2016 Mill and Overlay Project
Neighborhood Meeting April 28, 2016
2
Meeting Format Introductions Sing In Sheet Presentation Q & A Comments
3
Project Website Set up early May Contacts Layouts Schedules
4
Presentation City’s Pavement Management Program
Proposed Improvements ** Construction Impacts Schedule Project Funding Inquiries for Utilities
5
Pavement Management Plan
Goals/Objectives Address pavement degradation Manageable timeframe for completing the improvements Financially feasible Evaluate impacts on long-term maintenance operations
6
Pavement Ratings Pavement ratings on a 4-year cycle
Forensic report with maintenance recommendation Recommended roadway treatments Crack Fill Seal Coat Mill and Overlay *** Full Depth Reclamation Reconstruction Other
7
Pavement Management Plan
Process Prioritize Projects based on: Pavement ratings Traffic volumes Maintenance costs Determine Funding Sources Present to the Public and City Council
10
Proposed Improvements
Bituminous Mill and Overlay Old Birch Street and Holly Court Bituminous Reclamation Holly Drive Replace existing bituminous curb & gutter Maintain existing drainage patterns Match existing pavement widths
11
Project Location
12
Construction Impacts Emergency Vehicle Access Parking Mail service
Driveway access Mail service Garbage Roadway conditions Event coordination
13
Schedule Approve Plans/Authorize Bids April 11, 2016
Award Bids May 24, 2016 Construction June–September 2016 Substantial Completion - paving September 2016 Final Completion–clean up/restoration Spring 2017
14
Project Funding Project Construction Budget $350,000 City’s annual PMP funds – NO assessments Municipal utility extension is NOT included - requires a petition and would include assessments. Typically with a reconstruction project.
15
Questions?