Download presentation
Presentation is loading. Please wait.
Published byMaximillian Evans Modified over 6 years ago
1
Presented by Md. Imran Kabir Student No: 7664095 November 26 , 2014
Cost-Benefit Analysis on SHM Projects Presented by Md. Imran Kabir Student No: November 26 , 2014 Instructed By Dr. Ashutosh Bagchi Building, Civil and Environmental Engineering Concordia University
2
Introduction (Background)
Structural Health Monitoring: It is defined as a system that diagnose the “state” of the constituent materials of a structure at every moment during its life along with the monitoring, of the different parts and of the full assembly of these parts constituting the structure as a whole This is partially true, but SHM is much more
3
Introduction (Background)
Structural Health Monitoring: SHM is about insuring safety reducing risk adding prestige to a structure Reserving natural resource Enabling remote management
4
Structural Health Monitoring
The relationship between the cost and the benefit, has become a major concept for the SHM industry
5
Defining Cost Total Cost Capital Investment SHM Design Cost
1.Integration with the structure’s design 2. Planning and project management Hardware Costs 1. Sensors 2. Cables 3. Data acquisition and management hardware 4.Communication Installation Costs 1.Integration with building schedule 2.Configuration 3.Commissioning 4.Reporting Operational Cost System Maintenance 1.Spare parts and consumables 2. Energy 3.Communication Data Management 1. Publishing 2.Archiving Data Analysis 1. Interpretation 2. Reporting
6
Identifying Benefits Total Benefit Hard Benefit 1.Capital Value
2. Discover Structural Reserves 3. Early Detection of Defects 4. Safe Life Time Extension etc. Soft Benefit 1. Reduction of Risk 2. Increase Quality 3. Increase Safety 4. Image, prestige, public perception
7
Case Study Details The new St. Anthony Falls Bridge is 1,216-foot-long
10-lane concrete bridge with a 504-foot-long precast segmental main span constructed with two parallel structures over 500 sensors collect data regarding structural behavior and corrosion total cost for the sensing system was about $1 million Estimated life span 100 years
8
Overview of Sensors and Data Acquisition Systems Installed in the I-35W Bridge
Long-gauge SOFO fiber optic sensor Vibrating Wire Strain Gauge Concrete corrosion and Humidity sensors Vibrating wire and temperature sensors data logger Accelerometer SOFO Fiber Optic Sensor Data logger
9
Global Overview of Monitoring System of I-35 W St. Anthony Falls Bridge
10
Global Overview of Monitoring System of I-35 W St. Anthony Falls Bridge
11
Global Overview of Monitoring System of I-35 W St. Anthony Falls Bridge
12
Global Overview of Monitoring System of I-35 W St. Anthony Falls Bridge
13
Life Cycle Cost Analysis
What is Life Cycle Cost Analysis? An economic analysis procedure that uses engineering inputs Compares competing alternatives considering all significant costs Expresses results in equivalent money (present value)
14
Life Cycle Cost Analysis
Cost Analysis Methods Present Worth Method (PW) Future Worth Method (FW) Savings/Investment Ratio Method (SIR)
15
Life Cycle Cost Analysis
Cost Analysis Methods Net Present Value (NPV) : Converts all the costs to present values Together with Internal Rate of Return (IRR)
16
Cost Considerations Life Cycle Analysis Costs Years Net Present Value
Salvage Costs Capital Cost Maintenance and Inspection Cost Rehabilitation Cost Salvage Value
17
Life Cycle Cost Analysis for the I-35 W Bridge
Case 1 (w/o SHM) Clifestyle = Ccapital + Coperational + CSHM Case 2 (with SHM)
18
Life Cycle Cost Analysis for the I-35 W Bridge Case 1
Capital cost: Ccapital = $ 234,000,000* (*Source: MnDot) Operational Cost Calculation: Assumption: M & R of traffic control = $ 3,000/year Concrete Repair = $ 5,000,000/25 year Resurfacing= $ 150,000/25 year Demolishing cost= $ 3,000,000 Crepair/maintenance = ($ 3,000x100+$ 5,150,000x4+$ 3,000,000) = 23,900,000/100 = $ 239,000 / year Reference: ISIS Educational Module 7
19
Life Cycle Cost Analysis for the I-35 W Bridge Case 1
Assumption of Manpower Cost: No. of Inspector: 4 Engineer Duration of Inspection: 7 days/2 months Transportation fee: $500/engineer Hotel fee: $100/(engineer·day) Engineer fee: $500/(engineer·day) Cmanpower =500x4x6+( )x4x7x6 =$ 112,800/year Reference: MnDOT
20
Life Cycle Cost Analysis for the I-35 W Bridge
Case 1 Life Cycle Cost Analysis for the I-35 W Bridge Additional equipment cost: CAdE = $ 7,000/year Total Operational Cost w/o SHM Coperaional = Crepair/maintenance + Cmanpower + CAdE = $ 239,000 + $ 112,800 + $ 7000 = $ 358,800/year = $ 360,000/year (say)
21
Life Cycle Cost Analysis for the I-35 W Bridge Case 1
End of Year Capital Cost ($) Operating Cost ($) Increment factor (3.5%) Total cost Discount factor (2%) Present Value($) 1 233000 2 360 1.04 372.60 0.980 365.29 3 1.07 385.64 0.961 370.67 4 1.11 399.14 0.942 376.12 5 1.15 413.11 0.924 381.65 … 45 4.54 0.418 684.34 46 4.70 0.410 694.40 47 4.87 0.402 704.61 48 5.04 0.394 714.98 49 5.21 0.387 725.49 50 5.40 0.379 736.16 Total Present Value without SHM ($) (in Thousand)
22
Life Cycle Cost Analysis for the I-35 W Bridge Case 2
Total Capital Cost for SHM system: Ccapital = $1,000,000* (*Source: MnDOT)
23
Life Cycle Cost Analysis for the I-35 W Bridge
Case 2 Operational Cost of SHM System: Assumption of Manpower Cost: No. of Inspector: 4 Engineer Duration of Inspection: 7 days/4 months Transportation fee: $500/engineer Hotel fee: $100/(engineer·day) Engineer fee: $500/(engineer·day) Cmanpower = 500x4x3+( )x4x7x3 = $ 56,400/year Sensors updating and replacing: Csensor = $2,000/year
24
Life Cycle Cost Analysis for the I-35 W Bridge Case 2
Additional Cost in SHM System: CAdditional = CData management + CData analysis = $ 40,000/year Total Operational Cost in SHM System Coperational = $ 98,400/year = $ 100,000/year (say)
25
Life Cycle Cost Analysis for the I-35 W Bridge Case 2
End of Year Capital Cost ($) Operating Cost ($) Increment Factor Total Cost ($) Discount Factor Present Value($) 1 234000 2 460 1.04 476.10 0.980 466.76 3 1.07 492.76 0.961 473.63 4 1.11 510.01 0.942 480.59 5 1.15 527.86 0.924 487.66 … 70 10.74 0.255 71 11.11 0.250 72 11.50 0.245 73 11.90 0.240 74 12.32 0.236 75 12.75 0.231 Total Present Value with SHM ($) (in Thousand)
26
Benefit Analysis for the New I-35 W Bridge
Impacts Bridge Failure on Economy: Carried more than 140,000 veh/day (60,000 veh/day, 1967) Increased commuter expenses, Created a burden on surrounding roads creating congestion costs many switching departure times, modes, or destinations to avoid traffic Approximately $400,000 per day in lost revenue*. So, Cuser = CVHT/VKT + Cadditional = $ 400,000/day *Source: MnDOT & FLATIRON
27
Benefit Analysis for the New I-35 W Bridge
Feng Xie et al. (2009): Before Bridge Collapse Time Change & Route Change Time Fixed & Route Fixed Time Change & Route Fixed Time Fixed & Route Change Daily VHT (10^6 veh. hrs) 1.427 1.432 (0.35%) 1.442 (1.09%) 1.431 (0.31%) 1.441 (1.00%) Daily VKT (10^6 veh. kms) 86.53 86.27 (-0.31%) 86.58 (0.05%) (-0.30%) 86.58 (0.06%) Daily economic loss (US$) NA 71,466 220,198 62,408 203,409
28
Benefit Analysis for the New I-35 W Bridge
So, Cuser = CVHT/VKT + Cadditional = $ 242,210/day = $ /year = $ 88.5 million/year
29
Benefit Analysis for the New I-35 W Bridge Case 1
End of Year User Benefit ($) Increment factor (1.5%) Total Benefit ($) Discount Factor (3.5%) Present Value ($) 1 88500 1.02 1.000 2 1.03 0.980 3 1.05 0.961 4 1.06 0.942 5 1.08 0.924 … 45 1.95 0.418 46 1.98 0.410 47 2.01 0.402 48 2.04 0.394 49 2.07 0.387 50 0.379 Total Benefit w/o SHM ($) (in Thousand) 3,
30
Benefit Analysis for the New I-35 W Bridge Case 2
End of Year Operating Benefit($) Increment Factor (1.5%) Total Cost($) Discount Factor (3.5%) Present Value($) 1 88500 1.00 1.000 2 1.02 0.980 3 1.03 0.961 4 1.05 0.942 5 1.06 0.924 … 70 2.79 0.255 71 2.84 0.250 72 2.88 0.245 73 2.92 0.240 74 2.96 0.236 75 3.01 0.231 Total Benefit with SHM ($) (in Thousand) 5,565,
31
Benefit-Cost Analysis for the New I-35 W Bridge
CASE CASE2 NO SHM SHM BCR < Difference of BCR = 4 CASE 2 (WITH SHM) IS ACCEPTABLE!
32
Data Analysis and Results....
Personal Details of Motorcycle Rider 66% at Range of 25-40 yrs. 2% age Below 20 yrs. *Source: FHWA
33
Saving from SHM 31% savings Bridge Candidate for Replacement:
Is possible From SHM Bridge Candidate for Replacement: Cost of Replacement, no SHM: 100% Cost of SHM: 3% Bridges found to be OK: 20% Bridges needing rehabilitation: 20% Cost of rehabilitation: 30% Bridges needing replacement: 60% Cost with SHM: 3%+20%x30%+60%=69% Saving from SHM: 31%!!!
34
Recommendations Compared to the conventional methods, Wireless Sensor Networks (WSN) provide comparable functionality at a much lower price (Sukun Kim et al. 2007) Benefit-Cost analysis of new I-35 W bridge using WSN should be evaluated in future studies.
35
Thank You
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.