SPS YETS 2017/2018 Planning meeting (No.1) 13/09/17

Similar presentations


Presentation on theme: "SPS YETS 2017/2018 Planning meeting (No.1) 13/09/17"— Presentation transcript:

1 SPS YETS 2017/2018 Planning meeting (No.1) 13/09/17
David Mcfarlane EN-ACE D. Mcfarlane

2 Topics TS3-SPS-2017. YETS 2017/2018 dates.
Key Dates & Schedule for week 1. YETS AUG test draft dates. COORDINATION SECURITE PENDANT LES ARRETS DU SPS). Rappel EN-EL. ECRs. Future meetings & presentation of group planning's. What information I now need from you. External visitors. Access rights and safety equipment. Important group and project contacts. A.O.B. EN-ACE D. Mcfarlane

3 TS3-SPS-2017 Tuesday the 19th September.
The next technical stop will be on: Tuesday the 19th September. It will last for 24 hours. Which means 1 full working day of access. You can create an IMPACT using the intervention period (TS3-SPS-2017) If you do not use this intervention period it will not be approved!!!!! All IMPACTs will be approved by me by the end of this week. Access will be from 08:30 onwards. Access will be until 18:00 unless specifically requested. The Lift at BA1 will be out of service from 08:30 to 11:30. No access into BA1 and BA2 in the morning. (RP conditions) The lift at BA5 will be out of service from 13:00 to 17:00. Access can be via the stairs or BA4 or BA6. EN-ACE D. Mcfarlane

4 SPS Lift Maintenance during TS3
Location Lift/Monte-charge Lift number Tue 19th Sept Comments BA1 Lift AS-510 08:30 – 11:30 Cable change of speed device of AS-510 BA2 AS-503 08:00 – 09:30 Monte-charge AS-504 09:30 – 11:30 BA3 AS-505 13:00 – 14:30 AS-507 14:30 – 16:30 BA5 AS-506 13:00 – 17:00 Full lift maintenance of AS Overspeed device change BA6 AS-508 AS-509 BA80 AS-514 10:00 – 11:30

5 DO NOT FORCE THE DOORS BETWEEN ECX5 & ECA5

6 Machine access (weeks)
RELEASED Year-End Technical Stop References: 15 weeks beam to beam stop for the LHC Xenon physics for the North Area 5 weeks for commissioning (hardware tests + cold check-out + beam commissioning) in the injectors (PSB, PS, SPS) before beam ready for the LHC 2 to 3 days of diagnostic tests in the injectors with machine closed Machines Machine access (weeks) (not including the 2 weeks of annual closure) LINAC2 4 PSB 6.5 PS SPS 7.5 LHC 11

7 YETS 2017/2018 AUG Tests Draft Planning
Point Day (Access will be blocked) BA1 Monday 22nd January (W4) BA2 Wednesday 31st January (W5) BA3/BB3 Friday 2nd February (W5) BA4 + AWAKE Thursday 8th February (W6) BA5 Monday 12th February (W7) BA6 Tuesday 13th February (W7) BA7 Wednesday 14th February (W7) AUTO TRANSFERT TEST 2018 No access in LHC1, LHC18, BA6 & BA7 27th and 28th January Saturday & Sunday (W4) BA80 Monday 19th February (W8) BA81 Tuesday 20th February (W8) BA82 Wednesday21st February (W8) Can you please check if these dates are ok with your SPS YETS planning ? (And see if there are some blocking points or not..) EN-ACE D. Mcfarlane

8 Key dates Beam off at 06:00 on Monday the 18th December
Access into BA7, TI2, TAG41, TAG42 & TI8: Monday the 18th December until Friday the 23rd February 2018. 8 weeks of access. Access into BA3,4,5 & 6: Thursday the 21st December until Friday the 23rd February 2018. 7.4 weeks of access. NO works are currently planned during the 2 week Xmas vacation. XMAS holidays: Saturday the 23rd December to Sunday the 7th January inclusive Access into BA1 & BA2: Monday the 8th January until Friday the 23rd February 2018. 7 weeks of access. 3 weeks foreseen for EPC tests and cold-checkout by OP. SPS will take beam from the PS on Monday the 19th March 2018, followed by 1 week for beam setup. SPS ready to give beam to the LHC on Monday the 26th March 2018! EN/ACE/OSS BE/OP EN-ACE D. Mcfarlane

9 Current schedule for week 1 (18th to 22nd December)
Monday 18th December Beam off 06:00Hrs Access possible in BA7, TI2, TAG41, TAG42, TI8. All water and power to remain on (Machine is in standby) SPS ring closed to everyone except: RP: will survey the tunnel Magnet team: to remove covers on the magnets. Tuesday 19th December Magnet team conduct tests SPS closed (to everyone except Magnet team) Wednesday 20th December Thursday 21st December Water can be cut and the machine electrically isolated BA1 and BA2 remain closed for RP cool down BA3, BA4, BA5, BA6, BA7 are open for general access Friday the 22nd December BA3, BA4, BA5, BA6, BA7 are open for general The SPS is effectively still in run mode. General access into the SPS begins. EN-ACE D. Mcfarlane

10 RESUME DU FONCTIONNEMENT DE LA COORDINATION SECURITE PENDANT LES ARRETS DU SPS (Reference HSE / GSI – WS-1) Coordination sécurité pour les travaux dans les complexes (PS, SPS et LHC) Assurée par l’unité organique responsable de la coordination de l’arrêt (EN/ACE/OSS-COS) Réalisée via la planification, la validation des interventions (IMPACT) la présentation à chaque réunion de coordination d’un tableau de suivi des VIC VIC (visite d’inspection commune) Organisée par le superviseur de travaux, sur sa propre initiative ou sur demande de l’unité organique en charge de la coordination Présence obligatoire du superviseur de travaux et de l’intervenant – Présence sur demande d’un représentant d’une fonction de sécurité du CERN (EROS ou expert HSE) Rédaction d’un compte-rendu de VIC via IMPACT Suivi des travaux Assuré par le superviseur de travaux. Retour d’information à l’unité organique, au minimum chaque semaine lors de la réunion de coordination. Par les représentants de l’unité organique EN-ACE D. Mcfarlane

11 Rappel EN/EL Les DIC/DIF/DIR/DFP DEFINITIVES sont à transmettre au plus tard le accompagnées des documents nécessaires à la réalisation des travaux. Les demandes arrivées après se verront dans le meilleur des cas traitées dans un second temps, voir pas du tout.

12 Rappel EN/EL-FC Exemple de travaux évoqués mais pour lesquels les DIC n’ont pas encore été reçues ou encore incomplètes donc non traitables: Fire Safety (sprinkler, autres) Nouveau GSM (BA3/BA4) BAF3 câblage vers les bâtiments annexes

13 SRRs and ECRs for the SPS
SPS planning and coordination meeting for YETS Sonia Bartolomé Jiménez EN-ACE-CL – 13th September 2017

14 Sonia Bartolomé Jiménez EN-ACE-CL – 13th September 2017
Outline SPS ECRs for YETS : status All known activities needing ECRs ECRs received ECRs expected -drafts not yet submitted to EN-ACE-CL- SRRs and ECRs: reminder Roadmap Tips Sonia Bartolomé Jiménez EN-ACE-CL – 13th September 2017

15 SPS ECRs for YETS 2017-2018: status
All known activities needing ECRs n EDMS reference Title Authors/contact person 1 SPS-V-EC-0005 Modification of the SPS sectorization in long vacuum sectors (arcs) (EYETS ) – BA3* C. Pasquino, J. Ferreira (TE-VSC) 2 SPS-TPSWA-EC-0001 Diffuser for LSS2 ZS electrostatic septa B. Bahlan, J. Borburgh (TE-ABT) 3 SPS-LJ-EC-0005 New RF power feeder lines in SPS point 3 shaft (PA3) and GT10 for LIU-SPS P. Parrado, E. Montesinos (BE-RF) 4 SPS-ADKSV-EC-0001 Slotted Line Kicker in LSS3 of the SPS 5 LSS6 crab cavity installation G. Vandoni (BE-RF) 6 Installation of Target Absorber Collimator with Tungsten jaw in half-period S. Montesano (EN-STI) 7 SPS-CC-EC-0001 Replacement of Telecom Radiating Cable in the SPS S. Agosta (IT-CS) 8 Doors Fire safety (WP1) Point 4 - Prototype in LSS4 R. Morton (SMB-SE) 9 SPS-Y-EC-0003 Safety access in BB5: ECA5 Access Point Installation T. Ladzinski (BE-ICS) 10 SPS beam dumping system kicker platform, transmission cable trays and cables installation in point 5 P. Van Trappen (TE-ABT) 11 Installation of TPSC4 in front of the SPS extraction septa in LSS4 M. Hourican, M. Fraser (TE-ABT) 12 SPS amorphous carbon coating (related to ECR ) W. Vollenberg (TE-VSC) 13 SPS impedance flange reduction in Arc 45 (related to ECR ) J. Pérez Espinos (TE-VSC) 14 Change 1 ZS for the ZS improvements [TBC if carried out during YETS] 15 Replacement of the emergency lighting in the SPS tunnel and shafts S. Bertolasi (EN-EL) * The Modification of the SPS sectorization was described in SPS-V-EC-0005 (v.1.0 Released). The sectorisation in BA3 will be performed during the YETS  a different ECR should not be needed. Total number of ECRs needed = 14 Sonia Bartolomé Jiménez EN-ACE-CL – 13th September 2017

16 SPS ECRs for YETS 2017-2018: status
ECRs received EDMS reference EDMS Status Title Authors/contact person LIU Project Deadline Date / Released Date SPS-TPSWA-EC-0001 Under Approval Diffuser for LSS2 ZS electrostatic septa B. Bahlan, J. Borburgh (TE-ABT) NO SPS-LJ-EC-0005 New RF power feeder lines in SPS point 3 shaft (PA3) and GT10 for LIU-SPS P. Parrado, E. Montesinos (BE-RF) YES SPS-ADKSV-EC-0001 Slotted Line Kicker in LSS3 of the SPS SPS-V-EC-0005 Released Modification of the SPS sectorization in long vacuum sectors (arcs) (EYETS ) – BA3 C. Pasquino, J. Ferreira (TE-VSC) SPS-Y-EC-0003 In Work Safety access in BB5: ECA5 Access Point Installation T. Ladzinski (BE-ICS) 3 ECRs are now under approval. 1 ECR drafted, not yet ready to be sent for approval. Sonia Bartolomé Jiménez EN-ACE-CL – 13th September 2017

17 Draft submitted to EN-ACE-CL
SPS ECRs for YETS : status ECRs expected -drafts not yet submitted to EN-ACE-CL- EDMS reference Title Draft submitted to EN-ACE-CL Authors/contact person LIU Project LSS6 crab cavity installation No G. Vandoni (BE-RF) NO Installation of TACW (Target Absorber Collimator with Tungsten jaw) in half-period S. Montesano (EN-STI) SPS-CC-EC-0001 Replacement of Telecom Radiating Cable in the SPS S. Agosta (IT-CS) Doors Fire safety (WP1) Point 4 - Prototype in LSS4 R. Morton (SMB-SE) Replacement of the emergency lighting in the SPS tunnel and shafts S. Bertolasi (EN-EL) SPS beam dumping system kicker platform, transmission cable trays and cables installation in SPS point 5 P. Van Trappen (TE-ABT) YES Installation of TPSC4 in front of the SPS extraction septa in LSS4 M. Hourican, M. Fraser (TE-ABT) SPS amorphous carbon coating (related to ECR ) W. Vollenberg (TE-VSC) SPS impedance flange reduction in Arc 45 (related to ECR ) J. Pérez Espinos (TE-VSC) Change 1 ZS for the ZS improvements [TBC if carried out during YETS] B. Bahlan, J. Borburgh (TE-ABT) 10 ECRs not yet received!! Sonia Bartolomé Jiménez EN-ACE-CL – 13th September 2017

18 SRRs and ECRs: reminder
Roadmap ECRs submission to configuration team (EN-ACE-CL) 2 months before the approval deadline! Sonia Bartolomé Jiménez EN-ACE-CL – 13th September 2017

19 SRRs and ECRs: reminder
Tips All changes to the machine that will impact the beam shall be documented by SRRs/ECRs: SRR: Space Reservation Request (“light ECR”) ECR: Engineering Change Request Templates available on: To be sent to the SPS configuration manager: or Sonia Bartolomé Jiménez EN-ACE-CL – 13th September 2017

20 Future meetings It has been requested by the group leaders for each group to present their planned works to the coordinators of each machine. Therefore the table below will show which group will present at what SPS planning meeting. Date of meeting Presentation 1 Presentation 2 Presentation 3 Meeting 2 (27th Sept) EN/CV EN/EL BE/RF + Crab Cavity Meeting 3 (11th Oct) BE/BI TE/VSC + Coldex BE/ICS Meeting 4 (25th Oct) EN/STI + UA9 SMB/SE EN/HE Meeting 5 (8th Nov) TE/ABT TE/MSC EN/ACE (Survey) (Cabling) Meeting 6 (22nd Nov) BE/CO TE/EPC HSE/RP Meeting 7 (6th Dec) BE/OP EN-ACE D. Mcfarlane

21 What I need from you. I need your planning!
not simply a list of works. Identify the location of the works Surface, Underground, which sector (eg, 3-, LSS4 etc.) Any works under the false floors in the suface BA’s MUST be highlighted! Identify the duration of the works (in days or weeks) Try to plan nothing for the final week of the shutdown! Your target is to complete your works by February 16th! Identify any impact of your works. Access blocked, no transport through the zone, must work alone, etc. Identify what you need. Power, water, vacuum/transport support etc. Identify what type of works it is. LIU, Maintenance, Consolidation. If you need some information from any other group, explain what you want and WHEN you need this information by. EN-ACE D. Mcfarlane

22 Other presentations EN-ACE D. Mcfarlane

23 External Visitors If you have any external personnel needing to access the SPS for visits before starting works then you need to read the following document: "Etapes à suivre pour organiser des visites professionnelles dans les installations faisceaux" by CHRISTELLE GAIGNANT Link: EN-ACE D. Mcfarlane

24 Access rights and safety equipment
EVERYONE who enters the SPS MUST have the following: Completed the correct courses. (sir.cern.ch) CERN Safety Introduction. Electrical Safety Awareness. (19 choices) Self Rescue Mask Training. (4 choices) CERN – Beam Facilities. SPS – Machine. The correct access authorisation (via EDH). CHECK YOUR ACCESS RIGHTS HAVE NOT EXPIRED!!!! Zone Code “SPS” for access into the SPS Zone Code “NA_TARG” for access into BA80 Zone Code “TAG41 - AWAKE (ex-CNGS) (TAG41)” for access into the old CNGS areas Zone Code “SPS-KN-000” for “Autorisation conduite RTL” Zone Code “SPS-KN-001” for “SPS Shutdown Padlock” (only used during Long Shutdowns) Safety shoes. Biocell. Electronic dosimetre. Passive dosimetre. (All contractors must have an additional company passive dosimetre!!) Helmet plus Light. A valid approved IMPACT. (with their name included on this IMPACT) They must know the number of this IMPACT. Please note that personnel are not allowed to work in the tunnel alone!! EN-ACE D. Mcfarlane

25 Important Contacts Useful Contact Numbers SPS Coordination Team
David MCFARLANE Franck BAIS – Aurelio Berjillos BARRANCO Control Room SPS CCC – 77500 TI CCC – 72201 CSA RP Christophe Tromel – Angelito Herve – Nadine Conan (BA1) – Kurt Weiss (BA7) EROS Engineering Referent for Operational Safety Emmanuel Paulat – John Etheridge EN-ACE D. Mcfarlane

26 Group contact persons. (1)
Comments EN/EL Guillaume Gros (Cabling) Georgi Georgiev (De-cabling) Denis Ribiollet (Operation) Bruno Saint Sulpice (Operation) Jeremy Blanc (Fibres) Marcin Bartosz Szewczyk Gerardo Velazquez Gutierrez (Projects) EN/CV Bill Bannister (Water) Vivien Koutcheroff (Ventilation) Jani Lehtinen EN/STI Jerome Lendaro Simone Montesano (UA9) Sven De Man TE/MSC Jeremie Bauche Pascal Catherine TE/EPC Karsten Kahle (High power) Gilles Le Godec (Medium power) TE/VSC Anthony Harrison Chiara Pasquino Wilhelmus Vollenberg (aC coating) Vincent Baglin (COLDEX) TE/ABT Francesco Castronuovo Gael Bellotto (Kickers) Cedric Baud (Septas) Eteinne Carlier (New Beam Dump) BE/RF Eric Montesinos (RF upgrade) Christophe Renaud Gino Cipolla Group Contact Person Comments EN/EL Guillaume Gros Denis Ribiollet EN/CV Bill Bannister (Water) Vivien Koutcheroff (Ventilation) EN/STI Jerome Lendaro Simone Montesano TE/MSC Jeremie Bauche Pascal Catherine TE/EPC Karsten Kahle (High power) Gilles Le Godec (Medium power) TE/VSC Jose A. Ferreira Anthony Harrison Chiara Pasquino TE/ABT Francesco Castronuovo (Kickers) Cedric Baud (Septas) BE/RF Eric Montesinos Christophe Renaud Gino Cipolla BE/BI Raymond Veness Morad Hamani BE/CO Magnus Bjork EN-ACE D. Mcfarlane

27 Group contact persons. (2)
Comments BE/BI Raymond Veness Morad Hamani BE/CO Magnus Bjork IT/CS Maryse Da Costa Stephano Agosta (GSM) BE/ICS Didier Vaxelaire (Access) Tomasz Ladzinski (New access system) Denis Raffourt (Fire detection) Michael Dole (Fire Safety) Anna Suwalska (Sprinklers) Eva Sanchez-Corral Mena (Planning) HSE/RP Christophe Tromel Angelito Herve EN/ACE Patrick Bestmann (Survey) Sonia Bartolomé (E.C.R / S.R.R) Fred Galleazzi (Intergration) Scharif Mehanneche (Intergration) Emmanuel Paulat (Safety) EN/HE Patrick Vallet (Transport) Pascal Brunero (Transport) Jean-Louis Grenard (Transport) Nicolas Perez (Lifts) BE/OP James Ridewood Stephane Cettour Cave SMB/SE Alejandro Martinez Selles Richard Morton (Beam Dump) Crab Cavity Giovanna Vandoni EN-ACE D. Mcfarlane

28 A.O.B. Salut David, Peux-tu STP montrer l’image jointe cet après-midi en réunion et demander si la structure (qui ne doit plus servir, à confirmer…) peut être démontée ? Merci. Fred. EN-ACE D. Mcfarlane

29 Useful websites Link to SPS planning meetings on INDICO
Link to the SPS planning Roadmap: Schedule beyond LS1 Next meeting 27/09/2016 EN-ACE D. Mcfarlane

30 EN-ACE D. Mcfarlane


Download ppt "SPS YETS 2017/2018 Planning meeting (No.1) 13/09/17"