Project eMerge Status Update
COIT – Budget Subcommittee February 20, 2009 Project eMerge Status Update
2
Description Deploy a Human Resources Information System using a secure and robust technical platform for mission critical systems that: Integrates core business systems Eliminates manual and redundant business processes Provides enhanced services to active, retired and potential workforce
3
Accomplishments Hired 26 FTE – actively recruiting 3 technical positions Launched project website – Completed Pre-Implementation Phase Commenced implementation Phase I Hosted Project Kick Off event Created CCSF / Ciber Project Charter Completed first round functional training Chartered and kicked off forums - Recruitment, Time and Labor, Position Management
4
Project Health Summary
Project Attribute Deliverable Planned* Actual Status Start End Schedule Policy Database - Charter, Admin Code, Civil Service Rules, MOUs 06/23/08 10/31/08 10/10/08 Department Head Meetings - Project Goals & Alignment 9/22/08 12/26/08 Conduct remote time entry device analysis 08/26/08 12/31/08 8/26/08 Infrastructure Build Out - Pre-Production Environments 01/01/08 10/23/08 Fit Gap Sessions 05/01/08 07/31/08 08/18/08 Fit Gap Report 6/19/08 6/27/08 12/4/08 Determine Operational Support Structure 6/30/08 9/30/08 G Y G R R R R *Based on Statement of Work Project Schedule
5
Project Health Summary cont’d
Project Attribute Status Comments Overall Schedule Projected Phase I go-live – 02/2010; evaluation of included functionality for Phase I will be necessary Scope Increase in scope due to Disaster Service Work Program and Absence Management requirements Cost Expenditures within approved budget Overall Y Y G Y
6
Critical Milestone Schedule - Phase 1
Feb 09 Mar Apr May June July Aug Sept Oct Nov Dec Jan 10 Pre-production environments available 27 Fit/Gap Analysis complete Initial Data Conversion (Prototype I) 1 Development Coding/Unit Testing 28 Expanded Conversion (Prototype II & III) Performance/Production Environments 5 Expanded Conversion (Prototype IV) 2 User Acceptance Testing 6 Performance Testing 17 Parallel Testing 29 End User Training (Develop/Deliver Go/No-Go Decision Final Implementation Phase 1 (Go-Live) 7 20
7
Critical Milestone Schedule by Quarter - Phase II and III
Q3 FY09 Q4 FY09 Q1 FY10 Q2 FY10 Q3 FY10 Q4 FY10 Q1 FY11 Q2 FY11 Q3 FY11 Q4 FY11 Final Implementation Phase 1 (Go-Live) Phase II (Time & Attendance) Phase III (Training, Performance Management, Workers Compensation)
8
Issues & Risks Risk Description Triggers High Level Mitigation Plan
Impact - Cost, Scope, Time City Computer Hosting Center relocation from OMP to an undetermined location Timing of move conflicts with planned project milestones, so that project staff is unable to progress to the next stage of work Adjust schedule so it does not directly conflict with project requirements for production infrastructure environment schedule Time Potential inability to maintain enterprise level infrastructure – i.e. network inter-connectivity, application security, control and standardization DT develops operational support plan that exposes vulnerabilities in network and data security, interconnectivity and business continuity Develop a strong partnership with DT and partner in developing standards, i.e. Service Level Agreements, training Cost, Scope, Time Political imperatives result in a loss of project sponsorship Reallocation of funds from project Communicate and engage project sponsors; meet with supervisors to enlist support; prepare alternate plans with associated risks. Scope, Cost
9
Issues & Risks cont’d Risk Description Triggers
High Level Mitigation Plan Impact - Cost, Scope, Time Inability to control functional scope Stakeholders request additional functionality; lack of detail within original functional requirements; software out-of-box functionality does not meet expectations. Analyze and better define current requirements; work with project management and Executive Steering Committee to define what is in scope for the project vs. post-production Scope, Time End user concerns about security and confidentiality Media and external events Data breach Union resistance Encrypt sensitive data; limit access to info on reports; limit use of, and access to, SSN; work with COIT to create a City wide policy stopping the use of SSN Scope
10
Issues & Risks cont’d Risk Description Triggers
High Level Mitigation Plan Impact - Cost, Scope, Time Loss of jobs blamed on the new system Scheduled layoffs Communicate with Executive Steering Committee and key stakeholders to ensure that layoff communications are on focused on budgetary constraints and not tied to eMerge Benefits realization New software will force “current” policy compliance Example – New system enforces vacation accrual cap for departments who previously did not track hours accrued per employee As discrepancies are identified, project team will inform DHR what the system will enforce. DHR will determine how they address discrepancies with departments and unions in meet and confers. Reduction of multi-year budget funding commitment Citywide budget deficit; Enterprise departments decide to stop support through funding Monitor CCSF fiscal environment for budget impacting changes; provide ongoing reporting on project expenditures; maintain departments involvement in process; keep Executive Steering Committee and Board of Supervisors engaged Cost, Scope
11
Issues and Risks cont’d
Risk Description Triggers High Level Mitigation Plan Impact - Cost, Scope, Time Failure of legacy systems to remain operational Fatal crash of any of the systems for any reason, including disaster Create a disaster response plan for existing system; retain SMEs to support existing legacy systems; assess viability to support/replace the existing infrastructure; work with the Controller’s Office to review the contingency plan specifically for payroll Cost, Scope, Time Lack of union involvement, commitment, adoption Grievance of other type of complaint voiced from employee to union; union(s) make decision to stop or reduce support of the project Ensure unions are involved and committed to project; define and execute pro-active change management plan targeted to union leadership; monitor and survey union feedback on project; present the expected service model to unions, including revised roles and responsibilities.