Presentation is loading. Please wait.

Presentation is loading. Please wait.

Project Estimates 2/11/2008 By Mark Lutgen.

Similar presentations


Presentation on theme: "Project Estimates 2/11/2008 By Mark Lutgen."— Presentation transcript:

1 Project Estimates 2/11/2008 By Mark Lutgen

2 Why is estimating important to a PM?
Establishes trust and credibility in YOU Sets and manages expectations Project funding depends on the estimates Projects rarely have an open check book Project contacts depend on the estimates Project profitability is at risk Estimates define probable outcomes for future activities

3 You already know how to estimate…
Estimating Includes: Project costs Project schedule Project resources You already know how to estimate…

4 Our project – Ski Trip Scope 7 skiers / riders and their families
3 days (departure to return) Location TBD Project Manager is responsible for organizing and paying for transportation, lodging, lift tickets and lessons (no meals, entertainment or equipment)

5 Our project – Ski Trip Objectives (determined through interviews)
Want to learn how to ride (get down a green run without falling) Want to have a luxurious spa experience (like the spa at the St. Julien) Want to get a break from the project and not talk about work for three days Want child-care for my young kids while my wife and I ski together Budget is $12,000

6 How much will it cost? Transportation $? 1 @ $? ea way + gratuity
Lift tickets $? $200 for 3 day pass Lodging $? ? rooms (2 per $?/night Lessons $? $90/day for group lessons Subtotal $? Total $?  range +/- 20%

7 How long will the trip take?
Load Bus 0.5 hr Drive time 3-5 hrs Rest break 0.5 hr Unload / check-in 1 hr Sub total 5-7 hrs Reserve 1 hr Total 6 – 8 hrs each way

8 You already know how to estimate
What you may still need… Process / methodology Organization and format Effective use of estimates Nuisances Industry specific information Practice and experience Delegate where appropriate

9 We will focus on this type
Types of estimates Analogous / Benchmarks Similar projects Scale to fit (e.g., 100.6) S.W.A.G’s Very common when Rough Order of Magnitude is ok Parametric $ per unit hr per unit Bottoms up Detailed WBS driven Greatest $$ to develop We will focus on this type Each method has a time and place

10 Understand the estimate accuracy
State estimate as a range Use contingency or reserve to increase confidence of single point estimates (Monte Carlo) Accuracy is proportional to time / effort invested

11 Where to start… Scope definition WBS Deliverables
Work required to achieve business objective WBS Define the activities and deliverables Decompose to a level needed for the estimate Bottom’s up estimates vs Analogous estimates

12 Time & Resource Estimates

13 For bottoms-up- 1st - define the activities
Identifies deliverables at lowest level of the WBS If WBS is not available… brainstorm w/ team Decomposed to schedule activities Basis for estimating, scheduling, and controlling Rolling Wave Planning Near term – activities detailed Far term – activities high level Decomposition Breaking work into smaller more manageable pieces

14 Use a Work Breakdown Structure

15 2nd - define sequence Identifying logical relationships between activities Precedence Diagramming Methods (PDM) Activity on Node (AON) Arrow Diagramming Method (ADM) a.k.a. Activity on Arrow (AOA) Start / Finish relationships Finish to Start (most common) Start to Start Start to Finish Finish to Finish Lead = Starts earlier Lag = Starts later / delayed start For small projects, identification, sequence, and development may be concurrent

16 Model Activity Sequences
Activity on Node B E A C D Arrow Diagramming Method - Dummy Activities B A C D E

17 3rd - estimate resources
What resources required Amount of each resource required Resources People Equipment Materials

18 Activity Resource Estimating
For each activity… How many resources are needed How long Expert judgment / experience Use team members Use Functional managers Published estimating data Bottoms up estimate Break it down into smaller and smaller pieces until you can establish a ‘good enough’ estimate Benchmarks / similar projects

19 4th - estimate duration The goal is to determine the duration of each activity Number of resources Elapsed time Expert judgment (Delphi technique) Analogous – (similar projects) Parametric – (regression, scaled, time/unit) Three point estimate Program Evaluation and Review Technique PERT = 1/6[Pessimistic + 4(Most Likely) + Optimistic] Std Dev = (P-O)/ 6

20 5th - build / develop schedule
Iterative process to develop start / finish dates Monte Carlo Analysis Resource Leveling Moves resources from non-critical to critical path Schedule Compression Crashing (Increase $$ to reduce duration of CP) Fast Tracking (Overlapping phases) Critical Path Method Float (a.k.a. Slack) - Total Float, Free Float Early Start/Finish Late Start/Finish Forward / Backward paths Consider schedule reserves on the critical path

21 Schedule Development – CPM Examples…

22

23 6th – Compile resources Roll up resources across entire project
List resources by time period Scheduling software does this for you 

24 Cost Estimates

25 Cost estimating Break into smaller and smaller pieces until you have a benchmark or basis that provides an acceptable level accuracy or confidence Benchmarks Usually high level (parametric) Basis Usually itemized or based on deliverables Use basis and adjust for your specific requirements Organize budget in alignment with WBS Activity based Resource based *

26 Where do you get the information?
Historical projects Experience Project Database Vendors Literature / Trade Journals Internet Catalogs Experts / Consultants Build your own data base / file

27 Budget busts are usually items that we not included
Be thorough…. State assumptions Helps others review Helps PM manage changes Identify your biggest budget risks and mitigate State exclusions Include all applicable costs Travel, training, taxes, freight Include project benefits (savings) too!!! Budget busts are usually items that we not included

28 How to use contingency…
Always use it (contingency) Use contingency to cover uncertainty in approved scope Get additional funding for new scope Line item vs. bottom line contingency Percentage depends on level of certainty Rule of thumb – use 10% if scope is defined Learn your industry norms Engineering projects 50-100% with ROM 10-30% after 20-30% design 5-15% after 60-90% design

29 How to use contingency…
Use Monte Carlo for more robust method Develop nominal estimate (50% confidence interval) Develop risk register List risks Best / probable / worst case $$ impact Run Monte Carlo simulation Contingency / Mgmt Res = 90% interval – 50% interval Reserve Mgmt Contingency Base Estimate 50% Confidence 90% Confidence Use if high degree of certainty is needed

30 Delphi technique is good in a pinch
Process to converge expert opinions Information is not available elsewhere (i.e., 1st of a kind) Information is costly to develop Real example of program cost estimates… Delphi took < 5 hours 5% Eng required over 1000 hours Which is better?

31 Estimating is simple, doing it well is the challenge!
Project costs Project schedule Project resources


Download ppt "Project Estimates 2/11/2008 By Mark Lutgen."

Similar presentations


Ads by Google