1
DESIGN-BUILD A Case Study Emerald Middle School
Cajon Valley Union School District El Cajon, CA Larry
2
Case Study Emerald Middle School, at Cajon Valley Union School District Sharon
3
Cajon Valley Union School District
16,200 students K - 8 Sharon League of Innovative Schools
4
Emerald Middle School STEAM Magnet School 525 students currently
Sharon STEAM Magnet School 525 students currently Grades 6 – 8 Original school built circa 1959
5
Consideration of Design-Build
Background Past successful projects w/Lease Lease-Back Consideration of DB Delivery Method for Emerald Middle School Project Scope: New gymnasium/auditorium, stage, locker room, weight room, band room, school office, kitchen, lunch court Sharon
6
Choosing Design-Build
Background District researched DB Method AB 1402 Design-Build Project Guidelines (CDE) Discussions with legal, architects, contractors, & other school districts Sharon
7
Preparing for Design-Build
Tips 1 – Don’t rush the Planning Process 2 – Hire experienced Criteria Architect Well-written criteria is vital to success 3 – Consider minimum District Requirements vs Flexibility for Creative Design Ideas Sharon
8
Preparing for Design-Build
4 – Eliminate the unknowns 5 – Don’t design the project Provide details Provide program Provide “Must-Haves” Larry
9
Design-Build Collaboration
DISTRICT D-B TEAM Contractor + Design Architect CRITERIA ARCHITECT Larry
10
Design-Build Process TWO Step Process Larry
11
Design-Build Process Step1 Request For Qualifications Larry
12
Case Study: The Emerald Experience
RESULTS 13 Responses to RFQ 3 Selected Top for RFP Based on Evaluation and Score Sheet Larry
13
Design-Build Process Step2 Request For Proposals Larry
14
Case Study: The Emerald Experience
2 Demolition buildings + site 2 Construction buildings + site Sharon $1 1.5 million Budget
15
Case Study: The Emerald Experience 3 Responses
Sharon Team 1
16
Case Study: The Emerald Experience
Sharon Team 2
17
Case Study: The Emerald Experience
Team 3
18
Selection of Design-Build Team
The Selection Process Create Evaluation Team Proposal within the identified budget Proposal meets or exceeds criteria Proposal has innovative design Larry
20
Larry
21
Lessons Learned Create a Reasonable Project Budget
Listen to DB Teams Initial Responses Be prepared to increase budget or reduce scope if feedback is justified Submittal Requirements Limit design submittal requirements to keep AE team cost of competition minimal Larry
22
Emerald Middle School Timeline
Select Criteria Architect 3 months Creating Criteria for RFP RFQ Process RFP Process 1.5 months Selection DB Team Design including DSA 11 months Pre-Construction Total: Construction 23 months Larry
23
Emerald Middle School Project Completion
Sharon
29
Emerald Middle School District’s Impressions BEFORE: Skeptical
TODAY: With the right team and sufficient planning, Design-Build can be a great way to achieve: Creative design Good value Smooth & efficient construction process Sharon
30
QUESTIONS & DISCUSSION