TOTAL BRIDGE REPLACEMENT OF M-13 OVER CHEBOYGANING CREEK

Similar presentations


Presentation on theme: "TOTAL BRIDGE REPLACEMENT OF M-13 OVER CHEBOYGANING CREEK"— Presentation transcript:

1 TOTAL BRIDGE REPLACEMENT OF M-13 OVER CHEBOYGANING CREEK
DANIEL BURNS, PAUL HEBERT, AND BLAKE NICHOLS DEPARTMENT OF CIVIL & CONSTRUCTION ENGINEERING WESTERN MICHIGAN UNIVERSITY

2 Overview Background & Location Construction Engineering Constraints
Preliminary Cost Estimate Quantity Takeoff Deliverables Schedule of Pay Items Structural Design Estimate of Cost Bridge Profile Construction Schedule Proposed Bridge Conclusions Design Software Sustainability Welded Steel Plate Girders Summary Prestressed Concrete Girders Further Recommendations Girder Material Evaluation Acknowledgements Deck & Railing Design Column Design Pier Cap Analysis Footing Analysis Abutment Analysis

3 Background & Location Portsmouth Township, Bay County
Rated POOR (4) or worse MDOT recommends total replacement

4 Constraints Full Road Closure Freeboard = 1’ minimum
Demolition and Construction = $5 million No Construction between April 1 and July 31

5 Deliverables Design Recommendations Structural Design Calculations
Design Drawings Schedule of Pay Items Estimate of Cost Construction Schedule

6 Structural Design

7 Bridge Profile 249’ 6” 61’ 90’ 61’ Existing Profile - 1927 310’ 95’
120’ 95’ Proposed Profile

8 Proposed Bridge Top View with Stations LEAP Concrete Rendering

9 Design Software Bentley LEAP Concrete & LEAP Steel Bridge Design Programs

10 Welded Steel Plate Girders
End Cross Section Mid Cross Section

11 Prestressed Concrete Girders

12 Girder Material Evaluation
Item Description Qty Unit Cost Total Cost Prestressed Concrete Design Prest Conc I Beam, Furn, 54 inch 1,846 ft $174.00 /ft $321,204 Prest Conc I Beam, Erect, 54 inch $21.38 $39,467 Total $360,671 Welded Steel Plate Design Structural Steel, Plate, Erect 882,838 lb $0.16 /lb $141,254 Structural Steel, Plate, Furn and Fab $1.31 $1,156,517 $1,297,771 Cost Service Life Sustainability Total Prestressed Concrete Design 1 3 Welded Steel Plate Design 2 6 *Lower is better

13 Deck & Railing Design MDOT Bridge Design Guide
Aesthetic Parapet Tube ( ) MDOT Bridge Design Guide Standard Bridge Slab ( )

14 Column Design Top View Side View

15 Pier Cap Analysis Rebar Layout Rebar Schedule

16 Pier Cap Analysis Span 3 Flexure Check Span 3 Fatigue Check

17 Footing Analysis 6’ 6’ Cross-Section 50’ 6’ Rebar Plan Shear Analysis

18 Abutment Analysis Profile Dimensions End Dimensions Rebar Plan

19 Abutment Analysis LEAP Moment Analysis Output

20 Construction Engineering

21 Preliminary Cost Estimate
Existing Bridge Deck 11,040 ft2 Proposed Bridge Deck 16,130 Item Description Unit Unit Rate Cost Bridge Removal $35.00 $386,413 Bridge Construction (River Crossing) $220.00 $3,548,554 Traffic Control (Detour Route) LS $75,000.00 $75,000 Sub Total $3,934,967 General Provisions Mobilization 5% of Total Cost $196,748 Miscellaneous Items Preliminary Cost of Project $4,328,464

22 Quantity Takeoff Concrete Rebar Epoxy Coated Rebar
Superstructure (Deck) 399.70 yd3 0.00 lb 25,742.10 Abutment A 77.40 2,010.70 Pier B Cap 23.20 2,220.60 Column 15.40 2,827.60 Foundation 66.70 2,960.80 Pier C 16.00 2,924.40 Abutment B Substructure 366.00 9,943.00 10,193.20

23 Schedule of Pay Items Item ID Item Description QTY Units 7060001
Bridge Ltg, Furnish and Remove 1 LS Bridge Ltg, Operate and Maintain 400 yd3 Concrete, Low Temperature Protection 766 Reinforcement, Steel 9943 lb Reinforcement, Steel, Epoxy Coated 35935 Substructure Concrete 366 Superstructure Concrete, Form, Finish, and Cure Superstructure Concrete, Form, Finish, and Cure, Night Casting Superstructure Concrete, Night Casting, Deck Prestressed Concrete I Beam, Furnish, 54 inch 1846 ft Prestressed Concrete I Beam, Erect, 54 inch Bridge Railing, Aesthetic Parapet Tube 620

24 Detailed Cost Estimate
Division 2016 Award Avg Award 2016 Low 3 Avg Low 3 01 General Provisions $420,000 02 Earthwork $882,765 $843,637 $901,186 $871,872 03 Bases $100,495 $111,813 $109,218 $118,137 04 Drainage Features $44,792 $42,726 $46,213 $44,486 05 HMA Pavements $7,858 $7,722 $8,039 $7,916 06 PCC Pavements $213,353 $206,497 $247,174 $242,533 07 Structures $1,889,712 $1,884,071 $1,992,858 $1,963,286 08 Incidental Construction $404,227 $391,924 $425,466 $417,043 09 Materials N/A TOTAL $3,963,202 $3,908,389 $4,150,154 $4,085,274

25 Construction Schedule
Begin August 1, 2017 Total Duration is 121 Days End January 23, 2018 Sitework (17 Days) Substructure (30 Days) Superstructure (46 Days)

26 Conclusions

27 Sustainability Girder Material Selection Construction Schedule
Service Life Maintenance Impact Construction Schedule DNR Restrictions Recycle Demolished Materials

28 Summary 3-Span, 310’ Bridge Prestressed Concrete Girders
Demolition & Construction = $4.2 million Construction Duration = 121 days

29 Further Recommendations
Traffic Impact Verification Pile Design Quantity Updates Demolition Planning

30 Acknowledgements MDOT Sponsor Advisor Senior Design Faculty
Dina Tarazi, PE Dr. Yufeng Hu, PE James Ranger, PE Senior Design Faculty Dr. Decker Hains, PE, PMP Timothy Schnell

31 Questions?

32 Item Production Rate QTY Duration Cofferdam Installation (Pier B) 2000 ft2/day 4576 sq ft 3 days Cofferdam Installation (Pier C) Cofferdam Excavation (Pier B) 200 yd3/day 883 cyd 5 Cofferdam Excavation (Pier C) Substructure Excavation (Abutment A) 1 unit/day units Pile (Abutment A) 10 piles/day 16 piles 2 Piles (Pier B) 12 Piles (Pier C) Piles (Abutment D) Pier B Construction days/unit Pier C Construction Abutment A Construction Abutment D Construction Girder Erection (Bay A-B) 6 girders/day 8 girders Girder Erection (Bay B-C) Girder Erection (Bay C-D) Bridge Deck - Form, Place Rebar 15 Bridge Deck - Pour days/span spans Bridge Deck - Cure 7 Structural Approach (Abutment A) Structural Approach (Abutment D) Parapet ft/day 620 feet 4 Barrier

33 Cofferdam Calculations
Cofferdam Height Above OHWM 1 foot Width of Existing Footing 8 feet Ordinary High Water Mark (OHWM) 581.61 Width of Proposed Footing 6 Riverbed Elevation 571 Center to Center Distance 15 Bottom of Footing 561.5 Work Space Width Length of Proposed Footing 50 Excavation Height = 9.5 Cofferdam Height = 22 Single Pier Surface Area to Retain = 4576 sq. ft. Width = 38 Length = 66 Single Pier Riverbed to Excavate = 883 cyd

34


Download ppt "TOTAL BRIDGE REPLACEMENT OF M-13 OVER CHEBOYGANING CREEK"