Download presentation
Presentation is loading. Please wait.
1
LCLS-II CMTF@LERF For LCLS-II Cryomodule Testing at JLab
E. Daly / K. Jordan / C. Hovater / M. Wiseman with help from Accel Ops and Engineering 03-AUG-2017
2
LERF Vault as Cryomodule Test Facility (CMTF) Phasing
Outline Overview Introduction LERF Vault as Cryomodule Test Facility (CMTF) Phasing Cost / Schedule / Staffing Assumptions / Constraints Impacts / Risks Summary REV3, 03-AUG-2017
3
Using LERF as Cryomodule Test-Bed - Overview
A detailed scope, cost and schedule estimate for installing and testing LCLS-II cryomodules (two-at-a-time) as an assembly in the LERF has been developed in response to possible LCLS-II project needs. Estimate considers four phases of increasing scope - short term limited testing (microphonics & technical characterization) up to a full test bed (a possible mitigation for schedule recovery) to operate in parallel with the CMTF in the Test Lab. Phase 1 – Set Up LERF for CM testing Phase 2 – First pair of CMs - Initial Full Power Testing Phase 3 – Three Production CM testing cycles A typical test cycle is 5-8 weeks Phase 4 – Restore LERF REV3, 03-AUG-2017
4
Using LERF as Cryomodule Test-Bed - Opportunity
The LCLS-II project has discovered issues with microphonics during the prototype cryomodule testing phase at FNAL and JLab Development on-gooing to demonstrate closed-loop RF control due to microphonics Need to achieve expected cryogenic conditions in testing facilities In the longer term, a place to conduct integrated RF/Cryo testing and an additional place to test cryomodules could be very useful for both LCLS-II and JLab LERF has existing utilities (water, electrical, cryogenic, waveguides, radiation shielding, personnel protection, etc.) and is situated near a large-scale cryogenic plant Similarity to actual LCLS-II machine conditions – large Cryoplant located near operational cryomodules Address microphonics and large-scale issues which cannot be assessed in smaller cryogenic testing facilities REV3, 03-AUG-2017
5
Approach Phase I – Convert the FEL vault into a cryomodule testing facility to conduct integrated RF testing of CM/LLRF/HPRF (using Solid State Amplifiers) Phase II / Phase III – Utilize facility to expand capability to test multiple cryomodules in order to mitigate possible schedule delays caused by late CM assembly activities. Phase IV – Restore LERF REV3, 03-AUG-2017
6
LCLS-II CM Layout in LERF – Testing 2 CMs per Cycle
CM Slot CM Slot CM Slot Access Storage Current machine contains slots for 3 full CMs and 1 Injector CM Shielded vault Existing PSS including radiation and ODH monitoring Utilities include cryo, water, electrical Propose 2 CMs installed in middle of FEL machine REV2, 03-AUG-2017
7
Preliminary Detailed P6 Cost Estimate
Set Up First Test Three Tests Restoration Full cost recovery Including operating cost estimates for LERF Operating costs - $10.8K/week while CM is cold Path forward assuming JLab approval Proposal brought into the LCLS-II project baseline via baseline change request – expect some minor cost adjustments Subsequently managed using EVMS to monitor and report on progress REV3, 03-AUG-2017
8
P6 Schedule (1/2) REV3, 03-AUG-2017
9
P6 Schedule (2/2) REV3, 03-AUG-2017
10
CEBAF Operations – Constraints on LERF Ops
CEBAF Operation Plan FY18 Q1 – 10 wks (Oct/Nov/Dec) – Highly Likely FY18 Q2 – 6 wks (Feb/Mar) – Highly Likely FY18Q3 – 8 wks at 6 GeV - TBC CHL Configurations FY18 Q1/Q2 – 2 x (CHL + Cold Boxes) Transition by May 6th to 1 CHL FY18 Q3/Q4 – 1 x (CHL + Cold Box) – Two week transition at 4K (cold down opportunity) Transition by Sep 10th to 2 CHLs Cryogenics U-tube ops required at 4K Integrate with maintenance plans on SC1 (Ops on SC2 – FY18Q3) Power Consumption Off-peak running will save on power bill Mitigates the demand charge for the next year REV3, 03-AUG-2017
11
Schedule Integrated with CEBAF Operations
Testing cycles could occur three times per FY at the conclusion of planned CEBAF runs First testing cycle most likely in Jul-2018 contingent upon actual FY2018 run schedule and staffing availability REV3, 03-AUG-2017
12
P6 Labor Profile (1/2) – Incremental Labor Required
Incremental labor required to convert LERF and support testing (doesn’t include actual testing labor) CM Tests REV3, 03-AUG-2017
13
P6 Labor Profile (2/2) – Incremental + Testing Labor
Total labor required to convert LERF and support testing (includes actual testing labor time-phased) CM Tests REV3, 03-AUG-2017
14
Assumptions Priority for JLab is 12 GeV Operations
Schedule for testing CMs will be coordinated with FY2018 & FY2019 run schedules CM testing windows will be adjusted to minimize impact on NP program Full cost recovery from LERF operations is required Defined boundaries between laboratory program and WFO Cost includes specific LERF facility charges Draft cost and schedule presented in parallel to LCLS-II and JLab management. Updates and revisions based on discussions are included Staffing requirements will be considered as part of overall FY2018/2019 laboratory planning. Priority consistent with WFO vs. CEBAF operations. Recommend meeting with LCLS-II Project Director, Lab Director and Chief Planning Officer to review and discuss overall plan REV3, 03-AUG-2017
15
Impacts & Risks Cryogenics: present 2K issues complicate near term scheduling. Contamination is a concern that could affect availability. Can’t stab U-tubes during CEBAF ops (need 4K for 1 week) Repeated stabbing adds potential contamination problems Cooldown and warm-up : overall cryo load must be handled properly with controls. CEBAF Operations: Phase I no impact. Phase II & III requires PSS Control and interface. Cannot keep two of the FEL CMs cold as CEBAF spares. Coordination is required with other cryo activities. Phase II & III need coordination with CEBAF 12 GeV operations. LERF Operations: Phase II and Phase III would eliminate all other LERF operations. Staffing: Initial plan utilizes combination of in-house staff and possibly term hires. Higher priority work might limit available staff. Schedule: Working towards July test cycle (April if all goes very well.) REV3, 03-AUG-2017
16
LERF Vault as Cryomodule Test Facility
Summary LERF Vault as Cryomodule Test Facility Full Cost Recovery - ~ $4M over 18 to 24 months Provide parallel testing facility to reduce testing bottleneck (12 to 15 CMs may need to be tested in FY2018/FY2019) and mitigate schedule delays due to cavity supply and CM design issues Seeking decision from LCLS-II management regarding proposal for LERF facility REV3, 03-AUG-2017
17
Back Up REV3, 03-AUG-2017
18
JLab Proposed Layout for LCLS-II CM Production
CM Testing Phase II CM Assembly (2X) Clean Room String Assembly Phase I CM Assembly (2X) Final Assembly / Prep for Testing Vacuum Vessel Installation REV3, 03-AUG-2017
19
JLab Facilities Improvements : Testing in CMTF
Draft FRS for CMTF in Progress (LCLSII-4.6-FR-0285); Similar to FNAL CMTS1 FRS Ability to run 8 cavities simultaneously End Cans (2 sets to support CM production rate) Engineering Specification JL S in Review/Approval Process Connects CM to CTF valve box via u-tubes Interfaces for valves, LL and diodes to monitor and control helium flow/inventory Provides reliefs for primary circuit, shield circuit and insulating vacuum space HPRF Receive 1.3 GHz 3.8 kW Solid-State Amplifiers (SSAs) Procure Circulators Modify Waveguide and Interlocks Run line power to SSA/Circulators Provide controls in CMTF Control Room LLRF RF Instrumentation (arc detectors, IR sensors, etc.) Provide digital controls in CMTF Control Room Software development Cryogenic Test Facility (CTF) Improve return side piping to reduce overall pressure drop from CMTF Ensure recovery system (pumping, compression) provides base pressure of atm (23 torr) in the CM helium bath Improve/replace aging instrumentation such as arc cells, flow meters and temperature sensors REV3, 03-AUG-2017
20
JLab CMTF HPRF system suitable for individual cavity testing or 8 cavities in short duration steady state TBD system for testing SC magnet – need PS & leads info Magnetic shielding encloses testing volume reducing external fields to less than 50 mG Cryogenic capacity for testing up to 8 cavities in CW mode End Caps – specific for LCLS-II CM testing Interface to CM piping and existing junction box using u-tubes REV3, 03-AUG-2017
21
JLab CMTF Conceptual Layout
JUNCTION BOX * = New Hardware BAYONET BOX* END CAP* BAYONET U-TUBE* CAVE DOOR (CLOSED) HEAT EXCHANGER End view of CM with bayonets connecting JB, HX and BB REV3, 03-AUG-2017
22
Approval Process THE PROCESS INVOLVES FOUR STAGES: STAGE 1 – INITIAL EXPLORATION WITH POTENTIAL PARTNERS STAGE 2 – EVALUATION BY PRIMARY DIVISION MANAGER STAGE 3 – DECISION BRIEFING TO LABORATORY LEADERSHIP STAGE 4 – APPROVAL BY DOE REV3, 03-AUG-2017
23
STAGE 3 –DECISION BRIEFING TO LABORATORY LEADERSHIP*
Prepare a decision briefing, using the information from the Proposal Information Form (PIF), to obtain lab approval. The briefing must include the following elements: a. Outside Work Opportunity Title and Partner b. Overview of opportunity: description of work with deliverables and milestones c. Details of the opportunity: duration; resources needed, key skills, infrastructure needs, partner contribution d. Complete Budget Estimate form through the Budget Office (By FY, FTEs by skill, and non-labor) e. Benefit to Lab (how does opportunity supports JLab’s mission and scientific goals, core competencies, etc.) f. Proposed method for receiving funds (FOA, Grants, proposals, CRADAs in support of SBIR/STTR proposals, Work for Others, IAA, CRADAs, IWOs, etc.) Lab Leadership recommends that the Laboratory Director approves the initiative. Some initiatives may need DOE approval. The preparation of relevant documents is described under Stage 4, below. If approved, the PI has an actual commitment from the Lab to continue to Stage 4. If the proposal does not include new funds into the Lab then it can be approved without moving to Stage 4. *Taken directly from Lab Approval Process REV3, 03-AUG-2017
24
Phase I – Configure LERF for Testing
Removal of 20’ of back leg of existing machine to install/position CMs Removal of u-tubes from two existing CMs in FEL vault Can remove two high performing CMs to augment CEBAF Requires a set of u tubes to connect CMs to existing cryogenic transfer line bayonet connections Review design; procure cryogenic hardware Requires one set of CM testing end caps (same design as CMTF) Requires two sets of stands (same design as CMTF) Requires one set of interconnect hardware including HOM BLA, bellows Install cryogenic controls (Cryocon temp readbacks, heaters, JT and cooldown valves, etc.) Pull cabling Install SLAC-provided SSAs and HPRF hardware Install SLAC-provided LLRF controls Review and approve any updates to OSP for FEL vault operations Decarad and Faraday cups for radiation monitoring REV3, 03-AUG-2017
25
Phase II – Initial Full Power RF/Cryo Testing
Assumes all hardware from Phase I available Schedule allows for more time and resources for initial testing cycle Install pair of CMs in LERF Connect RF, instrumentation and cryo controls Coordinate cooldown with CEBAF operations Evaluate procedures for cooldown, RF testing and warm up Coordinate warm up with CEBAF operations Remove pair of CMs from LERF REV3, 03-AUG-2017
26
Phase III – CM Acceptance Testing
Assumes Phase II completed Schedule considers logistics for installing multiple CMs in LERF vault Staffing estimate will be based on current project baseline Assumes one test cycle in CMTF / 5 wks Potential impact - CMTF & LERF testing is conducted in parallel REV3, 03-AUG-2017
27
Assumes Phase III completed
Phase IV – Restore LERF Assumes Phase III completed Remove any LCLS-II specific hardware from vault Replace LERF specific hardware REV3, 03-AUG-2017
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.