Download presentation
Presentation is loading. Please wait.
1
Grouting using PUR in extreme geological and weather conditions in Iceland
By Tomasz Najder, Ph.D Civ. Eng. Senior Consultant, Najder engineering, SE Saltsjöbaden Sweden 1 ready
2
Location of the projects
Breiđalsheiđi and Botnsheiđi Project Héðinsfjarðargöng Project Kárahnjúkar Hydropower Project Location of the projects 2 ready
3
3 Icelandic geology 3 2 cm/year 2 cm/year Nord-America Plate
Eurasia Plate Eurasia Plate Icelandic geology 3 press ready 3
4
Case study – Ísafjörður Project (road tunnels): grouting for rock sealing and stability. Conditions: very high water ingress from the fault under high water pressure into D&B tunnels Water pressure ~ approx. 60 bars Water inflow ~ 50 l/s/hole Water temperature ~ +20 ºC ready
5
Limited rock permeability for cement based grouts
Ísafjörður Location of Ísafjörður press ready
6
fault 2 Leakage l/s !!! No probe holes !!! fault 1 press ready
7
X = wash-out Rock grouting in Breiđalsheiđi and Botnsheiđi (Iceland)
Water pressure ~ approx. 60 bars Water inflow ~ 50 l/s/hole Water temperature ~ +20 ºC fault water Water velocity ~ 3m/s = wash-out X ready Cement grouting ????
8
mineral component (OMC) (sequential grouting)
1-component PUR Hydrophilic PUR – limited range of penetration! components A+B Component B - polyisocyonate 2-component PUR Component A - polyol components A+B components A+B Proposal: 2-component PUR or mineral component (OMC) (sequential grouting) press press press ready
9
Final result of grouting
Drilling and grouting pattern for Fault 2 Drilling and grouting pattern for futher “normal” chainage Fault 2 Inserting of mechanical packers in high water pressure conditions Final result of grouting Drilling for grouting press ready
10
Case study - Kárahnjúkar Headrace Tunnels: grouting for rock sealing and stability. Conditions: very high water ingress under water pressure of 20 bars into D&B and TBM tunnels. Cold water (+1 °C °C ). Very wide faults filled with clay and boulders ready
11
Kárahnjúkar Hydropower Project 2006-2008
Diversion Tunnels at dam 2.4 km (Kar 14) Headrace Tunnel 53.0 km (Kar 14) Grouting galleries at dam 0.5 km (Kar 14) Cable tunnel km Hraun Diversion 2.0 km Grjótá Diversion km Adit km (Kar 14) Adit km (Kar 14) Adit km (Kar 14) Surge Tunnel km (Kar 14) Drainage Tunnel 0.7 km (Kar 14) Penstocks km (2x) Access to Powerhouse 1.0 km Tailrace Tunnel km Total Tunnel Length: 73.0 km (D&B=10 km, TBM=63 km) Kárahnjúkar Hydropower Project 11 press press ready 11
12
TBM D&B press ready
13
Low temperature problems with cement based grouts
Climate Low temperature problems with cement based grouts ready
14
14 14 Gravel and clay filled fault at the cutterhead
Stage 2: huge water ingress from the fault; TBM cutterhead passed the fault Stage 3: wash-out of the fill from the fault (TBM) Stage 4: material washed out from the fault Stage 1: TBM in progress in water scenery 14 ready 14
15
Wide fault (coobles “cemented” with clay)
Question of time.... Water:+1 °C ÷ +65 °C press ready
16
16 Bimbar inflatable reusable packers after one inserting operation
Double set of BVS inflatable, disposable, none drillable packers How to insert the packer ???? press ready 16
17
One-component PU resins
Fast reacting two-component PU resins Fast setting two-component urea-silicate resins (foams) ready
18
Fault above tunnel invert (D&B) after wash-out of fill material
ca. 8m Fault above tunnel invert (D&B) after wash-out of fill material ready
19
Solution chosen → urea – silicate foam
SPECIFIC CARACTERISTIC IN PRACTICAL APPLICATION WILKIT FOAM T GEOFOAM PUMPING SYSTEM SIMILAR INJECTION RATIO 1/1 EXPANSION RATIO (V) FILLING DRY HOLES AT 10º C AT 25º C V 20 V 40 V 15 V 30 RATIO OF PERFORMANCE IN VERY HIGH WATER FLOW AS SEEN IN KARAHNJUKAR % > % COUNSELLED TO INJECT AGAINST HIGH WATERFLOWS + +++ TOUGHNESS OF FOAM FIRE PROTECTION EURO CLASS B2 ready
20
Case study - Héðinsfjarðargöng Project (road tunnels): grouting for rock sealing and stability. Conditions: very high water ingress under water pressure of 40 bars into D&B tunnels. Cold water (+2 °C). Very wide faults filled with clay and boulders. Sections with unstable tunnel’s faces and crowns ready
21
Water inflow into Icelandic rock mass:
- Ólafsfjördur Tunnel ready
22
Ólafsfjörður Tunnel. Water in front of the face: water ingress in the hole ~ 50 l/s
Ólafsfjörður Tunnel. Water in front of the face: water ingress ~ 5-30 l/s/hole ready
23
Water ingress in heavy leaking zones
ready
24
Héðinsfjarðargöng Project - leakage at the face of Ólafsfjördur Tunnel
Héðinsfjarðargöng Project – face collapse at Ólafsfjördur Tunnel ready
25
Fault above tunnel invert before wash-out of fill material
Fault above tunnel invert after wash-out of fill material ready
26
Fault above tunnel invert after PUR pre grouting
ready
27
Large fault grouted with PUR (Ólafsfjörður Tunnel)
Stone from the face grouted with PUR - solid form like amber of PU resin (Ólafsfjörður Tunnel) Large fault grouted with PUR (Ólafsfjörður Tunnel) Stone from the face grouted with PUR - solid form like amber of PU resin (Ólafsfjörður Tunnel) ready PUR as “hard” amber (Ólafsfjörður Tunnel)
28
λ WilkitFoam, GeoFoam λ = 15÷30 x CarboPur λ = 3÷5 x Factor λ 28
wash-out effect ground water velocity 15 mm/sec De Neef Scandinavia AB 1991 Factor λ = relation between volume of material grouted / material still remaining in the rock mass after hardening vs. ground water velocity in mm/s press press ready 28
29
Water is enemy to cement based grouts
(dilution) water cement particles ready 29
30
PU resins love water for reaction
polyurethanes water ready 30
31
PUR and OMR OPC or PUR ??? Hydraulic conductivity < Lu ≈ 10-15
Winter conditions (temp ºC) High water velocity Big caverns press ready
32
Thank You for Your attention!
THE END Thank You for Your attention! ready
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.