Classroom Technology Report UTFAB October 2016
Dr. Al Powell Director, Learning Technologies ACNS & CSU Online
2
Report Agenda UTFAB FY 2017 completed projects
Planned updates remaining Request for funding re-allocation Early look at FY 2018 Q&A
3
FY 17 Technology Refreshes - Purpose
Digital/HDMI signals- Update switchers which do not carry HDMI audio signals Projectors– Refresh and move to lower maintenance laser projectors where appropriate Consistent electronic controls– Control technology equipment and software updates Microphone conversion– Move to new frequency, install rechargeable mics in rooms
4
Installations/Refreshes Completed
Video projectors: $84,500 Video switchers: $5,600 Control and HDMI electronics: $4,700 Audio Amp $1,200 Wireless microphone conversion $25,670 First half of project completed; 20 classrooms Classroom Support labor (still in process)
5
Install/Refresh Items Completed
Video projectors: BSB , Eddy , JNSN 222 Video switchers: BHSCI , Eddy Control and HDMI electronics: BHSCI , Eddy Audio Amp: BHSCI 105 Wireless microphone conversion: 20 classrooms
6
Budget FY 2017 Allocated Funding for FY17 $225,400 Equipment installed $121,670 Equipment remaining $35,000 Total equipment $156,760 Labor has not been billed yet, will run below original estimate
7
Installations/Refreshes Remaining
Projectors: $33,000 Eddy 212, Engineering 100, Plant Science C101 Switchers: $1,400 Eddy 212 Control & HDMI electronics: $600 Engineering B101 remodel: $20,000 Upgrade to Smart classroom status Total equipment remaining: $55,000
9
FY 2018 Forecast
10
FY 2018 Classroom Support Request
Projector & lamp replacements: $71,000 (incl. laser) AZ E112, AYLS C , Eddy(19), ED 236, ENG 120, PHYSIO 103, SHEP(4), VIS F101 HDMI switcher replacements: $35,100 Same rooms, minus four in Eddy, plus AYLS C111 Lectern control panels: $5,000 Eddy , SHEP Microphone conversion (part 2): $31,200 A/Z(2), ANSci(4), AYLES 106, GLOV 130, HES 105, Scott Bio(3), JNSN(2), Micro A101, NATR(3), PATH(1), PHYS(2),PLSci C101, TILT 221, VIS F101, Wagar 232, Yates 104 Labor: $35,575 Total: $177,875
11
Discussion?
12
Two More Things…. Help to advance the use of classroom technology at CSU
13
Request to re-allocate funding (1)
FY 17: wireless microphone conversion was funded at $39,000 Actual expense after bid: $25,670 Available funds: $13,330 Goal: provide touch screens in all eight Walnut GA classrooms Walnut is almost equipped for lecture capture Electronic touch screens are needed Cost: $925 per unit = $7400
14
Request to re-allocate funding
How will they be used? Instructor walks in, connects laptop and runs free whiteboard software Touch screen notations show on data projector Student visibility & readability are improved Notations can be saved for students No computer in lectern – less cost & maintenance CSUO, TILT and ACNS provide training
15
Request to re-allocate funding (2)
Classroom Support is creating something most universities don’t have - a Demonstration Classroom used for faculty technology training Clark A68, now being modified by CSS:
16
Request to re-allocate funding (2)
Classroom Support has most of the equipment needed to duplicate a lecture capture room Funding is needed for wireless microphone, touch screen electronic whiteboard, and short throw projector for Smartboard Microphone: $1200 Flat screen: $975 Projector: $1800 Total: $3975
17
Requests to re-allocate funding
Part 1- electronic touch screens: $7,400 Part 2- demonstration classroom: $3,975 Total re-allocation request: $11,375 Return to UTFAB: $1,955