Download presentation
Presentation is loading. Please wait.
Published byDamon Roberts Modified over 6 years ago
1
Minsi Lake Dam Public Meeting October 3, 2016 Paul Urbanik, P.E.
Chief of Engineering Mission: To protect, conserve, and enhance the Commonwealth’s aquatic resources and provide fishing and boating opportunities
2
Overview Dam Overview Dam Deficiencies and Drawdown
Rehabilitation Alternatives Working Estimates Timetable – Construction & Refill
3
Minsi Lake
4
Minsi Lake Dam Earthen embankment dam & concrete outlet works
Constructed 1970 Pond surface area (normal pool) – 117 acres Drainage area – 3.7 square miles East Branch of Martins Creek Maximum depth – 26.5 feet Maximum storage volume – 1,793 acre-feet (584 million gallons) (47 years old, design life for typical structures = 50 years)
5
Minsi Lake Dam Constructed by J.H. Beers Inc.
Purpose – fishing and boating recreation
6
Blue Mountain Dr. Minsi Lake Launch Parking Launch and Parking Dam Lake Minsi Dr. East Shore Dr.
7
Auxiliary Spillway Primary Spillway Dam East Br. Martins Creek
8
PA Code Title 25 Chapter 105 Dam Deficiencies
Department of Environmental Protection Chapter 105. Dam Safety and Waterway Management Dam Deficiencies Spillway Structural Stability Outlet Works Capacity Design Flood Criteria Unsafe Dams
9
Structural Stability - Spillway
NEW DESIGN OLD DESIGN
10
Spillway Capacity Spillway Capacity Spillway Integrity
East Br. Martins Creek
11
Spillway Capacity
12
Hazard Area
13
Rehabilitation Concept
Construct new reinforced concrete spillway capable of conveying the Probable Maximum Flood (Labyrinth Spillway) Proposed Spillway, To be constructed Existing Spillway, To be demolished
14
Rehabilitation Concept
Raise Top of dam approximately 2.3’
15
Construction
16
Construction
17
Construction
18
Construction
19
Fish Habitat Rock Rubble Humps
20
Spider Humps & Felled Trees
Fish Habitat Spider Humps & Felled Trees
21
ADA Access
22
Project Cost Estimate Working Estimate: $4,000,000 Costs include:
Design Engineering Geotechnical analysis Survey and property Environmental and Historic assessments Dam Break analysis Permitting Property Acquisition (flowage easements) Construction Contract ($3.0M) Field QA by design engineer
23
Next Steps Fish Salvage
Obtain dam safety permits and DGS authorization to advertise construction contract Construct Dam Rehabilitation
24
Fish Salvage Draw down reservoir (4-6 weeks) April-May 2017
Fish Salvage (1-2 days) June 2017 Fish mortality is expected as part of the process Fish moved to Brady's Lake Participants Include: Fisheries Staff Hatchery Staff Maintenance Staff Law Enforcement Staff
25
Fish Salvage
26
Fish Salvage
27
Fish Salvage
28
Rehabilitation Timeline
Minsi Lake Dam Rehabilitation Timeline DEP Dam Safety Permits Dec 2016 DGS Approval & Advertise Spring 2017 Drain reservoir & salvage fish April/June 2017 Construction Summer 2017 – 2018 Habitat Construction Spring 2018 Refill reservoir Spring 2019– Summer 2019
29
Questions & Answers Tim Schaeffer, Director, Policy & Planning
Paul Urbanik, Chief of Engineering Dave Arnold, Fisheries Manager Area 5 Ray Bednarchik, Captain, SE Region Law Enforcement
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.