Study and Development of Large Cryogenic Systems in China
中国科学院理化技术研究所 Technical Institute of Physics and Chemistry, CAS Study and Development of Large Cryogenic Systems in China Liu, Liqiang TTC Meeting Beijing, December, 2011
2
Contents Cryogenic system of BEPCII (IHEP & TIPC)
Cryogenic system of SSRF (SINAP & TIPC) Cryogenic system of PKU-FEL (PKU & TIPC) Cryogenic system of EAST (IPP) Cryogenic system of CSNS (IHEP & TIPC) International projects (TIPC)
3
1 Cryogenic system of BEPCII
Beijing Electron-Positron Collider Upgrade
4
1 Cryogenic system of BEPCII
2 cavities, 500 MHz & one cell each Cavities are made of niobium and will work at 4.5 K. Cavity resides inside a stainless steal liquid helium vessel of 290 liter. Thermal loads include about the 30 W static load and 84 W dynamic load.
5
1 Cryogenic system of BEPCII
A pair of SC interaction quadrupoles Consisting of 7 windings (SSQ, SCB, SCB or HDC, VDC, SKQ, ASI-3)
6
1 Cryogenic system of BEPCII
7
1 Cryogenic system of BEPCII
8
1 Cryogenic system of BEPCII
9
1 Cryogenic system of BEPCII Fabrication of cryogenic transfer lines
10
1 Cryogenic system of BEPCII Installation and commissioning
11
1 Cryogenic system of BEPCII
Success!
12
2 Cryogenic system of SSRF
Shanghai Synchrotron Radiation Facility The third generation light source The Investment is 1.30 BCNY Including three SC RF cavities ( Hz / 4.0 MV) A cryo-plant is needed
13
2 Cryogenic system of SSRF
Refrigerator: 650W/4.5K LHe Dewar: 2000L Valve Boxes: 4 LN tank: 40m3 GHe Storage Tanks: 4×100m3
14
2 Cryogenic system of SSRF
15
2 Cryogenic system of SSRF
Flow Scheme (PID)
16
2 Cryogenic system of SSRF
Process analysis
17
2 Cryogenic system of SSRF
Design of cryogenic transfer lines
18
2 Cryogenic system of SSRF
Piping work Ready for installation Clean room Pre-treatment in clean room welding Installation in tunnel Cleaning test
19
2 Cryogenic system of SSRF
Cryogenic system in 09/2008
20
3 Cryogenic system of PKU-FEL
Peking University FEL Facility The 1st 2K (56W) engineering system in China
21
3 Cryogenic system of PKU-FEL
1.8K, 4K, 80K cryogenic transfer lines for PKU-FEL cryogenic system
22
3 Cryogenic system of PKU-FEL
Valve box and control system for PKU-FEL cryogenic system
23
3 Cryogenic system of PKU-FEL
Commissioning of 4K and 2K cryogenic systems for PKU-FEL
24
4 Cryogenic system of EAST
Experimental Advanced Superconducting Tokamak
25
4 Cryogenic system of EAST
EAST is the world's first non-circle cross-section full SC tokamak. 1998: approved 2000: construction started 2005: assembly finished 2006: commissioning completed All of the TF and PF magnets are made of NbTi/Cu CICC and are cooled with forced flow supercritical helium at 3.8 K A cryoplant with an equivalent capacity of 2 kW/4K (1050 W/3.5 K + 200W/4.5K + 13 g/s LHe + 13 kW/80 K) is built by IPP Design, construction and commissioning: IPP, China Compressor: China Turbines: Geliymash, Russia Cryogenic Valves: WEGA, CH HX: China
26
4 Cryogenic system of EAST
Thermal Shield and Support Toroidal Magnet and Intercoil Structure Poloidal Magnet and Support LN2 ORP C1 C2 T1 T2 T3 4.4K 3.5K HT-7U T4 Current leads Busline 4 Cryogenic system of EAST PFD of cryogenic system of EAST
27
4 Cryogenic system of EAST The cold box of cryoplant
28
4 Cryogenic system of EAST 1st cool-down of TF coils
29
5 Cryogenic system of CSNS
China Spallation Neutron Source Drift-tube linac Rapid Cycling Synchrotron
30
5 Cryogenic system of CSNS Layout of cryogenic system for CSNS
Exhaust tower LN2 tank Helium buffer Helium CB Hydrogen CB Instrument Instrument LH2 moderator He station Target station H2 station 100m25m Target station and instrument hall Instrument Helium compressor Proton beam 200m28m Layout of cryogenic system for CSNS
31
5 Cryogenic system of CSNS Flow scheme of cryogenic system for CSNS
32
5 Cryogenic system of CSNS
helium cryoplant developed by TIPC for CSNS
33
5 Cryogenic system of CSNS
Helium turbo-expander Helium compressor Cold Box Dummy heat load PFD of helium cryoplant developed by TIPC for CSNS
34
6 International projects -LHC
5 cryogenic islands; 8 refrigerators ( K each) Possibility: 1 or 2 refrigerators for 1 sector
35
6 International projects -LHC
Our contributions: CD & WU simulation on LHC sectors Commissioning analysis of LHC cryogenic system
36
6 International projects - ITER
37
6 International projects - ITER
Our contributions: Thermal simulation Conceptual design of key components 2D Simulation of temperature distribution during cool-down of ITER magnets
38
6 International projects - ITER
3D Simulation of temperature distribution during cool-down of ITER magnets
39
6 International projects - ITER
3D design of Auxiliary Cold Boxes (ACB) of ITER cryogenic system
40
Thank you! LIU, Liqiang Telephone: +86-10-6255-4669