Pervious Parking lot Matthew Cockerham
2
Truck Traffic The trash truck has to turn on the pavement.
Concrete paving was installed where the truck turns.
3
Traffic Circle The traffic circle is constructed out of asphalt.
A flush concrete curb was installed to separate the flexible and rigid pavements.
4
Limited Site Access Site was soft and muddy.
The concrete trucks tires would have contaminated the clean stone. All of the concrete was placed with wheelbarrows.
5
Cold Weather Placement was in December.
Standard cold weather practices applied.
6
Clogging Sheet flow across the conventional pavement is carrying contaminants. Roof drains are discharging through the face of the curb.
7
Excavating The light pole bases were close to the pavement.
8
Saturated Pavement The last parking stalls hold water in the pavement.
There is no outfall designed.
9
Performance Very little raveling of surface. No random cracking.
Pavement percolates rapidly. Limited clogging at the edges.