City of Whitehorse Capital Projects & Service Requirements Peter O’Blenes, P. Eng February 21,2017
2
Main 2017 Capital Projects New Operations Building * $45,720K
Marwell Lift station Upgrades $2,400K Hidden Valley Storm Pond expansion $330K Wheeler Street West - Reconstruction* $5,150K 6th Avenue - Reconstruction* $3,700K 4th Avenue - Asphalt Overlay $1,000K Lewes Blvd Sanitary Lines CIPP $200K Irrigation at Whistle Bend $600K
3
New Operations Building
4
New Operations Building
New Operations building to replace Municipal Service Building (MSB) Capital Cost: $45,720K (Approx $15,000K in 2017) Location: Range Road / 2 Mile Hill Layout confirmed and detailed 50% Project started in 2016 with entrance road added Target Project End: Feb 2019 - Relocate to new Operations Building - Shut down Municipal Service Building
5
Wheeler Street – Reconstruction*
$5,150K project includes the following: Upgrades to water / sewage / drainage infrastructure New roadway and sidewalks
6
Marwell Lift station Upgrades
$2,400K project includes the following: Internal piping / valve replacement New lift station bypass Addition of a Surge Protection System Addition of controls & instruments
7
4th Avenue – Asphalt Overlay
$1,000K project includes the following: New asphalt from Main Street to Robert Service Way Includes line painting
8
Potential Service Requirements
Traffic Signal Upgrades Repair Permanent Cross Walk Markings Water / Soil Testing Extraordinary Snow & Ice Control Window Cleaning Carpet Cleaning Road line Painting Waste Oil Reclamation Sidewalk Upgrades Tree Cutting / Bush Clearing Flower / Trees supply & some planting Outdoor Toilet supply / service
9
Thank You Questions? Annual Industry Conference February 21,2017