1 Bond Oversight Committee
2015 Bond Program December 15, 2016

2 Thank you for supporting our students!
HIGH SCHOOL #3 December 6, 2016 2015 School Bond Construction Program Thank you for supporting our students!

3 Thank you for supporting our students!
High School #3 Team Owner’s Rep Inline Management Architect DLR Group Contractor Saunders Construction 2015 School Bond Construction Program Thank you for supporting our students!

4 Updates 2100 linear feet of grade beam poured 12/1
Paved Yosemite North of Sanchez house Paved remaining portion of 136th Ave On-site utilities complete (storm, water, sanitary sewer) Building permit picked up 11/28 22/60 light pole bases poured Grease and clay traps set

5 60 Day Look Ahead Masonry 12/5 – 4/6/17
Pressure Reducing Valve 12/5 – 12/30 Box culvert in Yosemite 12/5 – 12/30 Grade beams 10/4 – 2/8/17 Structural Steel 1/9 – 5/8/17 Underground plumbing & electrical in performing arts center /18 – 12/12 7 months into the project, we are on schedule

6 Grade Beam Progress 12/2/16

7 Pouring Concrete After the First Snow

8 Looking South Down the Main Building Corridor

9 Damp proofing North Side of Area 3