Download presentation
Presentation is loading. Please wait.
1
By Wilmer Arellano Spring 2010
SOW / Open Workbench By Wilmer Arellano Spring 2010
2
Please download and install
3
Project management Product development involves: many people many different tasks. Successful product development projects result in: Efficient use of time, Monetary savings high-quality; Saving in other resources. Project management is the activity of planning and coordinating resources and tasks to achieve the project goals.
4
Statement Of Work (SOW)
A statement of work (SOW) is a document used in the Project Development that organizes information about: Scope of Work (WBS), Describes the work to be done in detail and specifies the hardware and software involved and the exact nature of the work to be done. Location of Work, Describes where the work is to be performed. Specifies location of hardware and software and where people will meet to perform the work. Period of Performance, This specifies the allowable time for projects, such as start and finish times. Deliverables Schedule, This part list the specific deliverables, describing what and when it is due. Who is responsible for what. Similar to an estimate of somebody fixing your roof
5
Tasks A piece of work requiring effort, resources and having a concrete outcome (a deliverable). Although a task may be of any size (a project is a very large task), the term task is usually used to refer a smaller piece of work. Tasks are sometimes specified as activities. They take place over a period of time and generally consumes resources. We prefer tasks specified as deliverables.
6
Work Breakdown Structure (WBS)
The WBS is the hierarchical list of the project's phases, tasks and milestones Phase: A group of related tasks that completes a major step in a project. Task: An activity that has a beginning and an end. Project plans are made up of tasks. Milestone: A reference point marking a major event in a project and used to monitor the project's progress. Scope: The combination of all project goals and tasks, and the work required to accomplish them. The scope translates into the timeline and budget. Budget: The estimated cost of a project.
7
Work Breakdown Structure (WBS)
This is what we want Deliverables based WBS
8
Work Breakdown Structure (WBS)
The 100% rule The rule applies at all levels within the hierarchy: the sum of the work at the “child” level must equal 100% of the work represented by the “parent” and the WBS should not include any work that falls outside the actual scope of the project, that is, it cannot include more than 100% of the work The best way to adhere to the 100% Rule is to define WBS elements in terms of deliverables.
9
Phase: A group of related tasks that completes a major step in a project.
Task: An activity that has a beginning and an end. The end is marked by a deliverable
10
Documenting (WBS) Phase 1.1-Antenna Design
Objective: To produce a 50 Ohm input impedance antenna with a power handling capability of 100 Watts with minimum cost and a minimum power gain of 3 dB Approach: Two method will be used and compared to select the more economical design. Method 1 will consist of the recently acquired Antenna Design Software and method 2 will be based on newly published formulas by A. Jones [4] Expected Results: A fully functional transmit antenna with accompanying literature and mounting hardware. This phase will consist of the following tasks: Antenna Design Antenna Construction Antenna Testing Remember this is a deliverable based description
11
Project Timeline/ Sequential Tasks
Tasks are sequential when they are dependent on the output of another task. These because the dependencies impose a sequential order in which the tasks must be completed. We do not necessarily mean that the later task cannot be started before the earlier one has been completed
12
Project Timeline/ Parallel task
Two tasks are parallel when they are both dependent on the same task but are independent of each other.
13
Project Timeline/ Coupled tasks
Coupled tasks are mutually dependent; each task requires the result of the other tasks in order to be completed. Coupled tasks either must be executed simultaneously with continual exchanges of information or must he carried out in an iterative fashion.
14
Milestones Examples: Prototype Implementation. Testing. Documentation. Demonstration. Each Milestone should be explained with a sentence or two
15
PERT Charts / The Critical Path
The dependencies among the tasks in a PERT chart, some of which may be arranged sequentially and some of which may be arranged in parallel, lead to the concept of a critical path. The critical path is the longest chain of dependent events.
16
Example 16
17
Example 17
18
Example 18
19
Example 19
20
Possible Research (Missing Percentages)
22
This is just an example, you can customize as you like.
23
In Favorites Gantt Charts, double-click the little square and enter:
A new Phases with: Name Category And ID Make sure to select phase
24
The first phase has been created
25
In Favorites Gantt Charts, double-click the little square and enter:
The Tasks with: Names Category And ID Duration Could leave blank Probably Better Make sure to select task
26
The first task has been entered
27
This is how it would look after all tasks for the first phase have been entered
28
To indicate task’s dependencies drag from the end of one task to the beginning of the next one
29
Click here to auto-schedule
30
This is how it would look like
Red Color indicates the Critical Path
31
31
32
Project with two phases included
It is a coincidence that the two phases have same duration
33
Click to see the PERT The zoom commands were used to fit the chart in the window
34
On planning, Resource assignment, double click the little square to enter the resources and their costs
35
Do the same for non labor resources
Use Equipment for Space
36
You can add the cost of components as “material”
37
Right click on the tasks and select assignment to assign resources to the tasks
38
Select Resource and click on Assign
Enter estimated hours in Estimate
39
As components were entered with a rate of $100, 1
As components were entered with a rate of $100, 1.5 will represent $150
40
If you need to add a new task or phase in between tasks or phases, right click the square and select insert task The yellow color indicates that the task is low in resources, more hours or space or equipment, etc are needed
41
There will be a problem if you click schedule again
42
As the Audio Interface Module and the Mixer Module were using the same resources, they were converted to sequential. You would need to add more resources to keep the tasks in parallel The zoom commands were used to fit the chart in the window
43
Another Low Frequency Engineer was included
Two more Lab Spaces were included It was not necessary increase the project duration
44
Click on controlling and then Revise Schedule to see the budget
45
Updating The Project Status
Set The base Line
46
Updating The Project Status
47
Updating The Project Status
Double Click on the affected tasks and change the changes in estimated and actual time per Resource
48
Updating The Project Status
The task bar changes colour to reflect status (Red / Blue – Not Started) (Purple – Started) (Grey – Progress completed) The task name changes colour to reflect status (Red – Not Started) (Purple – Started) (Green – Completed)
49
Updating The Project Status
If the task is completed enter 0 in Estimate
50
Updating The Project Status
We reduced 20 hours but because of the weekend it appears to be a longer time
51
Milestones
52
Milestones Drag the milestone to the desired location
53
Milestones
54
Copy and Paste Table cells can be copied and pasted into excel
By the way, this is a representation of the WBS
55
You can use the information from Openworkbench to build your WBS
57
The Budget Even the Components are included here
58
& Questions Answers
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.