Guildford Baptist Church Phase 4 – Sept 2017 “kicking on to the finish” Building Redevelopment Project
2
Building Redevelopment Project
a light shining out, drawing people in
3
Since March….. - considered and reviewed over 80 design issues with ReFormat, Caldera and other specialists - Looked at opportunities to reduce costs and simplify design - Looked at the detailed design requirements for the auditorium
4
Lighting Sound systems and acoustics
5
Two more Phases of Work 4A – ground floor kitchen, toilets, lantern
4B – auditorium, front extension, external Work at ground floor now includes completion of this
6
Proposed scope of work for next phase (Phase 4A)
Part of Auditorium; Lantern roof Lantern windows Side windows Window and blind controls Lighting in lantern External cladding to auditorium Auditorium stays in use for services Ground Floor; Kitchen and food store Two store areas Gents and Ladies toilet Disabled toilet & wet room Dining space: lighting ceiling, acoustic partition Underfloor heating Drainage Rainwater harvesting
7
Phase 4A ACOUSTIC PARTITION GLASS PARTITION LADIES TOILET DRAINAGE &
UNDERFLOOR HEATING DISABLED TOILET DECORATION GENTS TOILET STORE CEILING AND LIGHTING STORE NEW DOOR KITCHEN
8
Dining space – toilets - kitchen - stores
Phase 4A Store areas Male, Female, disabled toilets Kitchen Servery Dining Dining space – toilets - kitchen - stores
9
-extends into snug area
Kitchen Layout -extends into snug area - includes servery Work at ground floor now includes completion of this
10
Phase 4A - Auditorium Lantern roof Lantern windows Side windows
Window and blind controls Lighting in lantern External cladding to auditorium Gutters & rainwater tank Auditorium stays in use for services
11
Phase 4B Auditorium Lighting, AV/IT Seating Parent & toddler
room (balcony) New entrance Media studio (balcony area) Flat area with flexible staging Ventilation with some cooling Auditorium
12
Phase 4B Servery Lounge area Terrace Ramp
Reception Terrace Ramp Servery – lounge - extension – external areas
13
Auditorium design concept images
More information on phase 4B and auditorium at future meeting
14
Cost for 4A Will be;- £1,000,000 (as approved at church meeting)
- This assumes a start in 2018
15
What next; Gift day 15 October
Complete update of drawings and specification documents When most of funding in place get tender from Caldera and check costs Phase 4B – as soon as possible after phase 4A.
16
“kicking on to the finish”
Building Redevelopment Project “kicking on to the finish”