Download presentation
Presentation is loading. Please wait.
1
Bruno POTTIN, Anne-Catherine CHAUVEAU
ESS RFQ Bruno POTTIN, Anne-Catherine CHAUVEAU and RFQ Team
2
STATUS RFQ PRESENTATION ESS RFQ SCHEDULE ESS RFQ SCOPE DELIVERABLES
ESS RFQ TEST BENCH ESS RFQ TOOLING WHERE ARE WE TODAY? RFQ MANUFACTURING PROCESS SECTION MANUFACTURING PROCESS QUALIFICATION STATUS REALISATION PICTURES REMAINING QUESTIONS TUNNEL DELIVERY AND ASSEMBLY COOLING SYSTEM OPEN DISCUSSIONS…… B. POTTIN, A-C. CHAUVEAU
3
RFQ PRESENTATION B. POTTIN, A-C. CHAUVEAU
4
SCHEDULE Lund delivery Q2 2018 B. POTTIN, A-C. CHAUVEAU
5
ESS RFQ SCOPE DELIVERABLES
An RFQ conditionned ready to accelerate the beam RFQ and support system Wave guides and Support system Tuner RFQ cooling system and its control system Coupler Hydraulic plate Magic T + Load in the gallery B. POTTIN, A-C. CHAUVEAU
6
ESS RFQ TESTS bench Test cavity ESS bunker
ESS bunker at Saclay for : Coupler conditionning A test cavity RF distribution system from the pulsed klystron at the 352 MHz platform Coupler conditioning control system (soft and hard) RFQ assembly validation Same condition as in the ESS tunnel Portable crane Same tools as in ESS tunnel Same suppot… ESS bunker Test cavity test bench with support and load B. POTTIN, A-C. CHAUVEAU
7
ESS RFQ TOOLING Transport chassis also used for rotating the sections for vertical brazing RFQ support system for adjustment and alignment RF tuning system tools for voltage law measurement B. POTTIN, A-C. CHAUVEAU
8
Where are we today? B. POTTIN, A-C. CHAUVEAU
9
RFQ Manufacturing PROCESS
1- Copper + HIP STARTED (MÉCACHROME) 3- Section manufacturing DONE (BODYCOTE) 2- Ancillaries 4- Brazing process (BODYCOTE) One RFQ section manufacturing’s steps process ON-GOING (AMD) B. POTTIN, A-C. CHAUVEAU
10
MANUFACTURING PROCESS according to iphi (PROCESS AND MANUFACTURERs)
Bodycote Brazing Machining Mécachrome IPHI like RF validation Vacuum leak test validation TriDim CEA Bodycote B. POTTIN, A-C. CHAUVEAU
11
RFQ MéCACHROME PROCESS QUALIFICATION
2 major technical phases to be tested in parallel Step1 Qualification of deep drilling and machining technic Validation of process and manufacturer capacity with his equipment Ultrasound test and tridim measurement Machining mock-up Deep drilling mock-up Step 2 Qualification of vertical brazing process Validation of manufacturer brazing process Tridim measurement and leak test Brazing mock-up IPHI B. POTTIN, A-C. CHAUVEAU
12
RFQMANUFACTURING PROCESS QUALIFICATION
ALMOST FINISHED ….. Deep drilling mock-up Brazing mock-up IPHI B. POTTIN, A-C. CHAUVEAU
13
SECTION MéCACHROME PROCESS QUALIFICATION
STARTED….. Step 3 Qualification of a total section manufacturing : Section 1 Leak test, tridim and RF measurement To start the series production, the step 3 must be validated Series production Sections manufacturing : process adaptation with industrial Process tracking to optimize the time Leak test, tridim and RF measurement Development plan and validation tests according to the qualification phase B. POTTIN, A-C. CHAUVEAU
14
ANCILLARIES Brazing bi-material Cu-Inox without deposit + TEST cavity
B. POTTIN, A-C. CHAUVEAU
15
RF COUPLER B. POTTIN, A-C. CHAUVEAU
16
Status RFQ process validation (Mécachrome) : almost done
RFQ section 1 (Mécachrome) : Started Coupler (PMB) : manufacturing process validated, couplers started Tuner: 2D and spec finalisation. Tender started RFQ support system: 2D and spec to be closed eo january: Late Section transport system: Late RFQ tuning system (Sominex, Micro-contrôle, Court SAS) : On-going Test cavity (AMD): Due before eo january Test cavity support (Norcan, Court): On-going ESS bunker set-up (CEA): On-going Cooling system (Technitub): tender signed. Decision for update needed eo january Cooling system control system (CEA): On-going Assembly process and tools: On-going …. B. POTTIN, A-C. CHAUVEAU
17
REMAINING QUESTIONS B. POTTIN, A-C. CHAUVEAU
18
Tunnel delivery and assembly
Continuous work with ESS (thank you for good quality exchange with Walter, Georg, Nick…..) This exchange is necessary because there are continuous changes (good or not.) It’s not an option to implement the assembly process on the building because we need to see the interfaces, tunnel insertion, space aorund RFQ …. Saclay to validate strategy and tools Minimize the assembly time inside the tunnel Saclay RFQ support tools manutention bead pull Truck transport B. POTTIN, A-C. CHAUVEAU
19
Tunnel delivery and assembly
B. POTTIN, A-C. CHAUVEAU
20
COOLING SYSTEM Cooling pipes implantation
Possible changes from ESS: to decrease the distance between skid and RFQ not easy, and final decision must be done What is possible inside the tunnel ? Study by CEA specialist on going B. POTTIN, A-C. CHAUVEAU
21
LEBT AND MEBT INTERFACES EXAMPLE
Input plate Output plate Input and ouput plate design finished. Next step will be reviewing by ESS for validation B. POTTIN, A-C. CHAUVEAU
22
OPEN DISCUSSIONS Conditionning procedure and command control :
RFQ Security (Power limitless, temperature acquisition, vacuum level to stop RFQ conditionning…) LLRF strategy : who? How? When? We have pick up on the RFQ, we need to speak with ESS what we want ESS must do with pick up information C&C We need those systems OK to start conditionning !!!!! Not only assembly process: transport from CEA Delivery storage before tunnel insertion storage inside the tunnel manutention space inside the tunnel tools….. I think we need to find time to have small private meetings during these two days to be efficient (for example RF for RFQ) B. POTTIN, A-C. CHAUVEAU
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.