Joel Bladow – Tri-State G & T
Mountain West Transmission Group Panel Discussion Joel Bladow – Tri-State G & T Midwest Electric Consumers Association Annual Meeting December 7, 2016
2
Organized Market Status – 2012
Establishing an Energy Imbalance Market in the West was “just around the corner” California was leading the charge Xcel Energy was looking hard to join something WAPA, Xcel, Basin, and Tri-State met to discuss options for the Rocky Mountain region
3
What your neighbors do really matters!
4
Where do you start? TRANSMISSION ENERGY MARKET FULL MARKET
Develop a full day-a-head market ENERGY MARKET Build a real-time energy market TRANSMISSION Foundation for the Market
5
Building the transmission foundation
How do you pay for the existing system costs while removing pancaked charges? What facilities are included License plate or postage stamp Cost shifts and benefit gains – by whom How do you share the costs of system improvements? Evaluate benefits Defined voltage level allocations
6
Organized Market Status 2012
7
Current market status
8
Projected markets 2017 ?
9
Mountain West Transmission Group – Getting Down to Business
After almost two years of meetings among the original group, participation is expanded The expanded group has meet over 60 times in the past couple of years to develop the framework A Request for Information was issued with responses to perform various services to; SPP, CISO, MISO, and PJM
10
Mountain West Tariff Transmission Owners PSCo Black Hills
Platte River Power Authority WAPA - LAP and CRSP Tri-State G&T Colorado Springs Utility Basin Electric
11
California ISO - CAISO Established 1997
CAISO market replaced market run by CA PX ISO status 2008 Staff: 588 Annual Budget $206 million Open Access Tariff - 2,736 pages
12
Southwest Power Pool - SPP
Established in 1941 Approved as RTO 2004 Energy Imbalance Market 2005 Full Energy Market 2014 Staff: 598 Annual Budget $182 million Open Access Tariff - 5,533 pages
13
Midcontinent ISO - MISO
Established 1997 Energy Market 2005 Ancillary Services Market 2009 Staff: ~ 900 Annual Budget $283 million Open Access Tariff - 6,123 pages
14
Mountain West status Development of a common tariff is close to completion Market impact studies are being jointly conducted by the participants All participants are evaluating the pros/cons of participation based on the work done to date Anticipate an early 2017 decision on proceeding.