Plano ISD 2016 Bond Program
2
Background Election Held May 2016 New Authorization - $481 million
Remaining Funds from 2008 Program $16 million Total Program - $497 million
3
Architect/Delivery Method
Pool of Architects / Engineers Already Selected Through RFQ Process Assigned on Project by Project Basis. Exception – Fine Arts Facility Vast Majority of Projects use Construction Manager at Risk Delivery Method
4
Signature Project – Fine Arts Facility
Total Budget (including land) - $68.5 million +/ ,000 square feet Land Closing by October 31st Architect Selection – November 15th Construction Begins late 2017/early 2018
5
Other New Construction Projects
Employee Childcare No. 3 9,000 square feet Site/Architect/Construction Manager (TBD) New Elementary School Only if Necessary (TBD) Early Childhood School TBD
6
Renovations/Refurbishments
Shepton High School - $40 million Architect and Construction Manager Already Chosen Robinson Middle School - $34.8 million Architect Selection by Year-End Six Elementary Schools Architect/Construction Manager Assigned for Two Next Two - Architect Selection Spring 2017 Last Two – Architect Selection Spring 2018 Two Middle Schools and Two High Schools Architects – Spring 2017 and 2018
7
Building Additions Permanent Classrooms to Replace Portables at Sites Architects assigned for all three Construction Managers assigned for two Remaining Construction Manager (PESHS) will be selected soon Fine Arts Expansion at 4 Middle Schools Architect Selection next fall
8
Other Turf Additions – 7 Turf Replacements – 4 Safety and Security
Technology Buses
9
Ray Weaver, Director of Purchasing
Contacts/Website Ray Weaver, Director of Purchasing