Attaining Cost Efficiency In Constructing Sports Facilities For Beijing 2008 Olympic Games By Use Of Operations Simulation Wah-Ho Chan, Ming Lu Dept. Of Civil and Structural Engineering Hong Kong Polytechnic University Hong Kong, China Jian-Ping Zhang Dept. Of Civil Engineering Beijing, China Presented By: Vinh H. Truong
2
Purpose Of The Simulation
Evaluating Construction Time Construction Operations Installation Sequences Varied Schedules For Assembling Cost Efficiency In Building The Structure
3
Construction Steel Pieces Hauled In Assembly Two 600-Ton Cranes
Inner Ring Two 800-Ton Cranes Outer Ring 24 Steel Columns 86 Steel Frames
4
Work Flow Model
5
Column/Frame Subassembly Reference Code
Short ID Code Of The Steel Component Column Or Frame 0 = Frame, 1 = Column Structural Complexity Index Real Number Representing Work Content and Complexity, Used For Adjusting Assembling and Installation Duration Installation Destination Zone 1 Or 2 Representing The Installation Zone Installation Sequence Index Smaller Value = Higher Priority For Processing
6
Activity Duration Summary
7
SDESA Simplified Discrete-Event Simulation Approach
Research Led By Ming Lu Easy-To-Apply, Cost-Effective Methods Of Artificial Intelligence And Computer Simulations For Construction Engineering And Project Management
8
SDESA
9
SDESA
10
Results Base Areas 4,5,6 – Start Areas 1,2,3,7 – 50 Days Later
Crash Accelerate The Concrete Construction Alternative Areas 1,2,3 – Start Areas 4,5,6,7 – 50 Days
11
Results
12