Presentation is loading. Please wait.

Presentation is loading. Please wait.

EXPERIENCE SHARING 4th April 2016   SSBG.

Similar presentations


Presentation on theme: "EXPERIENCE SHARING 4th April 2016   SSBG."— Presentation transcript:

1 EXPERIENCE SHARING 4th April 2016 SSBG

2 Options for Old Units ??? Retirement Capital Overhaul / Refurbishment
Mandatory maintenance & operate for an extended period and retire Capital Overhaul / Refurbishment R & M and LE R & M, LE and Up-rating

3 Factors causing the Dilemma
Age / Hours of operation Present Heat rate Availability / PLF Reduced Output Continuous deterioration Latest stringent emission norms GOI has identified 65 sets (~ 5860 MW), which have completed more than 25 years of life, for replacement with modern and environment-friendly (super-critical) ones.

4 Comparison of New Unit V/s R&M
New Units R&M Cost of a New Unit is X Cr. R&M will be approx. X/2 Cr. (as per CEA guidelines) Latest technology The latest technologies are incorporated in the existing systems/ equipments upto the extent possible Option of higher capacity sets with superior heat rate Recapture rated Output, Reliability and Availability with improvement in efficiencies, Marginal gain in output Reliable operation with minimum maintenance for next 20 years Extension of economic useful life by about 15 years Requirement of experienced new manpower Extant manpower may be trained Longer gestation period Smaller gestation period New infrastructure to be augmented No such requirements Transfer of knowledge/ know-how/ know -why New vendor base for spares / services Various statutory clearances to be obtained

5 Issues regarding R & M and LE
Capital overhauling with retrofitting is only a short term measure RM & U requires total design change Increase in cost due to vast scope in RM & U Uncertainty about post RM & U benefits Longer shutdown requirement v/s peak power shortage in RM & U

6 General Scope of R&M /L E
Boiler & Auxiliaries Replacement/augmentation of pressure parts Retrofitting/ modification of air pre-heater Augmentation of milling system Provision of flame scanner, igniters Renovation of draft system Retrofitting of ESPs TG & Auxiliaries Replacement of Turbine rotors & inner casing- with latest design blades Modernization of condenser by change of tube materials, augmenting with online tube cleaning systems Modernization of power cycle equipments with more efficient pumps, regenerative heaters etc Modification of air evacuation system with vacuum pumps C&I Replacement of obsolete C&I system with state of the art technology (maxDNA)

7 Future Scenario Package-wise Retrofitting Turbine Modules Retrofitting
LP Turbine Modification Condenser Retrofitting C&I Retrofits (SG, TG & Station) Boiler Retrofits ESP Retrofits FGD Retrofits Mill / Feeder Retrofits VFD Retrofit

8 Typical Benefits of R&M
Power Station Unit Rating PLF before R&M PLF after R&M Improvement in PLF Improvement in output R&M of Korba (E) TPS of CSEB (completed in 2003 & 2005) 5 120 MW 62.8 % > 80 % >20 % (achieved) >24 MW 6 59.6 %

9 Post-R&M Performance (Panipat TPS)

10 R&M /LE orders finalized in country
Total units ordered (110 MW and above) 40 sets (5300 MW) Orders placed on BHEL 30 sets (3890 MW)* (75 %) Orders placed on others 10 sets (1410 MW) (25 %) * Orders for 3 nos. sets cancelled (340 MW)

11 R&M/ LE - Ordering Trend (MW)
CEA’s Plan vs Actual 7060 (59 sets)* 2600 (19 sets) 3750 (26 sets)* 890 (8 sets) 16532 (72 sets) Planned 36.83% 23.73% MW 620 MW (3 sets) 3.75% * Only BHEL sets are considered

12 Challenges in R&M and LE
Limited agencies for R&M and LE implementation in the country Unfavorable cost benefit analysis, if the scope is not optimized R&M activity to be limited with plant shutdown Many surprises during execution of R & M and LE Limited BOP suppliers BOP suppliers are loaded with new plant orders Many BOP suppliers are not willing to take up R & M and hence quote exorbitantly Contd..

13 Challenges in R&M and LE
Non availability of Civil foundation details and sub-surface details with customer No details available for modifications carried out earlier / spares used earlier The changes/ deterioration during the time from CA to execution need to be addressed by customer

14 Factors attributing delay in execution of R&M Projects
Delay in shut down of unit for R&M Long delay between RLA and R & M execution Lack of maintenance during this period causes further deterioration and increase in scope. Additional scope /surprises during execution Difficulties in interfacing of new system with the existing system Lack of suitable offers for bought out items from original vendors due to obsolete design Contd..

15 Factors attributing delay in execution of R&M Projects
Not getting clearance for PG Test immediately after stabilization of unit leading to delay in contract closure Inadequate documentation of process parameters by utilities Long deliveries quoted by vendors for rotor forgings etc. RLA, CA & PET to be carried out by the agency responsible for R & M Difficulty in procurement of sub vendor items Non existence of original vendors Non availability of original equipment details, specifications etc.

16 Partnership for Win-Win Scenario
Provision should be made in contract for RLA/CA study of Critical Components affecting the guarantee parameters, by the R&M executing agency, just before releasing the Unit for R&M. RLA – Scope final Ordering Engg., Manufacture & Supply Site Execution (Shutdown Period) PG Test (RLA of Critical Components) R&M supplier must be intimated well in advance for award of job to carry out R&M works so that necessary action could be taken proactively in the interest of the project. Hand holding approach during execution of R&M (12 months) (12 months) (18-24 months) (8-12 months) (6 months)

17 Advantage – BHEL (Experience & Infrastructure)
Original Equipment manufacturer Manufacturing facilities for Spares Availability of original design data & performance test results Minimum dependence on external sources First hand knowledge of O&M practices and problems Vast experience with Indian coal Contd..

18 Advantage – BHEL (Experience & Infrastructure)
Geared up to take up comprehensive R & M including BOP Developed technologies / retrofits to improve the performance Well developed labs for testing of coals, ash, material etc. Spares & Services Business Group (SSBG) has been created within BHEL to provide a ‘single window facility’ regarding R&M requirement of customers.

19 THANK YOU

20 REVISED EMISSION NORMS (dt. 7th Dec’15)
Year of Commissioning of Unit Capacity Target emission Level as per new norms A. Level of ‘SOx’ emission to be achieved Installed before Dec 2003 Capacity < 500 MW 600 mg/Nm3 Capacity > 500 MW 200 mg/Nm3 Installed from Jan 2004 to Dec 2016 B. Level of ‘NOx‘ emission to be achieved All ratings 300 mg/Nm3 C. Level of ‘Particulate Matter’ emission to be achieved 100 mg/Nm3 50 mg/Nm3

21 BHEL Experience in R & M AND LE ( Completed Projects)
S.N. Project 1 4 X110 MW KOTHAGUDEM, APGENCO (Up-rating to 4x120 MW) 2 2X120 MW KORBA, CSEB 3 2X110 MW ENNORE , TNEB 4 2 X 120 MW UKAI, GSECL 5 1X110 MW PANIPAT, HPGCL (Up-rating to 117 MW) 6 1X110 MW PANIPAT, Unit 2 (HPGCL) 7 2X110 MW BATHINDA, PSPCL (Up-rating to 2x120 MW) 8 2X110 MW MUZAFFARPUR, KBUNL 9 1X110 MW HARDUAGANJ, UPRVUNL 10 1x200 MW OBRA, UPRVUNL (Up-rating to 216 MW) Contd..

22 BHEL Experience in R & M AND LE (Projects under execution)
S.N. Project 1 1x210 MW KORADI, MAHAGENCO (Up-rating to 228 MW) 2 2X110 MW PATRATU, JSEB (Rehabilitation) 3 4X200 MW OBRA, UPRVUNL 4 2X110 MW BARAUNI, BSEB

23 List of Units (5857 MW) identified for retirement
S.N. STATION UNIT CAPCITY (MW) 1 PANIPAT TPS 1, 2, 3 & 4 4x110 2 OBRA TPS 40 3 50 4 8 94 5 PANKI TPS 105 6 HARDUAGANJ TPS 60 7 UKAI TPS 1 & 2 2x120 AMARKANTAK EXT TPS 9 DSPM TPS Korba 4x50 10 KORADI TPS 4x105 11 KOTHAGUDEM TPS 4x60 Contd..

24 List of Units (5857 MW) identified for retirement
S.N. STATION UNIT CAPCITY (MW) 12 KOTHAGUDEM TPS 5, 6, 7 & 8 4x120 13 RAMAGUNDEM - B TPS 1 62.5 14 ENNORE TPS 1 & 2 2x60 15 3, 4 & 5 3x110 16 PATRATU TPS 1, 2 & 3 3x40 17 5 90 18 8 105 19 SANTALDIH TPS 1, 2, 3 & 4 20 D.P.L. TPS 3 70 21 4 & 5 2x75

25 List of Units (4800 MW) identified for R&M
S.N. STATION UNIT CAPCITY (MW) 1 RAJGHAT TPS 67.5 2 GANDHINAGAR TPS 1 & 2 2x120 3 SIKKA REP. TPS 120 4 SATPURA TPS 6 200 5 7, 8 & 9 3x210 NASIK TPS 3, 4 & 5 7 KORADI TPS 8 210 9 BHUSAWAL TPS 2 & 3 2x210 10 PARLI TPS 11 CHANDRAPUR (MH.) TPS 1, 2, 3 & 4 4x210

26 CHANDRAPUR (ASSAM) TPS
List of Units (4800 MW) identified for R&M S.N. STATION UNIT CAPCITY (MW) 12 PATRATU TPS 4 40 13 6 90 14 7 105 15 D.P.L. TPS 110 16 CHANDRAPUR (ASSAM) TPS 1 & 2 2x30 17 BOKARO ‘B’ TPS 1 210 TOTAL 29 4800

27 BHEL Experience in ESP Retrofitting
S.N. Project 1 UKAI & WANAKBORI, GSECL (4x210 MW) 2 SINGRAULI, NTPC (5x200 MW + 2x500 MW) 3 UNCHAHAR, NTPC (2x210 MW) 4 KORBA, NTPC (3x200 MW + 3x500 MW) 5 TALCHER (Kaniha), NTPC (2x500 MW) 6 TALCHER, NTPC (2x110 MW) 7 VINDHYACHAL, NTPC (6x210 MW + 2x500 MW) 8 IB VALLEY, OPGCL (2x210 MW) 9 ROURKELA, NSPCL (2x60 MW) 10 SAIL, Sinter Plant (2 sets) Total 37 sets Contd..

28 BHEL Experience in C&I Retrofitting
S.N. Project 1 KORBA NTPC (3x200 MW) 2 FARAKKA, NTPC (2x500 MW) 3 DADRI, NTPC (4x210 MW) 4 NEYVELI, NLC (4x210 MW) Total 13 sets

29 R&M/LE Orders Finalized in India
S.N. Customer Project Rating (MW) Job awarded to 1 AECO Sabarmati Extn 110 NASL 2 Doosan 3 APGENCO Kothagudem BHEL 4 5 6 7 BSEB Barauni 8 9 CSPGCL Korba East 120 10 Contd..

30 R&M/LE Orders Finalized in India
S.N. Customer Project Rating (MW) Job awarded to 11 GSECL Ukai 120 BHEL 12 13 Gandhinagar 14 15 200 NASL 16 Wanakbori 210 17 HPGCL Panipat 110 18 JSEB Patratu 19 20 KBUNL Muzaffarpur Contd..

31 R&M/LE Orders Finalized in India
S.N. Customer Project Rating (MW) Job awarded to 21 KBUNL Muzaffarpur 110 BHEL 22 MAHAGENCO Koradi 210 23 MPPCL Amarkantak Ext. 120 NASL 24 25 PSEB Bhatinda 26 27 28 29 TANDEDCO Ennore 30 Contd..

32 R&M/LE Orders Finalized in India
S.N. Customer Project Rating (MW) Job awarded to 31 TANDEDCO Ennore 110 SKODA 32 UPRVUNL Harduaganj BHEL 33 Obra 200 34 100 35 36 37 38 39 40 WBPDCL Bandel 210 Doosan


Download ppt "EXPERIENCE SHARING 4th April 2016   SSBG."

Similar presentations


Ads by Google