Project Planning: Scope and the Work Breakdown Structure
Chapter 5a
2
Project Planning Framework
Copyright 2012 John Wiley & Sons, Inc.
3
Introduction Scope – defines the work boundaries and deliverables of the project so what needs to get done, gets done – and only what needs to get done, gets done. is determined directly by the project’s MOV. Defines all the work, activities, and deliverables that the project team much provide for the project to achieve its MOV Work Breakdown Structure – a project management tool that provides a hierarchical structure that acts as a bridge, or link, between the project’s scope and the detailed project plan that will be created. Copyright 2015 John Wiley & Sons, Inc.
4
Figure 5.1 – The Triple Constraint
Copyright 2015 John Wiley & Sons, Inc.
5
Why do we need scope planning?
6
Scope Planning Copyright 2012 John Wiley & Sons, Inc.
7
Scope Boundary Copyright 2012 John Wiley & Sons, Inc.
8
Planning Scope Management
The project team uses expert judgment and meetings to develop two important outputs The scope management plan is a subsidiary part of the project management plan
9
Scope Management Plan Contents
Example A Example B
10
Requirements Management Plan (RMP)
“conditions or capabilities that must be met by the project or present in the product, service, or result to satisfy an agreement or other formally imposed specification*” *The PMBOK® Guide, Fifth Edition
11
RMP: Collecting Requirements
For some IT projects, it is helpful to divide requirements development into categories called elicitation, analysis, specification, and validation
12
Relative Cost to Correct a Software Requirement Defect
13
RMP: Methods for Collecting Requirements
14
Statistics on Requirements for Software Projects *
88% of the software projects involved enhancing existing products instead of creating new ones 86% said that customer satisfaction was the most important metric for measuring the success of development projects 83% of software development teams still use MS Office applications (e.g. Word and Excel) as their main tools to communicate requirements *John Simpson, “2011: The State of Requirements Management” (2011).
15
Improving User Input
16
Improving User Input
17
Reduce Incomplete and Changing Requirements
18
RMP: Managing Requirements during Project
A requirements traceability matrix (RTM) is a table that lists requirements, various attributes of each requirement, and the status of the requirements to ensure that all requirements are addressed Another Example
19
SMP: Defining Scope Project scope statements should include at least:
20
Statement of Work Narrative description of the product, service, or information system. For internal projects, this is tied to the business need For external projects, this would include specifications, quantities, quality standards, and performance requirements for prospective bidders.
21
Scope Statement Develop a proactive electronic commerce strategy that identifies the processes, products and services to be delivered through the World Wide Web. Develop an application system that supports all of the processes, products, and services identified in the electronic commerce strategy. The application system must integrate with the bank’s existing enterprise resource planning system.
22
Out of Scope Technology and organizational assessment of the current environment Customer resource management and data mining components
23
Project Scope Definition
The scope boundary and scope statement provide a useful first step The project’s scope must now be defined in more detail in terms of specific deliverables that provide a basis for developing the project’s work breakdown structure (WBS) Tools:
24
Project-Oriented vs. Product-Oriented Deliverables
Project-Oriented Deliverables Product-Oriented Deliverables
25
Deliverable Definition Table (DDT)
Deliverable Definition Table (DDT) Deliverable Structure Standards Approval Needed By Resources Required Business Case Document As defined in the Project Methodology Project Sponsor Business Case Team, & office automation (OA) tools Project Charter & Project Plan Project manager, project sponsor & OA tools Current System Study Project Manager & Project Sponsor Systems analysts users, case tool and OA tools
26
Deliverable Structure Chart Copyright 2012 John Wiley & Sons, Inc.
27
Context Data Flow Diagram
Product-Oriented
28
Use Case Diagram
29
Project Scope Verification
MOV Deliverables Quality Standards Milestones Review and Acceptance
30
Sample Project Charter (partial)
Describes the high level scope
31
Refining Project Scope
32
Example Scope Statements
33
Project Scope Statement - Exercise
POQ Organization – Online Shoe Store Review the exercise and answer the questions at the bottom of the sheet We will discuss each of these questions and then create the scope statement
34
Controlling Scope Scope control involves controlling changes to the project scope
35
Controlling Scope Goals of scope control:
36
Scope Change Control Concerned with managing changes to the project’s scope and to ensure that these changes are beneficial when they occur Mitigates: Tools/Procedures:
37
Scope Change Request Form
Scope Change Request Form Requestor Name: _______________ Request Date: __________ Request Title: __________________ Request Number: _______ Request Description: Justification: Possible Alternatives: Impacts Alternative 1 Alternative 2 Alternative 3 Scope Schedule Resources Required Cost Recommendation: Authorized By: Date:
38
Scope Change Request Log
39
Benefits of Scope Control
Keeps the project manager in control of the project. Allows the project team to stay focused and on track
40
Avoiding Scope Creep Scope creep may occur as a result of:
41
Scope Creep To mitigate these types of issues, the proposed solutions are the following:
42
Best Practices - Avoiding Scope Problems
43
Scope Problems -> Project Failures
A project scope that is too broad and grandiose can cause severe problems FoxMeyer Drug McDonalds
44
What is Project Scope Management?
45
PMI: Project Scope Management Processes
Process Group Integration Management Process Major Output Planning P1: Plan Scope Management Scope Mgmt Plan Requirement Mgmt Plan P2: Collect Requirements Req. Documentation Req. Traceability Matrix P3: Define Scope Project Scope Stmt Project Docs Update P4: Create WBS Scope Baseline Monitoring and Controlling MC1: Validate Scope Accept Deliverables Change Requests Work Performance Info MC2: Control Scope Project Mgmt Plan Updates Org, Process Asset Updates \
46
Scope Management Plan Collect Requirements Define Scope
Defining and documenting the customer, sponsor, or stakeholder needs and expectations. This may be a formal document. Define Scope A detailed description of the product, service, or information system to be designed, built and implemented. A detailed scope statement defines what work will and will not be part of the project and will serve as a basis for all future project decisions Create the Work Breakdown Structure The decomposition or dividing of the major project deliverables (i.e., scope) into smaller and more manageable components Verify Scope Confirmation and formal acceptance that the project’s scope is accurate, complete, and supports the project’s MOV. The project team and sponsor must agree to all deliverables Control Scope Ensuring that controls are in place to manage proposed scope changes once the project’s scope is set. Must be communicated to all project stakeholders.
47
Scope Management Plan Collect Requirements
Centers on defining and documenting the stakeholders’ needs to properly manage expectations Define Scope A detailed description of project and the product. It should define what work will and will not be included in the project. Create Work Breakdown Structure (WBS) The decomposition or dividing of the major project deliverables into smaller and more manageable components. Verify Scope Confirmation and formal acceptance that project’s scope is accurate, complete, and supports the project’s goal. Control Scope Ensuring that controls are in place to manage proposed scope changes one the project’s scope is accepted. These procedures must be communicated and understood by all project stakeholders.