1 Solid Handling Systems Of FFBL Coal Power Plant Project(CPP) Project
By: Saqib Iqbal Management Associate (Process)

2 CPP PROJECT – INTRODUCTION
CPP Project AIM Alternate fuel for steam and power generation owing to shortage of Natural Gas. Meeting FFBL Steam and Power requirements Additional margins for Power Export to National grid Main Components of CPP Project 2 x 250 MeT/hr Circulating Fluidized Bed (CFB) Boilers 3 x STG’s at 60 Hz 1 x BPSTG’s or BPSTG cum Condensing at 60 Hz 1 x 55 MWe STG’s at 50 Hz for Power Export

3 Over-view of Flow Schematic
New Coal Power Plant (CPP) Project FFBL Existing Plants Ammonia-Urea-DAP-Utilities Fertilizer’s Plant Coal (Mainly Indonesia / South Africa & local Coal) Utilities supplies to Coal Power Plant Exchange Facilities CPP Project 2 x 250 t/h CFB Boilers 3 x STGs + 01 BPSTG (60Hz) 1 x 50 ~ 60 MW (50 Hz) Balance of Plants (BOP) Limestone (Local Source) Steam supply to existing complex Sand (Local Source) Power supply to existing complex (60 Hz) Power Export to National Grid (on 50 Hz) Effluent (Storm water / Cooling tower blow down) FFBL Complex (350 Acres)

4 Sorbent Handling System
OBJECTIVE Solid Handling System Coal Handling system Sorbent Handling System Ash Handling System Fly Ash System Bottom Ash System

5 Unloading at KPT / BQ Port Inland Transportation
Coal Supply Chain Unloading at KPT / BQ Port Mine Site Ocean Transportation Temporary Yard at KPT Inland Transportation FFBL Plantsite

6 Coal Handling Plant (CHP) Layout
Coal Yard Crusher House Boiler 1 Bunkers Boiler 2 Bunkers

7 MAIN EQUIPMENTS FOR CHP
Weighing Bridges Coal Truck’s Unloading station. Magnetic Separator / Sampling Point / On-line Weighing Coal Yard (60,000 Met) Stacker ( 1 x 500 Met/hr) Re-claimer (1 x 200 Met/hr) Vibrating Feeders / Screens Conveying Belts (2 x 200 Met/hr; one line standby) Crusher House (2 x 200 Met/hr; one standby) Tripper Cars (2 x 200 Met/hr; one standby) De-dusting System Dust Suppression system

8 COAL TRUCKS 20 Tons Truck with hydraulic unloading system
40 Tons Truck with gates on sides for manual unloading

9 COAL UNLOADING STATION
Covered underground unloading hoppers Ground level Coal Unloading hoppers to coal yard Conveyor belt 500 T/hr

10 COAL YARD Coal yard capacity is around 60,000 Met with dust suppression system Portal type stacker, 500 MeT/hr capacity with telescope discharge and dust suppression system Coal yard bypass system

11 STACKER & RECLAIMER Coal Pile 60,000 MeT
Stacker with conveyor belt (500T/hr) Reclaimer with conveyor belt (200 T/hr) Coal Pile 60,000 MeT

12 BELT CONVEYOR Redundant conveying system 200 Met/hr Each line
Automation through PLC Enclosed conveyor. Dust mitigation at transfer towers. Fire resistant belts

13 Main Equipments of Sorbent Handling Plant(SHP)
Weighing Bridge (Common for Coal & Sorbent system) Sorbent Truck’s Unloading to Storage Hall Storage Silo Crushers Vibrating Feeders / Screens Conveying Belts Bucket Elevators Pneumatic Conveyor Conveying Blowers Limestone Storage Bins

14 Fly & Bottom Ash Handling Plant
The solid matter generated after burning coal in furnace is called ash and will be generated from CFB boilers in two parts; one is Fly and other is Bottom ash. Fly ash will be collected from bag house filter and from Air Heater hopper from each boiler to prevent ash from release into environment and will be pneumatically conveyed to Fly Ash silo for disposal. Bottom ash is basically heavier and will discharge from CFB boiler furnace bottom and after cooling will be transferred to Bottom ash silo for disposal.

15 Fly & Bottom Ash Handling Plant
Fly Ash Handling Component Fly ash 2.7 Met/hr at 150oC at BMCR per boiler for design coal. Pressurized Conveying pipes Fly Ash Silo for each boiler Silos Fluidization System Ash humidifier / conditioner for dry / wet unloading into truck. Bottom Ash Handling Component Fly ash 1.4 Met/hr at 150~230oC at BMCR per boiler for design coal. Drag Chain Conveyor up to silo Bottom Ash Silo for each boiler Ash humidifier / conditioner for dry / wet unloading into truck

16 Layout Diagram of Ash Handling Plant
Fly Ash Handling Plant Layout Diagram of Ash Handling Plant

17 Bottom Ash Handling Plant

18 Layout Diagram of Ash Handling Plant

19 Bottom Ash Silo Loading Fly Ash Silo Loading Truck
Ash Handling Plant Bottom Ash Silo Loading Fly Ash Silo Loading Truck

20 Environmental Mitigation Measures
State of Art Coal, Sorbent and Ash handling system. Covered coal unloading station Bag house filter on each ash silo. Dust suppression system. Water fogging / spray system for coal handling including during coal stacking Coal yard water drainage and recovery system Enclosed conveying system. Telescopic loading of ash into trucks.