SPS EYETS 2016/2017 Planning meeting (No.4) 12/10/16
David Mcfarlane EN-ACE D. Mcfarlane
2
Topics EYETS master schedule. Key Dates & schedule for 1st week.
Works during the Xmas Vacation. Yet another request from EPC. Future meetings & presentation of group planning. Other presentations. (EN/STI + UA9, SMB/SE & EN/HE) ECRs. External visitors. Access rights and safety equipment. Important Contacts. Round Table. A.O.B. EN-ACE D. Mcfarlane
3
Extended YETS 2016-2017 Reference time :
13 Weeks from Beam off until we close the SPS (12th December until the 24th March) EDMS: EN-ACE D. Mcfarlane
4
Key dates Beam off at 06:00 on Monday the 12th December
Access into BA7, TI2, TAG41, TAG42 & TI8: Monday the 12th December until Friday the 24th March 2017. 13 weeks of access. Access into BA3,4,5 & 6: Thursday the 15th December until Friday the 24th March 2017. 12.4 weeks of access. XMAS holidays: Thursday the 22nd December to Wednesday the 4th January inclusive Access into BA1 & BA2: Thursday the 5th January until Friday the 24th March 2017. 11.4 weeks of access. 4 weeks foreseen for EPC tests and cold-checkout by OP. SPS will take beam from the PS on Monday the 24th April 2017, followed by 1 week for beam setup. SPS ready to give beam to the LHC on Monday the 1st May 2017! EN-ACE D. Mcfarlane
5
Current schedule for week 1 (12th to 16th December)
Monday 12th December Beam off 06:00Hrs Access possible in BA7, TI2, TAG41, TAG42, TI8. All water and power to remain on (Machine is in standby) SPS ring closed to everyone except: RP: will survey the tunnel Magnet team: to remove covers on the magnets. Tuesday 13th December Magnet team conduct tests SPS closed (to everyone except Magnet team) Wednesday 14th December Thursday 15th December Water can be cut and the machine electrically isolated BA1 and BA2 remain closed for RP cool down BA3, BA4, BA5, BA6, BA7 are open for general access Friday the 16th December BA3, BA4, BA5, BA6, BA7 are open for general The access system will be switched over to CSA control The SPS is effectively still in run mode. General access into the SPS begins. EN-ACE D. Mcfarlane
6
Activities in the SPS during the Xmas Vacation
EN-HE: BA5 Underground Revamping ECX5 - RP support needed - 5 days / 6p. EN-EL: BA4 Surface Replacement of a control unit in the ESD1/K5 switchboard - 8h - 2p. BA5 Surface De-cabling campaign. EN-CV BA6 Surface: Replacement of demineralised water and chilled water cooling station PLCs (including input and output cards). BA80 Surface: Consolidation of ventilation control cubicle
7
Activities in the SPS during the Xmas Vacation
Surface works only. Access to tunnel required EN-CV: Consolidation of ventilation control cubicle EN-EL: Replacement of a control unit in the ESD1/K5 switchboard. EN-CV: Replacement of demineralised water and chilled water cooling station PLCs. EN-HE: Renovation of the over head crane (ECX5) EN-EL: De-cabling campaign.
8
Another Request from EPC
Voici un mail pour décrire la tache de commissioning des 5 nouveaux bypass (type N09) de TT20. Il s’agit des convertisseurs ci-dessous (disposés au BA2): RPPCG.BA2.SBYH2109 RPPCG.BA2.SBYH2113 RPPCG.BA2.SBYV2103 RPPCG.BA2.SBYV2113 N09.BA2.SPARE1 Premièrement, pour tester les bypass, il est nécessaire de faire fonctionner la demi-station MBE.2103M (type R120), pour alimenter les bendings de TT20. Les bypass ne permettent que de soutirer du courant sur certains de ces dipôles. Lors de nos tests, tout le travail sera localisé en surface, mais nous enverrons du courant dans les dipôles de TT20. Nous aurons également besoin d’avoir accès au faux-planchés pour le déplacement des câbles DC (des anciens vers les nouveaux convertisseurs). Il y a une restriction de passage uniquement aux piétons dans l’environnement proche des anciens et des nouveaux bypass. Et donc une interdiction d’accès sous les faux-planchés autour de ceux-ci sans autorisation. Les services absolument nécessaires durant la période de test sont: - Pré-requis : Autorisation d’accès au faux-planchés HSE - Cooling dans le BA2 opérationnel pour le refroidissement des convertisseurs (1/2 station et bypass) EN-CV - Refroidissement des dipôles de TT20 opérationnel EN-CV - Distribution électrique déconsigné au BA2 : EN-EL et TE-EPC Départ 18KV : EMD112/A2 Départs 400V (R120): EBD2/A ; EBD217/A2.04 (chaufferette) Départ 400V (bypass): EBD2/A - Concernant les EIS, demande de la sortie de chaine (SPS n°10) du convertisseur principal. TE-EPC Et pour finir, le balisage, il faudra donc : - identification des tests aux entrées du BA2 (par TE-EPC), - un balisage devra être mis en place dans le tunnel près des dipôles (par TE-MSC) EN-ACE D. Mcfarlane
9
Commissioning des x5 BYPASS de type N09 deTT20
SPS closed TT20 closed EN-ACE D. Mcfarlane
10
SPS Water Availability
Location De-min Circuit stop date Primary Water Off De-min Circuit start date Comments BA1 20/12/16 09-13/01/17 17/02/17 (Main Magnet & Power supplies for Kickers) Remaining circuit 13/03/17 BA2 14/12/16 (end) 06-10/02/17 27/02/17 Available for users from 06/03/17 BA3 19/12/16 16-20/01/17 (inc BEQ2 & BEQ3) 13/03/17 BB3 16-20/01/17 (except RF Skid) BA4 15/12/16 (end) 09-13/01/17 (Coldex) Remaining circuits 13/03/17 BA5 16/12/16 (end) BA6 14/12/16(end) 16/12/16 – 16/01/17 (SF1) Available for users from 13/03/17 BA7 12/12/17 BA80 19/12/16 – 16/03/17 EN-ACE D. Mcfarlane
11
Test AUG/ Access Tests (Access will be blocked)
Location AUG test Access tests Radiation interlock tests SPS Auto Transfer Test 4th & 5th February 16th December (15:00 to 17:00) 29th March (chain 1) 30th March (Chain 2,3,4,5) BA1 13th February 23rd January (AM) BA2 15th February 23rd January (PM) BA3 16th February 24th January (AM) BA4 ECX4 TAG42 28th February 24th January (PM) 25th January (AM) 25th January (PM) 14th March (1 day) BA5 ECX5/ECA5 1st March 26th January (AM) 26th January (PM) BA6 20th January 27th January (AM) BA7 TT61 27th January 30th January (PM) BA80 4th April 30th January (AM) 13th March (1 day)
12
Future meetings It has been requested by the group leaders for each group to present their planned works to the coordinators of each machine. Therefore the table below will show which group will present at what SPS planning meeting. Date of meeting Presentation 1 Presentation 2 Presentation 3 Meeting 2 (7th Sept) EN/CV EN/EL BE/ICS Meeting 3 (28th Sept) BE/BI TE/VSC + Coldex BE/RF + Crab Cavity Meeting 4 (12th Oct) EN/STI + UA9 SMB/SE EN/HE Meeting 5 (26th Oct) TE/ABT TE/MSC EN/ACE (Survey) (Cabling) Meeting 6 (9th Nov) BE/CO TE/EPC DGS/RP Meeting 7 (23rd Nov) BE/OP EN-ACE D. Mcfarlane
13
Other presentations EN-ACE D. Mcfarlane
14
SRRs and ECRs for the SPS
SPS planning and coordination meeting for EYETS 2016/2017 SRRs and ECRs for the SPS Sonia Bartolomé Jiménez EN-ACE-CL – 12th October 2016
15
SRRs and ECRs: reminder
All changes to the machine that will impact the beam shall be documented by SRRs/ECRs: SRR: Space Reservation Request (“light ECR”) ECR: Engineering Change Request Templates available on: To be sent to the SPS configuration manager: or Sonia Bartolomé Jiménez EN-ACE-CL – 12th October 2016
16
SPS ECRs for EYETS 2016/2017: status
LIU-SPS project EDMS Number Doc type Title Revision Shutdown LIU EDMS Status Authors SPS-JHCAA-EC-0001 ECR Construction of concrete support structure for new LIU beam dump in SPS ECX5 0.1 EYETS16/17 YES Under Approval Richard Morton (SMB/SE) SPS-V-EC-0005 Modification of the SPS sectorization in long vacuum sectors (arcs) Chiara Pasquino (TE/VSC) SPS-BCTW-EC-0002 BCTW for LSS5 of the SPS ring (EYETS ) Lars Soby (BE/BI) SPS-VC-EC-0001 SPS amorphous carbon coating in EYETS Mattias Van Gompel (TE/VSC) SPS-BCTW-EC-0002 discussed at the LIU-PLI meeting on LIU approval pending on acceptance by Impedance WG. SPS-VC-EC-0001 discussed at the LIU-PLI meeting on Approved by LIU. Ready for presentation at the IEFC. SPS-V-EC-0005 and SPS-JHCAA-EC-0001 will be discussed at the LIU-PLI meeting on Sonia Bartolomé Jiménez EN-ACE-CL – 12th October 2016
17
Sonia Bartolomé Jiménez EN-ACE-CL – 12th October 2016
SPS ECRs for EYETS 2016/2017: status Non LIU-SPS project EDMS Number Doc type Title Revision Shutdown LIU EDMS Status Authors SPS-B-EC-0003 ECR Proposed layout changes for BI detectors in the SPS domain during the EYETS 0.0 EYETS16/17 NO New Lars Jensen (BE/BI) SPS-Y-EC-0001 Integration of RP monitors to interlock SPS chains 1, 2 and 4 0.1 Under Approval Markus Widorski (HSE/RP) ACC-RFB-EC-0001 New Table Format for Function Generator/Controllers (FGC) Quentin King (TE/EPC) SPS-LJ-EC-0006 HL-LHC Crab-cavity infrastructure in SPS: tunnel areas (EYETS ) 0.2 HL-LHC Giovanna Vandoni (BE/RF) SPS-TIDVG-EC-0001 Modifications to the TIDVG during 2016 Paula Rios Rodriguez (EN/STI) SPS-Y-EC-0001: Two rejections. Discussions on going. ACC-RFB-EC-0001: Ready for presentation at the IEFC. SPS-LJ-EC-0006: New version 0.2 circulating for comments. SPS-TIDVG-EC-0001: Integration needs to be checked. Sonia Bartolomé Jiménez EN-ACE-CL – 12th October 2016
18
External Visitors If you have any external personnel needing to access the SPS for visits before starting works then you need to read the following document: "Etapes à suivre pour organiser des visites professionnelles dans les installations faisceaux" by CHRISTELLE GAIGNANT Link: EN-ACE D. Mcfarlane
19
Access rights and safety equipment
EVERYONE who enters the SPS MUST have the following: Completed the correct courses. (sir.cern.ch) CERN Safety Introduction. Electrical Safety Awareness. (19 choices) Self Rescue Mask Training. (4 choices) CERN – Beam Facilities. SPS – Machine. The correct access authorisation (via EDH). CHECK YOUR ACCESS RIGHTS HAVE NOT EXPIRED!!!! Zone Code “SPS” for access into the SPS Zone Code “NA_TARG” for access into BA80 Zone Code “TAG41 - AWAKE (ex-CNGS) (TAG41)” for access into the old CNGS areas Zone Code “SPS-KN-000” for “Autorisation conduite RTL” Zone Code “SPS-KN-001” for “SPS Shutdown Padlock” (only used during Long Shutdowns) Safety shoes. Biocell. Electronic dosimetre. Passive dosimetre. (All contractors must have an additional company passive dosimetre!!) Helmet plus Light. A valid approved IMPACT. (with their name included on this IMPACT) They must know the number of this IMPACT. Please note that personnel are not allowed to work in the tunnel alone!! EN-ACE D. Mcfarlane
20
Important Contacts Useful Contact Numbers SPS Coordination Team
David MCFARLANE Franck BAIS – Aurelio Berjillos BARRANCO Control Room SPS CCC – 77500 TI CCC – 72201 CSA RP Christophe Tromel – Angelito Herve – Nadine Conan (BA1) – Kurt Weiss (BA7) EROS Engineering Referent for Operational Safety Emmanuel Paulat – John Etheridge EN-ACE D. Mcfarlane
21
Round Table (1) Group Contact Persons Comments EN/EL EN/CV EN/STI
Guillaume Gros Denis Ribiollet Jeremy Blanc EN/CV Bill Bannister (Water) Vivien Koutcheroff (Ventilation) EN/STI Jerome Lendaro Simone Montesano TE/MSC Jeremie Bauche Pascal Catherine TE/EPC Karsten Kahle (High power) Gilles Le Godec (Medium power) TE/VSC Jose A. Ferreira Anthony Harrison Chiara Pasquino TE/ABT Francesco Castronuovo (Kickers) Cedric Baud (Septas) BE/RF Eric Montesinos Christophe Renaud Gino Cipolla BE/BI Raymond Veness Morad Hamani BE/CO Magnus Bjork IT/CS Maryse Da Costa EN-ACE D. Mcfarlane
22
Round Table (2) Group Contact Persons Comments BE/ICS HSE/RP EN/ACE
Didier Vaxelaire (Access) Denis Raffourt (Fire detection) HSE/RP Christophe Tromel Angelito Herve EN/ACE Patrick Bestmann (Survey) Sonia Bartolomé (Integration) Fred Galleazzi (Intergration) Emmanuel Paulat (Safety) EN/HE Patrick Vallet (Transport) Nicolas Perez (Lifts) BE/OP James Ridewood Stephane Cettour Cave SMB/SE Alejandro Martinez Selles Crab Cavity Giovanna Vandoni EN-ACE D. Mcfarlane
23
A.O.B. Hello David, Could you please add a reminder into your slides today about the powercut in BA4-BB4 and BA5-BB5 this week the 14th and 15th ( Nobody will access underground during the powercut. Thanks a lot. Denis EN-ACE D. Mcfarlane
24
Useful websites Link to SPS planning meetings on INDICO
Link to the SPS planning Roadmap: Schedule beyond LS1 Next meeting 26/10/2016 EN-ACE D. Mcfarlane
25
EN-ACE D. Mcfarlane