Presentation is loading. Please wait.

Presentation is loading. Please wait.

Electricity System Cost Outlook

Similar presentations


Presentation on theme: "Electricity System Cost Outlook"— Presentation transcript:

1 Electricity System Cost Outlook
MODULE 7: Electricity System Cost Outlook August 2016

2 Overview The following module provides an illustration of the cost of the electricity system across the demand outlooks presented in the Ontario Planning Outlook Further information with respect to the demand outlooks can be found in Module 2 “Demand Outlook” The total cost of electricity service and average unit cost for electricity service are illustrated for each of the demand outlooks The cost outlooks illustrated here are not forecasts. They illustrate a range of potential outcomes based on the assumptions made. There are many assumptions with varying levels of uncertainty. These assumptions could change over time. The purpose of this module is to illustrate a range of potential outcomes. They are best interpreted in relation to each other and serve to inform discussions on how to meet electricity system needs across the demand outlooks. This is facilitated by illustrating a number of resource portfolios for meeting the four demand outlooks. The resource portfolios are illustrative. It is recognized that many options exist beyond those considered here.

3 Electricity System Cost Outlook
The electricity system cost outlook varies with the outlook for supply resources which in turn varies with the outlook for demand. The cost of delivering, operating, and maintaining electricity resources (conservation, generation, and transmission/distribution) and the extent to which investments are made in new resources vary with the level of electricity demand. As described in Module 4 “Supply Outlook”, Ontario: Could meet flat demand outlooks provided that existing resources continue to operate, planned resource come into service, and arrangements can be made for the continued operations of resources past their current contract expiry. Ontario could also take advantage of improvements in technology performance and costs that may emerge to replace existing resources as contracts expire. Could find itself in a position of excess supply over the planning outlook under low demand outlooks Would require more electricity resources than it has today to serve higher demand outlooks There are a number of ways in which electricity demand can be met across each of the demand outlooks. Some of these are illustrated in the following slides for each of the four demand outlooks. Each demand outlook has a resource requirement. Developing cost outlooks for the four demand outlooks entailed making assumptions about the cost and performance of resource options for the purpose of illustrating relative cost performance to inform discussions with policymakers and stakeholders.

4 Electricity System Cost Outlook:
Outlook B “Flat” Demand Outlook

5 Overview of Electricity System Cost Outlook: Outlook B
In demand Outlook B, Ontario could meet flat demand outlooks with existing and planned resources provided they continue to operate following contract expiry Ontario could also take advantage of improvements in technology performance and costs that may emerge to replace existing resources as contracts expire. Opportunities in this regard include ongoing evolution in renewable technologies, storage technologies, distributed energy resources, clean energy imports and others Ontario could adapt by not recontracting with generation facilities when contracts expire Ontario also has the option of exercising nuclear refurbishment off-ramps where there are more economic electricity supply alternatives To illustrate the outlook for electricity costs in demand Outlook B, it is assumed that existing resources continue to operate, planned resources come into service, and arrangements can be made for the continued operations of resources past their current contract expiry. No new transmission investments is assumed to be required beyond those currently in various stages of development (see Module 5) It is assumed that resources with expired contracts continue to operate at costs below existing contract rates, reflecting the reduced cost of capital for continuing to operate these facilities (relative to building new resources)

6 Change in Resource Requirements: Outlook B
Existing, Committed, and Directed resources would be sufficient to meet the flat demand outlook assuming resources with expiring contracts continue to operate Further information on conservation and demand response resources can be found in Module 3. Further information on supply resources can be found in Module 4.

7 Change in Resource Requirements: Outlook B, Summer
  Capacity at Time of Summer Peak Demand, MW 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 Nuclear 12,939 12,061 11,242 10,364 8,581 10,277 7,446 Natural Gas 8,774 8,784 9,153 9,943 10,019 Waterpower 6,206 6,232 6,295 6,299 6,300 6,325 6,378 Bioenergy 537 540 543 591 621 Wind 553 579 594 624 685 Solar PV 711 806 927 1,044 1,134 1,236 1,336 Storage & Demand Response 616 633 802 971 1,140 Firm Import (if needed) 500 TOTAL 30,337 30,118 30,705 31,666 30,879 30,195 30,280 28,768 30,687 28,125 Capacity at Time of Summer Peak Demand, MW 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 8,259 8,208 9,026 9,845 6,441 6,578 684 28,501 28,587 29,404 30,223

8 Change in Resource Requirements: Outlook B, Winter
Capacity at Time of Winter Peak Demand, MW 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 Nuclear 11,651 10,773 9,076 9,954 6,929 7,807 6,673 Natural Gas 9,267 9,325 9,623 9,694 10,613 10,704 Waterpower 6,562 6,577 6,627 6,657 6,662 6,663 6,689 6,745 Bioenergy 537 539 542 543 591 621 Wind 1,240 1,338 1,445 1,520 1,670 Solar PV 100 106 116 130 146 158 172 Storage & Demand Response 442 458 524 678 832 TOTAL 29,799 29,099 29,567 29,700 29,057 30,102 29,265 27,295 28,340 27,417 Reserved for Quebec (500) Total Available for Ontario 29,299 28,599 29,067 29,200 28,557 29,602 28,765 26,795 27,840 26,917 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 7,486 7,435 8,254 8,253 9,072 6,811 6,956 1,669 185 987 27,584 28,463 29,375 30,193

9 Electricity production in 2035 relative to 2015: Outlook B

10 Electricity production in 2035 relative to 2015: Outlook B
Energy Production, TWh 2015, Actual 2035, Outlook B Nuclear 92 73 Natural Gas 16 14 Waterpower 37 41 Non-Waterpower Renewables 24 Total 159 152

11 Electricity production, 2016-2035: Outlook B

12 Electricity production, 2016-2035: Outlook B
Energy Production, TWh 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 Nuclear 92 86 83 81 75 73 65 56 Natural Gas 12 10 9 8 11 Waterpower 36 37 38 39 40 Non-Waterpower Renewables 17 18 19 20 21 22 23 24 Total 157 151 149 152 150 145 144 138 147 132  Energy Production, TWh 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 62 67 68 70 66 72 14 41 136 141 142 143

13 Cost Assumptions Existing and committed generation costs for generators of all fuel types are based on the contract prices negotiated. OPG regulated rates for nuclear and waterpower are as provided by OPG. Cost assumption for resources assumed to be recontracted following end of their contract term is outlined in the next slide Conservation program cost reflects IESO experience with conservation programs. Transmission costs are based on the 2016 Hydro One Transmission Revenue Requirement EB Decision and Order, plus the cost for incremental capital projects required to meet resource requirements. Distribution costs are based on 2015 OEB Yearbook distribution cost indexed to the growth of housing stocks. Wholesale Market Service Charge components that are market based such as auxiliary services, IOG are indexed the change in the cost of generation. IESO fees and legislated rates (i.e., Rural/Remote Settlement Rate) are assumed to remain constant. Debt Retirement Charge is based on the legislated rate of $7/MWh in nominal dollars for 2016 to 2018, and applicable to non-residential customers

14 Repowering Cost Assumptions
Assumption of cost of continuing to operate resources following the end of their contract term Resource Type Repowering Cost Assumptions Non-Utility Generators (NUGs) - for all expired NUG Contracts (Bio, MSW (Municipal Solid Waste), and Gas) Variable cost component plus 50% of the fixed costs Natural Gas  Lennox As per original contract CCGT All original contract price components, with 20% of the capital portion SCGT CHP MSW (Municipal Solid Waste) All original contract price components, with 35% of the capital portion Waterpower Assumes the regulated non-prescribed waterpower rates Bioenergy  Thunder Bay Bio Conversion Atikokan Bio Conversion (ABESA) CHP3 RES BIO, RESOP, Advance RESOP Fit Amendment (ARFA), MicroFIT/FIT Base Contract Price, variable component plus 35% of the capital component Wind Consistent with the procurement rates for LRP I wind Solar PV Consistent with the procurement rates for LRP I solar Source: IESO.

15 Total Cost of Electricity Service: Outlook B

16 Total Cost of Electricity Service: Outlook B
2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 Total Cost of Electricity Services (2016$) 20.7 21.3 21.2 20.5 21.5 20.8 20.9 21.0 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 20.4 20.2 20.1 19.9 19.4

17 Average Unit Cost of Electricity Service: Outlook B

18 Average Unit Cost of Electricity Service: Outlook B
2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 Demand: Outlook B (TWh) 143 142 B (2016$/MWh) $144 $149 $151 $146 $147 $148 $152 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 141 144 145 146 148 $145 $150 $143 $141 $140 $137 $136 $131

19 Electricity System Cost Outlook:
Outlook A “Low” Demand Outlook

20 Overview of Electricity System Cost Outlook: Outlook A
In demand Outlook A, by 2035 the electricity peak demand is 2 GW less than in Outlook B and energy consumption is 15 TWh less. The reduction in peak demand translates to a reduction in total resource requirement of 2.5 GW after accounting for the reduction in reserve requirements. Ontario could find itself with resources in excess of demand. There are a number of ways in which lower electricity demand can be met: Ontario could adapt to low demand outlooks by not recontracting with generation facilities when contracts expire Ontario also has the option of exercising nuclear refurbishment off-ramps in response to sustained, very low demand expectations To illustrate the outlook for electricity costs in demand Outlook A, two illustrative resource outlooks were developed to reflect potential ways to address the low demand outlook: A1 “Gas, Solar PV & Wind”: As resource contracts expire, they are assumed to be not recontracted. This includes a reduction in gas-fired resources for capacity and solar PV and wind resources for energy in quantities that are in excess of resource requirements. A2- “Gas & Nuclear”: As gas-fired resource contracts expire they are assumed to be not recontracted due to reduced capacity requirements. Two nuclear units are not refurbished due to reduced energy requirements. The reduction in resources is equivalent to the reduction in capacity requirements and energy consumption relative to Outlook B. No changes in transmission and distribution costs, relative to Outlook B, was assumed.

21 Change in Resource Requirements: Outlook A
The overall reduction in available capacity at time of system peak is the same for the two options (~2.5 GW) In A1 “Gas, Solar PV & Wind”, the reduction in peak capacity is greater for natural gas than for wind and solar PV. The lower capacity contributions of wind and solar PV at the time of peak demand translates to a larger reduction in their installed capacity.

22 Change in Resource Capacity: Outlook A
Capacity Reduction, MW A1, At Peak A2, At Peak A1, Installed A2, Installed Nuclear 1,644 Natural Gas 1,700 981 1,090 Wind 460 4,600 Solar PV 600 2,000

23 Electricity production in 2035 relative to 2015: Outlook A

24 Electricity production in 2035 relative to 2015: Outlook A
Energy Production, TWh 2015, Actual 2035, A1 2035, A2 Nuclear 92 73 60 Natural Gas 16 15 Waterpower 37 41 Solar PV, Wind & Bioenergy 14 9 24

25 Total Cost of Electricity Service: Outlook A

26 Total Cost of Electricity Service: Outlook A
2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 A - High Range (2016$) $20.7 $21.3 $21.1 $20.4 $20.5 $20.6 $20.9 A - Low Range (2016$) $21.0  Total Cost of Electricity Service 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 $19.9 $20.3 $19.8 $19.6 $19.4 $19.3 $19.0 $18.8 $18.2 $20.2 $19.7 $19.2 $18.6 $18.4 $17.8

27 Average Unit Cost of Electricity Service: Outlook A

28 Average Unit Cost of Electricity Service: Outlook A
2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 Demand: Outlook A (TWh) 143 142 141 139 138 136 135 134 133 A - High Range (2016$/MWh) $144 $150 $146 $154 $152 $153 $158 A - Low Range (2016$/MWh)  Average Unit Cost of Electricity Service 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 132 131 $151 $157 $155 $149 $147 $142 $136 $145 $139 $134

29 Electricity System Cost Outlook:
Outlook C & D “Higher” Demand Outlook

30 Overview of Electricity System Cost Outlook: Outlooks C & D
Ontario would require more electricity resources than it has today to serve higher levels of electricity demand growth. In addition, Ontario would transition back to a winter peaking jurisdiction due to the increase in electric heating loads. While higher demand could create a need for additional resources in the longer-term, these needs are not projected to occur until the mid-2020s Resources considered for inclusion in the outlooks include conservation, wind, solar PV, waterpower, bioenergy, demand response, nuclear, firm imports, and natural gas. In light of Ontario transitioning to a winter peaking system, it was found that solar PV would have a limited role in meeting capacity requirements in the winter (when solar insolation is low). Solar PV has the potential to reduce demand requirements other times of the year. As additional solar PV is incorporated though the net-metering program, it would be reflected in the net demand that is to be served. Gas-fired resources provide considerable flexibility and can facilitate the integration of variable resources. Opportunities could exist for other technologies such as storage to provide similar services. Currently these technologies are higher cost than the resources considered. Opportunities exist to incorporate lessons learned from the various storage pilot projects underway.

31 Overview of Electricity System Cost Outlook: Outlooks C & D (continued)
As described in Module 4, Ontario faces sizeable and increasing opportunities for further deployment of cleaner technologies including distributed energy resources to meet higher demand outlooks. These opportunities are being driven by technological advancements, evolutions in policy and market design and increasing customer engagement. No single technology is expected to fully meet potential increases in electricity demand. Some resources are baseload in nature, others are peaking. Some have higher costs, other lower. Some produce GHG emissions, while others do not. To illustrate a range of potential electricity cost outlooks under higher demand outlooks, a number of resource outlooks are presented. The resource outlooks were constructed in the following manner: The increase in capacity and energy requirements in Outlook C and Outlook D are met, taking into consideration reserve requirements GHG emissions are kept at or below those illustrated in Outlook B Sufficient resources are included to meet system operability requirements as they relate to ramping requirements (see Module 5) to facilitate the integration of renewable resources Additional transmission is included to accommodate new resources The electricity cost outlook in Outlook C and Outlook D reflect the capital investment in new resources, operations and maintenance cost, fuel cost, and incremental transmission investments Due to the limited information available to the IESO, it was assumed that distribution system costs remain unchanged relative to Outlook B. However, it is recognized that these costs would also increase in order to accommodate the additional investments distribution companies would require to serve additional load.

32 Conservation opportunities in Outlooks C and D
All demand outlooks reflect the achievement of the 2013 LTEP conservation targets for existing loads. A considerable amount of conservation is assumed in the demand outlooks. New loads that drive the increases in demand are assumed to occur efficiently (i.e. fuel switching leads to an uptake in heat pumps as opposed to baseboard heating) and there is limited potential for additional future conservation savings on fuel switching actions that are being undertaken (described further in Module 3). Higher demand outlooks provide greater potential for electricity conservation from existing loads: The value of conservation is greater in the higher demand outlooks because in these outlooks incremental conservation will avoid the construction of new electricity infrastructure and increase the avoided costs These increased avoided costs of conservation will unlock conservation potential from existing end uses which are uneconomic under outlook B, supporting higher investment in more efficient technologies The cost outlooks set out in the following slides provide an illustration of the cost of electricity service. Additional investments in cost effective conservation would help meet the demand and reduce the cost of electricity service as less infrastructure investment would be required Further work is needed to understand the amount of available additional conservation potential under the higher demand outlooks. The cost analysis assists in the development of avoided costs for conservation potential assessments.

33 Capacity Contribution at Summer/Winter Peak
Input assumptions for cost, performance, maximum available capacity, and lead time for new resources The input assumptions for each resource are based on the information provided in Module 4 Incremental Resource LUEC (2016$/MWh) Capacity Cost ($/kW-year) Capacity Factor Construction Lead Time Capacity Contribution at Summer/Winter Peak Notes Simple Cycle Natural Gas-Fired Turbine N/A $135 0-1%* 3 years 89%/95% Peak capacity Large Nuclear $120 85% 10 years 99%/90% Waterpower $140 50% 63%/67% Maximum new, incremental waterpower capacity of 6,000 MW Wind $86 30% 10%/20% Solar PV $90 (2030) 15% 20%/3% Bioenergy $164 80% 90%/90% Demand Response $100 N/A* 85%/60% Max capacity of 2,000 MW Firm Imports (<1,250 MW) Up to 85% 5 years 95%/95% Not available for winter capacity prior to 2028 (Up to 3,300 MW) $160 *Simple Cycle Natural Gas-Fired Turbine and Demand Response are capacity based resources. The cost of these resources is not expressed as a LUEC (levelized unit energy cost) due to the limited amount of energy these resources are expected to provide (due to their low utilization).

34 Outlook C

35 Overview of Outlook C Electricity System Cost Outlook
In demand Outlook C, by 2035 the electricity peak demand is 2.5 GW (Summer) and 6.7 GW (Winter) more than in Outlook B and energy consumption is 30 TWh more. The increase in peak demand translates to an increase in total resource requirement of 5.6 GW after accounting for reserve requirements. To illustrate the outlook for electricity costs in demand Outlook C, three illustrative resource outlooks were developed to reflect potential ways to address this particular higher demand future: C1 “Wind, Waterpower, Demand Response, Firm Imports”: A mix of renewable resources are added supplemented by additional demand response for capacity and firm imports. C2 “Wind, Demand Response, Gas, Firm Imports”: Assumes new waterpower is out of scope. Gas-fired resources are added to provide capacity. C3 “Wind, Demand Response, Nuclear, Firm Imports”: Assumes new waterpower is out of scope but new nuclear is in scope to meet energy requirements. The amount of new resources added is equivalent to the increase in capacity requirements and energy consumption relative to Outlook B. The bulk electricity system would require additional investments in transmission to incorporate these resource additions as outlined in the next slide.

36 Change in Resource Requirements: Outlook C
Three resource outlooks were developed to illustrate a range of possible approaches to meeting the increased demand in Outlook C

37 Change in Resource Requirements: Outlook C
Capacity Additions, MW C1, Installed C2, Installed C3, Installed Nuclear 1,700 Waterpower 2,500 Wind 2,550 5,950 1,550 Gas 1,900 Demand Response 600 900 800 Firm Imports 1,800  Capacity Additions, MW C1, At Peak C2, At Peak C3, At Peak 1,750 410 1,190 310 480 720 640

38 Electricity production in 2035 relative to 2015: Outlook C

39 Electricity production in 2035 relative to 2015: Outlook C
Energy Production, TWh 2015, Actual 2035, C1 2035, C2 2035, C3 Nuclear 92 73 86 Natural Gas 16 14 15 Waterpower 37 52 41 Solar PV, Wind & Bioenergy 29 40 28 Firm Imports 10 11

40 Bulk transmission requirements for Outlook C outlooks
The Outlook C outlooks require bulk transmission upgrades in order to be incorporated into the transmission system. Estimated total capital costs of conceptual transmission options explored for Outlook C range between $4.0 billion and $9.5 billion (2016$), depending on the resource outlooks Additional information on the nature of these transmission options can be found in Module 5 Resource Outlook Transmission Projects to Enable New Resources Total Capital Cost (2016$) C1 North-South Reinforcements, Sudbury West Reinforcements, Sudbury North Reinforcements, Enabling Facilities, New HVDC Line from Quebec to Lennox $7.2 Billion C2 North-South Reinforcements, Sudbury West Reinforcements, Sudbury North Reinforcements, Enabling Facilities, New HVDC Line from Quebec to Lennox, West of London Reinforcements $9.5 Billion C3 North-South Reinforcements, Sudbury West Reinforcements, Enabling Facilities, New HVDC Intertie from Quebec to Lennox, Reinforcements from Bowmanville to GTA, New HVDC Line from Quebec to Lennox $4.0 Billion

41 Total Cost of Electricity Service: Outlook C

42 Total Cost of Electricity Service: Outlook C
Total Cost of Electricity Service (2016$ Billions) 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 C1 - Wind, Waterpower, Demand Response, Firm Imports $20.7 $21.4 $21.3 $20.6 $21.6 $20.9 $21.5 $21.8 $21.7 $23.0 C2 - Wind, Demand Response, Firm Imports, Gas $23.2 C3 - Wind, Demand Response, Nuclear, Firm Imports $21.9 $22.8 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 $22.0 $22.6 $22.3 $22.2 $22.9 $23.3 $22.5 $22.4 $23.1 $22.1 $22.7

43 Average Unit Cost of Electricity Service: Outlook C

44 Average Unit Cost of Electricity Service: Outlook C
Average Unit Cost of Electricity Service (2016$/MWh) 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 Demand: Outlook C (TWh) 144 143 145 146 147 148 149 151 C1 - Wind, Waterpower, Demand Response, Firm Imports $144 $149 $148 $143 $147 $145 $153 C2 - Wind, Demand Response, Firm Imports, Gas $154 C3 - Wind, Demand Response, Nuclear, Firm Imports $151 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 152 154 156 158 161 163 166 170 173 177 $141 $138 $140 $135 $134 $132 $146 $150 $142 $139 $136 $130 $137 $131

45 Outlook D

46 Overview of Electricity System Cost Outlook: Outlook D
In demand Outlook D, by 2035 the electricity peak demand is 3.7 GW (Summer) and 13 GW (Winter) more than in Outlook B and energy consumption is 50 TWh more. The increase in peak demand translates to an increase in total resource requirement of 11.4 GW after accounting for reserve requirements. To illustrate the outlook for electricity costs in demand Outlook D, four illustrative resource outlooks were developed to reflect potential ways to address this particular higher demand future: D1 “Wind, Waterpower, Demand Response, Firm Imports”: A mix of renewable resources are added supplemented by additional demand response for capacity and firm imports. D2 “Wind, Demand Response, Waterpower, Gas, Firm Imports”: Assumes gas-fired resources are added to supplement renewable additions. The gas-fired resource provides capacity and makes up for the lower capacity contribution of renewables. D3 “Wind, Waterpower, Demand Response, Nuclear, Firm Imports”: Assumes new nuclear is in scope to meet energy requirements. D4 “Wind, Demand Response, Nuclear, Gas, Firm Imports”: Assumes new nuclear is in scope to meet energy requirements. The gas-fired resource provides capacity and makes up for the lower capacity contribution of renewables. The amount of new resources added is equivalent to the increase in capacity requirements and energy consumption relative to Outlook B. This is more than in Outlook C. The bulk electricity system would also require additional investments in transmission to incorporate new resources as outlined in the next slide.

47 Change in Resource Requirements: Outlook D
Four resource outlooks were developed to illustrate a range of possible approaches to meeting the increased demand in Outlook D The four outlooks represent a diverse approach to meeting the higher demand outlook. The scale of new resource build demonstrates the challenges associated with significant electrification.

48 Change in Resource Requirements: Outlook D
Capacity Additions, MW D1, Installed D2, Installed D3, Installed D4, Installed Nuclear 3,400 2,500 Waterpower 6,000 3,700 1,850 Wind 9,600 4,500 4,250 Gas 2,450 2,050 Demand Response 2,000 1,900 1,750 Firm Imports 3,300 D1, At Peak D2, At Peak D3, At Peak D4, At Peak 4,200 2,950 1,295 1,920 1,200 900 850 1,600 1,520 1,400

49 Bulk Transmission Requirements for Outlook D outlooks
Outlook D outlooks require bulk transmission upgrades in order to be incorporated into the transmission system. Estimated total capital costs of conceptual transmission options explored for Outlook C range between $7.4 billion and $24 billion (2016$), depending on the resource outlooks Additional information on the nature of these transmission options can be found in Module 5 Resource Outlook Transmission Projects to Enable New Resources Total Capital Cost (2016$) D1 North-South Reinforcements, Sudbury West Reinforcements, Sudbury North Reinforcements, Enabling Facilities, New HVDC Line from Quebec to Lennox and a New HVDC Line from Quebec to GTA $24 Billion D2 North-South Reinforcements, Sudbury West Reinforcements, Sudbury North Reinforcements, Enabling Facilities, New HVDC Line from Quebec to Lennox and a New HVDC Line from Quebec to GTA, West of London Reinforcements $17.1 Billion D3 North-South Reinforcements, Sudbury West Reinforcements, Sudbury North Reinforcements, Enabling Facilities, New HVDC Line from Quebec to Lennox and a New HVDC Line from Quebec to GTA, Reinforcements from Bowmanville to GTA $7.4 Billion D4 North-South Reinforcements, Sudbury West Reinforcements, Sudbury North Reinforcements, Enabling Facilities, New HVDC Line from Quebec to Lennox and a New HVDC Line from Quebec to GTA, Reinforcements from Bowmanville to GTA, West of London Reinforcements $12.5 Billion

50 Electricity production in 2035 relative to 2015: Outlook D

51 Electricity production in 2035 relative to 2015: Outlook D
Energy Production, TWh 2015, Actual 2035, D1 2035, D2 2035, D3 2035, D4 Nuclear 92 73 101 87 Natural Gas 16 12 17 11 Waterpower 37 67 57 52 49 Solar PV, Wind & Bioenergy 14 48 40 36 35 Firm Imports  0 20

52 Total Cost of Electricity Service: Outlook D

53 Total Cost of Electricity Service: Outlook D
Total Cost of Electricity Service (2016$ Billions) 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 D1 - Wind, Waterpower, Demand Response, Firm Imports $20.7 $21.3 $20.6 $21.7 $21.0 $23.1 $23.3 $23.2 $25.1 D2 - Wind, Waterpower, Demand Response, Firm Imports, Gas $22.5 $22.8 $22.7 $24.7 D3 - Wind, Waterpower, Demand Response, Nuclear, Firm Imports $21.6 $21.9 $22.2 $22.1 $24.0 D4 - Wind, Waterpower, Demand Response, Nuclear, Firm Imports, Gas $22.4 $24.3 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 $25.2 $25.0 $26.5 $26.9 $27.7 $27.9 $23.8 $24.5 $24.2 $24.6 $25.5 $26.8 $27.1 $23.9 $23.6 $25.4 $25.8 $26.6 $27.5 $23.5 $24.4 $26.7 $27.0

54 Average Unit Cost of Electricity Service: Outlook D

55 Average Unit Cost of Electricity Service: Outlook D
Average Unit Cost of Electricity Service (2016$/MWh) 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 Demand: Outlook D (TWh) 144 143 145 147 148 150 152 155 157 D1 - Wind, Waterpower, Demand Response, Firm Imports $144 $149 $147 $142 $154 $153 $150 $160 D2 - Wind, Waterpower, Demand Response, Firm Imports, Gas $157 D3 - Wind, Waterpower, Demand Response, Nuclear, Firm Imports $146 $143 D4 - Wind, Waterpower, Demand Response, Nuclear, Firm Imports, Gas $148 $145 $155 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 159 162 165 169 173 176 181 186 191 197 $151 $141 $138 $140 $139 $137

56 Summary

57 Range of 2035 Total Cost of Electricity Service: Outlooks A-D (2016$)
The total cost of electricity service in 2035 ranges from $18-28 billion (2016$) across the demand outlooks

58 Range of 2035 Total Cost of Electricity Service: Outlooks A-D (2016$)
Total Cost of Electricity Service, 2016$ Billions Low Range High Range Outlook A $17.8 $18.2 Outlook B $19.4 Outlook C $23.1 $23.3 Outlook D $27.1 $27.9

59 Range of 2035 Average Unit Cost of Electricity Service: Outlooks A-D (2016$)
The 2035 average unit cost of electricity service ranges from $ /MWh (2016$) across the demand outlooks

60 Range of 2035 Average Unit Cost of Electricity Service: Outlooks A-D (2016$)
Average Unit Cost of Electricity Service, 2016$/MWh Low Range High Range Outlook A $134 $136 Outlook B $131 Outlook C $130 $132 Outlook D $137 $142


Download ppt "Electricity System Cost Outlook"

Similar presentations


Ads by Google