Infrastructure Delivery Management Toolkit: 2010 Edition
Delivery Process 1: Portfolio Management Infrastructure Planning: The U-AMP Sonny Schmidt development through partnership
2
The IDMS DP1: Portfolio Management DP2: Project Management
Prov Infr Strat DP1: Portfolio Management DP1-1 Infrastructure Planning DP1-2 Programme Management Develop U-AMP (including prioritised MTEF works list) Develop C-AMP (including work plans) Dev Proc Strat Develop/review IPMP Manage Implementation G1(a) G1(b) G2 PC1 PF1.4 PF1.3 PF2.1 PF2.2 PF2.3 PF3 PF4 PF5 DP2: Project Management DP2-1 Planning (Develop IPIP) DP2-2 Design DP2-3 Works DP2-4 Close Out Package prep Package definition Works planning Design developt. MFC Info Con/Del works Handovr works Project Close Out Update Asset Register G3 G4 G5 G6(a) G6(b) G7 G8 PC2 PC3 PC4a PC5 PC4b T1 T2 Delivery Gates: G1a – Approved U-AMP (incl MTEF list) G1b – Approved C-AMP (incl Works list G2 – Accepted Procurement Strategy G3 – Accepted Strategic Brief G4 – Accepted Concept Report G5 – Accepted Design Development Report G6 a – Accepted Production Information G6b - Accepted Manufacture, Fabrication & Construction information G6c ?? – Sonny to confirm if required G7 – Accepted works in accordance with requirements G8 – Works taken over by User, complete with record information Procurement Milestones: PC1 – Procure PSP for Programme Management, incl strategic procurement services PC2 – Management Contractor / Framework Contract PC3 – Design and Construct PC4a – Design by Employer (Consultant procurement) PC4b – Design by Employer (Contractor procurement) PC5 – Develop and Construct Performance Management Processes: PF1.1 – Develop Indicators from Strategic Plan objectives PF1.2 - Develop Indicators from Programme Implementation Plans and Budgets PF1.3 – Develop Indicators from Project / Operational & Maintenance Plans PF1.4 – Link Indicators and RACI to individual Performance Agreements PF2.1 – Monitor & Evaluate Inputs, Activities and Outputs against plan PF2.2 – Monitor & Evaluate Outcomes against plan PF2.3 – Monitor & Evaluate Impacts against plan PF3 – Publish Performance Information PF4 – Review / Appraise individual performance PF5 – Take management action Triggers: T1 – Trigger – To O&M on requirements for works that will be delivered T2 – Trigger – To other Dep’s on requirements for other services (staff, books (Edu), pharmaceuticals (Health), etc) PF1.4 PF1.3 PF2.1 PF2.2 PF2.3 PF3 PF4 PF5 DP3: Operations & Maintenance DP3-1 Recognise & accept assets DP3-2 Mobilisation for Facilities Mgt DP3-3 Operations DP3-4 Maintenance DP3-5 Demobilise Facilities Mgt G8 PF1.4 PF1.3 PF2.1 PF2.2 PF2.3 PF3 PF4 PF5
3
User and Custodian Portfolio Management Outputs
organisations Custodian U-AMP Construction procurement strategy IPMP Organisation and Support plan Monitoring reports Recommended actions C-AMP Work Plans Portfolio Management outputs by responsible organisation The Implementing Agent is managed by the User on the basis of the SDA between the organisations and the IPIP it submits
6
Infrastructure Planning Methodology
Generically the planning process for both asset solutions and organisational capacity discussed in this module are based on identifying needs, comparing these to current services and facilities available and developing solutions to any gaps.
7
Gaps to be determined: Space Gaps Utilisation Gaps Functional Gaps
Basic 3 Gaps to be determined: Space Gaps Utilisation Gaps Functional Gaps Condition Gaps Efficiency Gaps Other Gaps: Capacity gaps Funding Gaps
8
Project Cost Estimating & Budgeting
SCOA: Category of Expenditure: Capital: Acquisition (new, additions) Upgrading, Alterations, Conversions Renovation, Refurbishment (Rehabilitation) Disposal Current: Routine maintenance Staff, systems Based on Life Cycle Costing User organisation prepares estimates – scope, schedule, management capacity, funds Good collaboration with Custodian and Implementing Agent will improve estimates
9
Life Cycle Costing (1) All costs (estimated & actual) over the life cycle of an asset are taken into consideration in order to make future decisions about the asset. Includes: capital e.g. initial acquisition cost and future upgrades, rehabilitations operations and maintenance This will help make the decision about whether to continue using or acquiring an asset to provide services.
10
Life Cycle Costing (2) The asset is obtained at an initial acquisition cost. Ordinary use of the asset leads to wear and tear, requiring preventative maintenance to ensure that the asset remains above its minimum required performance level After an initial period preventative maintenance is no longer able to ensure the minimum level of performance and the asset requires renovation/rehabilitation. The renovation restores the assets to its original condition. Preventative maintenance now continues During the asset’s life it may be upgraded or extended, increasing the value of the asset The asset could be renovated/rehabilitated a number of times. However (typically at the end of the asset’s planned life), systems supporting the asset can be expected to fail. The asset now requires major rehabilitation/refurbishment which may involve a major overhaul of systems and/or replacement of these systems or components of systems Once the refurbishment has been completed a new economic life cycle begins.
11
Estimate for new infrastructure asset
Typical estimate for a single new asset showing; Acquisition Maintenance Rehabilitation (every 5 years in this case) Organisation and support costs
12
Portfolio Budget build up
Based on estimates for all assets, build up long term budget Portion of the budget approaching the MTEF period will be more accurate as feasibility studies are completed.
13
“Programme View” of Budget
Summary budget for previous 3 asset organisation Can be re-ordered to show “Asset View” – costs per asset in single line Different views required for different reporting requirements
14
The Need for Budget Revision
Project Budget The “Control” Budget? Financial Year Budget: Demand for work exceeds available fund: Re-schedule work Apply robust Prioritisation Criteria Document prioritisation decisions Work is not “cancelled (deleted form works list) – only rescheduled Ensure that current contractual work is accommodated effectively
15
Budget Revision due to Progressive Improvement of Cost Estimates
Cost estimating through the Project Life Cost Estimate Name Gateway Process stage Conceptual Infrastructure Planning Pre-feasibility Package Preparation Preliminary (Feasibility) Design Development Tender Design Documentation Definitive Works Final Close Out Initially work (projects/jobs) enter list by means of a pre-feasibility study As work as included in MTEF period estimates based on feasibility study Accuracy improved as work advance through implementation phases until the costs are 100% known at final account stage
16
Alignment of Budget and Infrastructure Planning Cycles (1)
Expenditure characterised by spike (hockey stick!) Resulting in: Roll over of funds Over expenditure Value not achieved Incorrect services procured Cabinet approved framework (2007) Allows for due process to take place Framework know as the “Alignment Model”
17
Alignment of Infrastructure Planning and Budgeting (1)
Infrastructure cycle takes 4.5 years to complete Infrastructure planning now informs the budget cycle The correct work is now funded (not just funds spent on selected work)
18
Summary: Infrastructure Planning
User: U-AMP (G1a) Consider service delivery mandate Infrastructure required (“Gaps”) Life cycle costs Collaboration with custodian First gate (2 halves) in CIDB Gateway Process User will fund all infrastructure work Custodian will assist with services such as asset register, condition assessments, life cycle costing plans for each asset Custodian will co-ordinate work across all users
19
Thank you 2006 Ver planning philosophy remains the same
GIAMA requirements added – essentially a combination of the outputs of each of the steps in the roadmaps Good working relationship between Custodian and User essential Flows now linear – easier for people to use