1 Coffee Chat: LA COSTA MEADOWS Elementary school Construction update
April 14, 2017 Tova K. Corman M.A. Executive Director, Facilities Planning and Development

2 Project Details New thirty-eight (38) classrooms, two (CR) buildings
Removal of portable buildings New student drop-off and parking Solar lunch shelters Campus beautification Pending (Building A): Library expansion Multipurpose room expansion Administration renovation Kindergarten modernization Kitchen modernization

3 Overall Site Plan

4 Renderings

5 Floor Plans – Building B
1st 2nd

6 Floor Plans – Building C
1st 2nd

7 Standard Classroom

8 Construction Phasing

9 Construction Schedule/Next Steps
9 Construction Schedule/Next Steps Schedule Construction start: Early Summer, pending State Architect approval Phase I & II, Admin - Pending Anticipated State Architect approval: May 2017 Total Construction Duration: months, including 3 summers Building B Opening: August 2018 Building C Opening: August 2019 Site Work and Building A Completion: August , pending funding Next steps State Architect approval Closure of portion of the site at new building location and adjacent areas: May/June 2017

10 Thank You! Questions?