Network Diagram Prob 1 Activity Predecessor Duration (days) A None 2 B

Similar presentations


Presentation on theme: "Network Diagram Prob 1 Activity Predecessor Duration (days) A None 2 B"— Presentation transcript:

1 Network Diagram Prob 1 Activity Predecessor Duration (days) A None 2 B
3 C 1 D E C,D 4 F G Draw network diagram and apply duration to activities Determine number of paths and list Determine critical path

2 Network Diagram Prob 2 Activity Predecessor Duration (days) A None 2 B
3 C 1 D E 4 F D,E G Draw network diagram and apply duration to activities Determine number of paths and list Determine critical path

3 Network Diagram Prob 3 Activity Predecessor Duration (days) A None 2 B
1 D B,C E 4 F G Draw network diagram and apply duration to activities Determine number of paths and list Determine critical path

4 Network Diagram Prob 4 Activity Predecessor Duration (days) A None 2 B
3 C 1 D 6 E C,D 4 F G Draw network diagram and apply duration to activities Determine number of paths and list Determine critical path

5 Network Diagram Prob 5 Activity Predecessor Duration (days) A None 2 B
3 C 1 D 5 E F D,E G Draw network diagram and apply duration to activities Determine number of paths and list Determine critical path


Download ppt "Network Diagram Prob 1 Activity Predecessor Duration (days) A None 2 B"