegas and potentially on towards Canada Alternatives include a south-west route utilizing the I-215 Bruce Woodbury Beltway, a central route utilizing US 95, and an east-north route utilizing I-15, CC215, and a new alignment to be determined to the east of the valley If the east-north route alternative, is determined to be the preferred route, this would redistribute traffic and add a significant new component through the I- 15/CC215 interchange I-11 and Intermountain West Corridor Study Is envisioned to be a continuous high-capacity trade corridor extending from Nogales, Arizona to Las Vegas and potentially on towards Canada Alternatives include a south-west route utilizing the I-215 Bruce Woodbury Beltway, a central route utilizing US 95, and an east-north route utilizing I-15, CC215, and a new alignment to be determined to the east of the valley If the east-north route alternative, is determined to be the preferred route, this would redistribute traffic and add a significant new component through the I- 15/CC215 interchange

43 I-15 North Phase 4 – Issue Wall Costs vs Extending the length of the bridges Background: The conceptual plans, for both alternatives, show the layout of bridges and walls for the northbound I-15 ramp to westbound CC215 and Tropical Parkway.  Along this ramp there are two new bridge structures, one over UPRR and Range Road and the other over I-15.  Additionally, there are two retaining walls on the south side of the ramp.  The terrain in this area generally slopes downward from north to south and I-15 is on an embankment for its overcrossing of the UPRR and Range Road.  Because of the height of the I-15 embankment, the sloping terrain, drainage and right-of-way constraints, these retaining walls along the south side of the ramp are very tall, H max = 65'.  Wall costs are estimated to be $10.5 million. 

44 I-15 North Phase 4 – Issue

45 I-15 North Phase 4 – Phasing Plan
Goal: Break the Project into several stand-alone but operationally independent projects costing $40 – 60 million Phasing Plan will be developed following NDOT approval of the preferred alternative Delivery time frames (design and construction) will be based on operational need supported by Benefit-Cost Analysis

46 I-15 North Phase 4 – Phasing Plan
Sample Stage 1 Construct CC215 Bridges over Surface Streets Re-align Surface Streets & Ramps Construct/Widen Ramps NOTE: Green shading indicates completed work, active roadways

47 I-15 North Phase 4 – Phasing Plan
Sample Stage 2 Construct SW Ramp & Bridge Construct NW Flyover Ramp NOTE: Green shading indicates completed work, active roadways

48 I-15 North Phase 4 – Phasing Plan
Sample Stage 3 Construct EN Flyover Ramp NOTE: Green shading indicates completed work, active roadways

49 Project Contact & Questions?
NDOT Project Management Division: Assistant Chief – Lynnette Russell Phone – Project Manager – Dwayne Wilkinson Phone –