Status of the ATLAS Forward Proton Detectors Michael Rijssenbeek for the ATLAS AFP group
25FEB2016
2
AFP Phase-1: AFP0+2 2 horizontal Roman Pot Stations at 205 and 217 m in A6R1 very much similar to the CMS-PPS – TOTEM horizontal stations installed since 18 Jan; under vacuum and baked-out since 3 Feb. Detectors installed yesterday & today… BPM and BLMs installed and cabled Motor motion calibrated, limit switches (HOME, IN, OUT) set, LVDT calibrated on 18 Feb. Interlock logic (copy of ALFA logic) installed and ready for validation tests & commissioning … 25FEB2016 TREX Mtg
3
Beam View: Horizontal pot with 0.3 mm thick windows
AFP in 2015 TDR approved by ATLAS and LHCC – 19 Jun 2015, AFP0+2 ECR approved by the LHC – 2 Oct 2015 Roman Pot Stations: (Vakuum Praha) Prototype ( ) 2 Production stations ( ) NEG coating start ( ) Roman Pots: Prototype (Sep): Leak & pressure tested 2 Production Pots on 20 Oct, 12 Dec Station assembly: equipped with Pots and Motorization ( ) Vacuum validation (TE-VSC): Leak testing, baking, outgassing analysis start on Cabling: Opening of Survey galleries for fast cable pulling All cables prepared … Beam View: Horizontal pot with 0.3 mm thick windows 25FEB2016 TREX Mtg
4
AFP in 2016 – RP Installation
Two stations validated on 13 Jan (TE-VSC) Cabling: Fast Cabling finished on (SPIE) C-side cables finished (ATLAS-TC); A-side cabling cont. inuing until 26 Feb All C-side cables connectorized and tested (PH-DT, AFP) Services: Compressed air for Cooling Secondary Vacuum (PH-DT) BPM, BLMs connected Fiducialization & Installation on 18 Jan connected to Beam Pipe, pumped and baked-out Pot Motion calibrated in tunnel: Survey of slide vs motor position, vs switches and LVDT. 20 Feb Patch Panels & LV Regulators (Milano) at 211 m station at 217 m, BPM, BLM, TCL6 25FEB2016 TREX Mtg
5
AFP in Detectors 11 Silicon 3D detector assemblies produced at IFAE (more in coming months) 7 assemblies are operational Assemblies precision-mounted on Al-CF carrier cards FLEX Heat Exchanger holds Tiltbars –40 C air from AirCooler Installation: this week leak testing Mo-Tu cooling exhaust signal feedthrough trial assembly with 2 bad assemblies ( ) heat exchanger 25FEB2016 TREX Mtg
6
AFP in 2016: TDAQ Local Trigger Board:
Uses HitBus chip and the HitOR from FE-I4. NIM trigger signal to CTP in less than 80 BX Data Acquisition using Optoboard and fibers to RCE-HSIO system in USA15 System pre-tested in stand- alone mode: from tunnel USA15 local trigger board HV (ToF) Feed through flange Vortex Cooler 25FEB2016 TREX Mtg
7
NTC Distribution Panel
AFP in 2016: DCS LV and HV purchased and connected to DCS capacity for 45 NTC’s per arm, sec. vac., radiation dose … RPHC1 ToF PMT SiT Far Station Tunnel floor Reference Clock HPTDC Card CFD Card N ToF Preamp Card P RPHC0 Local Trigger Board Near Station OnWall HE Outside Flange ACS Opto Board VREG Crate NTC Distribution Panel Trigger/amplifier Stepper Motor NTC PT1000 P0 P1 P2 P3 Movement Vacuum E. Banaś 16/2/2016 25FEB2016 TREX Mtg
8
Range Switches and Stops
Pot Motion & Controls Document in preparation: “Specification and Validation of the Motion Control System of the ATLAS Forward Proton Roman Pots” we implemented mechanical stops to prevent damage to electrical STOP Range Switches and Stops 25FEB2016 TREX Mtg
9
AFP RP Interlock Diagram 2016
MOTOR CONTROL RACK AFP RP Beam Interlock System (BIS) Rack USA15 Y A1 RP_HOME_B1(1) Home Switch B1(1) AND ALL_RP_HOME_B1 ATLAS Inj. Permit Beam 1 INJECTION_PERMIT RP1 (Beam 1) RP_HOME_B1(2) Home Switch B1(2) Pos_B1(1) LVDT_B1(1) compare AND ALL_LVDT_OK_B1 AND USER_PERMIT (Beam 1) Pos_B1(2) OR CIBU RP (double) LVDT_B1(2) compare Limits FESA OR AND USER_PERMIT (Beam 2) LVDT_B2(1) compare AND Pos_B2(1) ALL_LVDT_OK_B2 LVDT_B2(2) compare Pos_B2(2) ATLAS Inj. Permit Beam 2 Home Switch B2(1) INJECTION_PERMIT RP2 (Beam 2) RP_HOME_B2(1) AND ALL_RP_HOME_B2 Home Switch B2(2) RP_HOME_B2(2) Motor Control DCS x 4 ATLAS Slimos OVERRIDE OVERRIDE OR MOV. DEVICE_ALLOWED IN OR NOT_BACK_HOME GMT (SMP) AND STABLE_BEAMS all machine flags all machine flags 25FEB2016
10
AFP 2016 – Commissioning & Data
Ultimate Goal: ATLAS Forward Proton detectors: Measure forward protons with AFP horizontal Roman pot detectors for the study of soft and hard diffractive processes with ATLAS. Commissioning: Commissioning of Interlocks and Roman pot insertion during no-beam periods. Motorization control & Interlock documentation in progress Contact with MPP – next presentation next week Parasitic stand-alone running (in garage position) for detector commissioning (NO pot insertion). Time period: March – April 2016 Data Taking After commissioning: Participate parasitically in low-μ special runs; stand-alone data taking with tentative insertion up to 20 σ. Time period: May – June 2016 After LHC and ATLAS approvals: Participate parasitically in a few end-of-store runs (standard optics); stand-alone data taking with tentative insertion up to 20 σ. Time period: before September 2016 After ATLAS Review and Approvals: Participate in a number of standard runs with ATLAS+AFP TDAQ with tentative insertion up to 20 σ. Time period: Before mid-November 2016 25FEB2016 TREX Mtg
11
Back-up Slides 25FEB2016 TREX Mtg
12
AFP in 2015 – TDR, TS, ECR, PO … AFP Internally and externally approved for special runs TDR, TS, ECR, POs, … 25FEB2016 TREX Mtg