EAST PENNSBORO AREA SCHOOL DISTRICT
COMMUNITY FACILITY COMMITTEE AUGUST 1, 2017 AGENDA 01 DECISION MAKING PROCESS 02 K-2 / 3-5 OPTION K-5 OPTION OPTION ESTIMATES 05 OPTION COMPARISON 06 NEXT STEPS Presented By: Leah Shiley – Director of Client Relations, Crabtree, Rohrbaugh & Associates Anthony Colestock – Project Manager, Crabtree, Rohrbaugh & Associates Providing a Client Oriented Approach to Architecture Crabtree, Rohrbaugh & Associates, Architects
2
DECISION MAKING PROCESS
EPASD outlines District Wide Goals. CRA develops options based on EPASD goals. EPASD establishes guiding principles to prioritize decision making process. CRA compares options with the District’s guiding principles. A decision making matrix is created to assist with selecting an option. EPASD makes recommendation to School Board of Directors based on matrix.
3
DECISION MAKING MATRIX
**Options do not include work to existing Middle School Natatorium
4
K-2/3-5 OPTION 8 & 8a OPTION 8 & 8a OVERVIEW
K-2, 3-5, 6-8 Grade Grouping with 1,350 Elementary Enrollment EPE: Proposed K-2 Grade Grouping (9 CRs per Grade) Current Capacity = 25 Existing CRs / 625 Capacity Planned Capacity = 27 Proposed CRs / 675 Capacity Requires 2 Classroom Addition WCH: Proposed 3-5 Grade Grouping (9 CRs per Grade) Current Capacity = 23 Existing CRs / 575 Capacity w/out modular Requires 4 Classroom Addition New District Administration Office Option 8 – New DAO EPE Option 8a – DAO EPMS (Eliminates 10 CRs)
5
K-5 OPTION 9 & 9a OPTION 9 & 9a OVERVIEW
K-5, 6-8 Grade Grouping with 1,400 Elementary Enrollment EPE: K-5 Grade Grouping (4-5 CRs per Grade) Current Capacity = 25 Existing CRs / 625 Capacity Planned Capacity = 28 Proposed CRs / 700 Capacity Requires 3 Classroom Addition WCH: K-5 Grade Grouping (4-5 CRs per Grade) Current Capacity = 23 Existing CRs / 575 Capacity w/out modular Requires 8 Classroom Addition (5 General Classrooms + 3 Special Education Classrooms) New District Administration Office Option 9 – New DAO EPE Option 9a – DAO EPMS
6
EXISTING FLOOR PLANS West Creek Hills Elementary
SECOND FLOOR K K LS FAC FIRST FLOOR West Creek Hills Elementary East Pennsboro Elementary
7
EXISTING FLOOR PLANS East Pennsboro Middle School SECOND FLOOR
FIRST FLOOR East Pennsboro Middle School
8
K-2/3-5 OPTION 8 & 8a ESTIMATE
9
K-2/3-5 OPTION 8 ESTIMATE OPTION 8 OVERVIEW – K-2, 3-5, 6-8 Grade Grouping East Pennsboro Elementary: K $7.2M New Gymnasium Addition New Classrooms (2) & LGI Additions New DAO Addition Does not include Architectural & MEP Renovations West Creek Hills Elementary: $2.5M New Classroom (4) Additions Middle School: $18.5M Total Architectural & MEP Renovation New Lobby / Administration Addition STEM / Flex Classroom Renovation High School $5.0M New STEM / Flex Classroom Addition New Band / Chorus Addition TOTAL PROJECT COST $33.2M
10
K-2/3-5 OPTION 8a ESTIMATE OPTION 8a OVERVIEW – K-2, 3-5, 6-8 Grade Grouping East Pennsboro Elementary: K $4.9M New Gymnasium Addition New Classrooms (2) & LGI Additions Does not include Architectural & MEP Renovations West Creek Hills Elementary: $2.5M New Classroom (4) Additions Middle School: $18.5M Total Architectural & MEP Renovation New Lobby / Administration Addition DAO Alteration Does not include STEM / Flex Classroom Renovation High School $5.0M New STEM / Flex Classroom Addition New Band / Chorus Addition TOTAL PROJECT COST $30.9M
11
K-5 OPTION 9 & 9a ESTIMATE
12
K-5 OPTION 9 ESTIMATE OPTION 9 OVERVIEW – K-5, 6-8 Grade Grouping
East Pennsboro Elementary: K $7.5M New Gymnasium Addition New Classrooms (3) & LGI Additions New DAO Addition Does not include Architectural & MEP Renovations West Creek Hills Elementary: K $3.9M New Classroom (8) Additions Middle School: $18.5M Total Architectural & MEP Renovation New Lobby / Administration Addition STEM / Flex Classroom Renovation High School $5.0M New STEM / Flex Classroom Addition New Band / Chorus Addition TOTAL PROJECT COST $34.9M
13
K-5 OPTION 9a ESTIMATE OPTION 9a OVERVIEW – K-5, 6-8 Grade Grouping
East Pennsboro Elementary: K $5.2M New Gymnasium Addition New Classrooms (3) & LGI Additions Does not include Architectural & MEP Renovations West Creek Hills Elementary: K $3.9M New Classroom (8) Additions Middle School: $18.5M Total Architectural & MEP Renovation New Lobby / Administration Addition New DAO Alteration Does not include STEM / Flex Classroom Renovation High School $5.0M New STEM / Flex Classroom Addition New Band / Chorus Addition TOTAL PROJECT COST $32.6M
14
OPTION COMPARISON
15
OPTION COMPARISON
16
DECISION MAKING MATRIX
**Options do not include work to existing Middle School Natatorium
17
SAMPLE SCHEDULE