Presentation is loading. Please wait.

Presentation is loading. Please wait.

Equipment Reliability Working Group

Similar presentations


Presentation on theme: "Equipment Reliability Working Group"— Presentation transcript:

1 Equipment Reliability Working Group
Sub Group – Equipment Categorisation Helsinki 8th to 9th November 2016

2 PURPOSE for Classification (in order to…. For who …
Common Language Systematic Consequence based with focus on sustained Nuclear Safety and Efficient Mission Delivery Based on IAEA, INPO and relevant good practice. Must be a guide and not prescriptive. Identify issues for consideration and provide informed choices.

3 Members at Helsinki November 2016
Graham Norman UK Thomas Gerin Engie (Tihange and Doel) Ferran Tarrasa ANAV Spain Bertil Van Boven Netherlands Gerard Beije Netherlands Luis Yague Spain (Ebedrola) Yujie Liu China Ying Cai China Chen Yu China

4 Helsinki Day 1 Equipment Classification working group
Discussed draft 1 document on Equipment Classification Findings We do not know what we want, until we see what we do not want! The Draft 1 document has provided a good structure to start from. In essence the document is directing peoples thoughts in the right direction. There is some preceding activities or additional sections to add with respect to:- Asset hierarchy /Scope Glossary/ Definitions End of life/ change of mission considerations Reference to mandatory requirements

5 There are some activities the EC sub working group need to start over the next 6 months in addition to producing draft 2, 3,4…of the guide e.g. Exemplars/ templates/ standard check lists, reactor type examples… Rules of thumb for time, cost, manpower to implement EC to various levels of deetail/ maturity Develop a document structure for the various sub group outputs Further populate the table relating to station equipment classification Consider linking classification with condition and influencing O&M

6 Helsinki Day 2 Asset hierarchy considerations Comprehensive asset register Safety case derived assets (active and passive) PM register (maintained assets only) Spares register (Purchasing/ commercial/ contracts register) In service inspection schedule Building register Programmable Electronic System register (software, firm ware, hardware, networks..) Active assets (assets that have moving components, assets that need power to move) Passive components (Safety features such as containment boundary, utility services, cables, civil structures, mechanical load paths……) Site/ Station security assets Site infrastructure

7 Actions Action Who Asset hierarchy Mid December bertil Glossary/ Definitions Luis End of life/ change of mission considerations December Graham Reference to mandatory requirements Ferran

8 Action By when Who Exemplars/ Templates/ standard checklists of criteria/ questions Dec Thomas reactor type examples of equipment classified as C1, C2, C3, RTM VVER Westinghouse PWR Candu AGR EDF UK EPR Rules of thumb for time, cost, manpower to implement EC to various levels of detail/ maturity Dec for Q, Feb for As Luis Further populate the table relating to station equipment classification (add reactor type) As above Graham Develop a document structure for the various sub group outputs 11th November 2016 Dajun Consider linking classification with condition and influencing O&M

9 Actions Action By When Who Add reactor type to the table Dec Graham Considerations for in scope/ out of scope options Feb Bertil/ Graham Arrange a sub group mid point telecon Mid Dec, mid February, mid March Aim to vote on the document in April Working Group

10 Summary NPPs are very complex facilities consisting of 100,000 to 500,000 components A prioritisation process is needed to enable the deployment of the various tools, processes and stations resources (both people and money). Many Utilities have performed EC and it works for them. Every country has sovereign right to do what they want to do (within international law) A process has been developed that hopefully can be used by all NPPs. The process is for guidance allowing newcomers to start and to allow others to review their current processes. Final comment:- JUST DO IT, DIVE IN, HAVE A GO,

11 C1=12% C2=5% NC=12% RTM=13% Out=59% C1=0.5% C2=3.5% C3=29% C4=67% RTF=67%

12 C1=12% C2=5% NC=12% RTM=13% Out=59% C1=0.5% C2=3.5% C3=29% C4=67% RTF=67%

13 Utilities Categories Maint Rule Assessment by Package Status Used by Tags per category Active/ Passive SSCs Cernavoda SPVs Safety Prod’n ‘other’ Non crit RTM n System Eng MS xl 15 years maturity WM, Maint, Tech, Procurement Stock SPV=2% Safety=6% Prodn=4% Other=1% NC=87% Active only Slovenske Elektrarne Critical Non Crit RTF System Eng with support MS xl + SAP 5 years experience All processes C=15% NC=47% RTF=37% Mainly active with some passive PAKS Nuke Safety 4 Seismic 4 N but considering the US MS xl then Access 20 years experience WM, Tech, C1=4% C2=25% C3=21% NC=50% A and P Engie C1 C2 C3 Contractor, SRO, verification by ops MS xl, SAP, P&IDs 0 years Not started Pilot done C1,2,3 =17% RTM and NC=83% Utilities Categories Maint Rule Assessment by Package Status Used by Tags per category Active/ Passive SSCs Cernavoda SPVs Safety Prod’n ‘other’ Non crit RTM n System Eng MS xl 15 years maturity WM, Maint, Tech, Procurement Stock SPV=2% Safety=6% Prodn=4% Other=1% NC=87% Active only Slovenske Elektrarne Critical Non Crit RTF System Eng with support MS xl + SAP 5 years experience All processes C=15% NC=47% RTF=37% Mainly active with some passive PAKS Nuke Safety 4 Seismic 4 N but considering the US MS xl then Access 20 years experience WM, Tech, C1=4% C2=25% C3=21% NC=50% A and P Engie C1 C2 C3 Contractor, SRO, verification by ops MS xl, SAP, P&IDs 0 years Not started Pilot done C1,2,3 =17% RTM and NC=83%

14 Do this quickly- round table Things to consider
Q3 Compare OPTIONS from the 7 Utilities, ENHANCE (consider opening this up to all members contributions) Do this quickly- round table Things to consider Question Answer Can we live with USNRC Maintenance Rule? No, not all countries can adopt it. Can we live with INPO AP913? Yes, as a guide, but seriously consider the integration with other processes such as AP928 (IWM) Does your Regulator or Company force you to do something different or prevent you from implementing International Standards? Yes, there are many different regulatory frameworks e.g. some prescriptive, some goal setting – different arrangements for life extensions Is your Station/ Facility in need of some other process? We can develop a process to be flexible enough to meet all needs Can we develop a pick and mix? Yes

15 Scope:- Where do we put C1s, C2s, C3s…..?
Consequences Frequency Terminal Survivable Trivial Industry Acceptability daily 10-7year SCRAMS Loss of Primary Containment Run to Maintenance Active SSCs Passive SSCs

16 Expected Mitigation Effort
Deployment of Effort on Active and Passive SSCs Expected Mitigation Effort Risks and Issues Station Age 20y 40y 80y 60y Active SSCs Passive SSCs

17 Comment from Tuesday 11th April discussion
Make it explicit the scope of the procedure is not to be too specific with Category definitions as there are too many countries, nuclear facility types and cultures to accommodate. Include lessons learned form those utilities that have classified their SSCs. i.e. list the ‘what worked well, how not to do it and identify the benefits of categorisation. Ensure it is made explicit the WANO EC process will be guidance and not mandatory. It should be a guide for those that want to perform EC for the first time or to review their current process.

18 Classification LFE + ves What has went well - ves What has not worked
Include key groups in the process e.g. Operations, Maintenance, Design, Safety assessors Being too conservative resulting in too many items as C1 thus diluting focus on the truly critical items Establish a review panel to ‘Approve’ the classification and to ensure consistency of approach and assessment across the unit, station or utility. Grouping too many sub components or components incorrectly into a higher asset and allocating the same classification to them all. Ensure the process links correctly with other processes e.g AP913 EC links to AP928 (work management) and should link to ‘Critical Spares’ process. Do not mix equipment classification with maintenance strategies (e.g. RTM is a maintenance strategy and not a EC) Perform prework, understand the purpose, process, clarify the classification definition etc before starting. Benchmark with others that have both +ve and –ve results. Target others with the same reactor, vendor equipment, same problems etc.

19 Step 1 Select the unit’s stage of life :-
Step 2 Select the purpose for SSC classification:- Step 3 Select SSC classification approach Step 4 Modify the unit’s operating processes and procedures Then implement and keep it live especially based on OE and your stations situation

20 PRODEquipm’t Rel. ECONEconomics ALL 3Combined C2 C3 NSNuclear Safety
Options Classification 1 NSNuclear Safety (ref, IAEA SS DS 367) 2 PRODEquipm’t Rel. Sustained production, minimisation of SCRAMS, maximum MWhr (ref, INPO AP 913) 3 ECONEconomics Long Term Operation Life Extension Asset Life Optimisation (ref INSAG 14) 4 ALL 3Combined Balanced Comprehensive C1 1st Gold Top, Highest, Grand, Big, No 1 SSCs preventing off site release of nuclear material from Reactivity Control Cooling Containment (3C’s) SSCs that cause production to be stopped quickly or stopped for a long time (eg SPVs causing SCRAMs, Turbine loss of lubrication). Life limiting SSC’s that are impossible to repair or replace eg reactor pressure vessel, usually large passive structures. C1s from Nuclear Safety +Equipm’t Rel+Econ, or NS+ER, ER+Econ C2 2nd Silver Second, Middle SSCs preventing on site release of nuclear material from Reactivity Control SSCs that cause production output to be reduced – long period of revealed deterioration Very expensive to replace SSCs such as large one offs or large quantities of smaller items (e.g. heat exchanger replacement or station rewire) C2s from Nuclear Safety +Equipm’t Rel+Econ, C3 3rd Bronze Third SSCs preventing worker dose or contamination. Minor impact to station output e.g. fuelling delays due to fuel path equipment failures SSCs that impact Station Efficiency or SSC where their replacement costs far outweighs the cost of maintenance C3s from Nuclear Safety +Equipm’t Rel+Econ, C ‘n’ Bottom, Lowest Out of scope, not covered No nuclear or radiological impact No production impact Minimum, legal, good industry practice

21 Engineering Department EC Workload
1 Stage of life 2 EC Purpose New Build NS Prod Econ Mid Life Life Extension/ End of life 3 Approach Cons→Risk Own Others 4 Outputs Age Management Strategy for Larger SSCs Investment Plans, Optimisation/ Efficiency Continuous ER Improvement In Service Inspection OE driven SSC inspections Initial Asset Register ( MEL) and Classification of SSCs SSC Maint Strat. Crit Spares List SPV list Equipment Training Condition Assessments Margin Management Age Management Investment Plans Risk and Mitigation Management Fit for Purpose solutions and Specs Refurb vs Replace..

22 Members from Madrid Sept 2015
Graham Norman UK Alexander Lindqvist Sweden Mike Ballard WANO Lassi Hostikka Finland Zhang Chi China Bertil Van Boven Netherlands Ferran Tarrasa Spain

23 Members from Budapest 2016 Graham Norman UK
Alexander Lindqvist Vattenfall Sweden Mike Ballard WANO Thomas Gerin Engie (Tihange and Doel) Zoltan Macsai Paks Saulea Sorinel Cernavoda Vesa Tanttari Fortum Pavol Dubosky Slovenske Elektrarne Ferran Tarrasa Blanes ANAV Spain

24 END


Download ppt "Equipment Reliability Working Group"

Similar presentations


Ads by Google