PAI Paris Gare de Lyon PrEsentation Of the PROJECT 20/06/2017
Technical organisation of the commissioning Dominique BERGÉ DIRECTION DES PROJETS FRANCILIENS
2
SUMMARY 01. Technical organisation of the commissioning
01.1. before commissioning 01.2 during commissioning 01.3. after commissioning
3
01. Technical Organisation of the commissioning
4
COMMISSIONING Organisation
STANDARD IN 3225 "Commissioning on safety installations“ Standard Its goal: to prepare and carry out commissioning under optimum conditions of efficiency and safety Preparing the commissioning operation: Cutting plan in elementary operations Safely: Implementation Plan for Regulatory Procedures Shared by all: Traffic operation and overhead lines operation, Train Operating Companies, maintainers, PROJECT team, …
5
COMMISSIONING Organisation
Commissioning working group: EIC, INFRAPOLE, ITIF, TSEE, DCF, EF, PRI, EALE, ESTI… Monthly meetings from september 2015 Definition of the test area Definition of the Detailed Timeline Follow-up of the Check List of the commission activities Specific Risk Analysis for Commissioning (Organisational, external, technical, post commissioning, fallback solutions, dysfunctions,…) Preparation from M-6 to D-14 Preparation from Y-1 COM. ASS D-14
6
01.1 COMMISSIONING ORGANISATION : BEFORE COMMISSIONING
7
COMMISSIONING Organisation
Before commissioning TEST AREA Determine a perimeter to be protected by S6 / S9 / S11 measures to ensure the safety of switching installation works and commissioning tests Ensure that the boundary of the ZEPs and their associated devices remain compatible with the tests to be carried out during the commissioning Define, in accordance with the operators and the TOCs, the track occupancy in the area, as well as the authorised movements requiring PS9E measures These documents must be known and shared by all the activities of the site Preparation from M-6 to D-14 Preparation from Y-1 COM. ASS D-14
8
COMMISSIONING Organisation
BEFORE COMMISSIONING COMMISSIONING TIMELINE Sequencing all procedure, switching installation and commissioning testing activities Dimension the number of agents (disciplines and accreditations) and the additional needs (radios, vehicles, ...) By geographical location for switching installation and testing activities List and quantify specialised mobile teams Organize team turnover taking into account HR constraints Preparation from Y-1 Preparation from M-6 to D-14 D-14 COM. ASS
9
COMMISSIONING Organisation
BEFORE COMMISSIONING CHECK-LIST OF ACTIVITIES OF THE COMMISSIONING: built on the experience of previous projects, enriched and shared within the projects: Editing the signalling notice Technical documentation: Signalling scheme plan, Control tables, as-built drawings, Regulations, Works contract,… Training Removal of installations: supply contracts, ... Preparation of work and switching installation sheets Preparation of commissioning tests sheets Resources: call for volunteers, team sizing, reinforcements (EIC, EALE, Contractors) ... Cleaning and maintenance: cleaning of pathways, deoxidation of rails,… Logistics for commissioning: reception, directory, catering, accommodation, transport,… Preparation of means of communication: radios, portables,… Security for the area access Communication : before, during and after the commissioning Preparation from M-6 to D-14 Preparation from Y-1 COM. ASS D-14
10
COMMISSIONING Organisation
BEFORE COMMISSIONING Trial run for the protection operations of the test area: Simulation of the protection procedures for the area (10 km of track, 2 hours of procedure, 15 operational signal boxes Repetition concerning the EIC / EF / MOET management for verifying the test area protection regulation Trial run for the test area closure operations: Reconnaissance of the closure locations by the staff (Pk, voie, …) Testing the means of communication Checks of material means (SAM, detonators, DSh, ...) Simulation of the closure implementation Checks of organization, duration and sequencing of operations Repetition of the commissioning for all agents: Presentation of the project, organisation of the commissioning, planning of assignment by agent, visit of the site of reception and intervention for each agent, provision of the worksheets for verification in order to detect any anomalies or Preparation from M-6 to D-14 Preparation from Y-1 COM. ASS D-14
11
01.2 Commissioning Organisation : DURING COMMISSIONING
12
COMMISSIONING Organisation
Commissioning sequence 18/03/17 19/03/17 20/03/17 Reception Closure EIC Technical closure Removal IS Switching works PLX, Ag, CdV Switching works and complementary markings (KVB, SAAT, …) Preliminary tests records Concordance tests and Functional tests End of closure S11 End of closure S9 Commissiong records S6/S9 Measures from 3h30 to 0h00 S11 Measures from 3h30 to 22h00 0h00 08h00 16h00 0h00 08h00 16h00 0h00 Internal / external communication: VIP, Media, Rooftop, ...
13
Commissioning Organisation
During Commissioning: OrganiSation of the general coordination Preparation from M-6 to D-14 Preparation from Y-1 COM. ASS D-14
14
01.3 COMMISSIONING Organisation : AFTER COMMISSIONING
15
COMMISSIONING Organisation
AFTER COMMISSIONING Transfer of the safety installations and removal of reservations identified before and during the commissioning Thermography: infrared camera detection of hot spots on all power supplies Airproof sealing of technical rooms (REX Denguin, efficiency of automatic fire suppression) Assistance after commissioning: Accompanying instructions for the Commissioning and the ASS (After Sale Services): Reinforcement EIC MISTRAL testers: diagnostic aid to distinguish malfunctions from faults or nominal situations (operation in dynamics of automatisms) Reinforcement Infrapôle : assistance to the fault clearance, mainly located in the SER 1 Contractors Reinforcements (ANSALDO, ATOS, SIEMA, TECHNILOG, …) Reinforcement IP-SYS and IP-SF, ISI Preparation from Y-1 Preparation from M-6 to D-14 D-14 ASS COM.
16
CHIFFRES Clés