Download presentation
Presentation is loading. Please wait.
Published byJoel Chambers Modified over 6 years ago
1
Single Phase Test at CERN DUNE prototype Requirements (Cryostat and Cryogenics)
David Montanari / Johan Bremer / Jack Fowler / Dimitar Mladenov Apr 9, 2015 Rev. 14
2
Single Phase test at CERN
Outline Intro Cryostat Detector installation Infrastructures Cryogenic systems Outstanding issues Summary Apr 9, 2015 Single Phase test at CERN
3
Single Phase test at CERN
Intro The goal of this prototype is to do a test of a full scale single phase TPCs (before the long-shut down in mid 2018). Each panel is about 2.5 m wide, 6.3 m tall and 0.16 m thick and weights about 600 kg. The general idea is to build a flexible facility that can potentially host other detectors in the future (including a 6.9 m tall TPC, with same other dimensions). Current configuration is CPA-APA-CPA, but there is a proposal to do APA-CPA-APA. TPCs are currently hung from the top plate, but there is a proposal to decouple them from the the top plate and hung the TPC support rails from a bridge across the roof of the cryostat supported on the floor of the building. Current internal dimensions: 7,282 mm (Transv) x 9,522 mm (Parallel) x 8,391 m (Height). Current external dimensions: 10,082 mm (Transv) x 12,322 mm (Parallel) x 11,291 m (Height). These slides present the current requirements for cryostat and cryogenic systems. Apr 9, 2015 Single Phase test at CERN
4
Cryostat Requirements – 1
Parameter Value Type of structure Membrane cryostat Membrane material SS 304/304L, 316/316L or equivalent. Other materials upon approval. Fluid Liquid Argon (LAr) Outside reinforcement (Support structure) Self standing steel enclosure. Might include heaters to prevent steel from freezing. TPC size (Field Cage + Frame) CPA-APA-CPA Configuration (APA-CPA-APA possible) Length: 5,282 mm (Transverse to beam) Width: 7,322 mm (Parallel to beam) Total Height: 6,305 mm Drift distance 2,500 mm Minimum clearance of TPC (Back) 1,200 mm (CPA bar to the tip of the corrugation) * Minimum clearance of TPC (Front) 1,000 mm (CPA bar to the tip of the corrugation) * Minimum clearance of TPC (Sides) Minimum clearance of TPC (Floor) 400 mm (CPA bar to the tip of the corrugation) * Depth of LAr above TPC 300 mm (Over the CPA bar) Minimum depth of LAr inside cryostat 7,491 mm (from the floor) Ullage 900 mm (to match the Far Detector to test TPC supports) Maximum static heat leak 10 W/m2 (Sides/Floor) 15 W/m2 (Roof) Note (*): The TPC clearances are set to allow for installation of TPC from inside the cryostat Apr 9, 2015 Single Phase test at CERN
5
Cryostat Requirements – 2
Parameter Value Vapor barrier Stainless steel plates (part of support structure) Insulation thickness 900 mm (it was 800 mm. Updated to reflect GTT standard dimensions) Secondary barrier GTT design (sandwiched within the insulation). Liquid tight. Membrane thickness (GTT) 1.2 mm (assumed 2 mm to calculate outer structure) Corrugation height 60 mm (to be changed to 70 mm) Minimum inner dimensions cryostat 7,282 mm (Transverse) x 9,522 mm (Parallel) x 8,391 m (H) * (flat plate to flat plate) Operating gas pressure Positive pressure. Nominally 70 mbar (~1 psig) Design Pressure 345 mbarg (~5 psig) Design Temperature 77 K (liquid Nitrogen temperature for flexibility) Leak tightness 1E-6 mbar*l/sec All surfaces in the ullage during operations < 100K Penetrations 1 Side penetration through the membrane at the lowest possible/practical elevation for LAr circulation and purification. 2 Beam windows. See location on drawings. Size TBD. Accessibility after operations Capability to empty the cryostat in 30 days and access it in 60 days after shutdown. Lifetime / Thermal cycles Consistent with LAr program. 20 cool down and total warm ups. Note (*): The dimensions are calculated assuming to be able to insert a 6.6m high TPC inside the cryostat as well. The current one is only 6.0 m high. Apr 9, 2015 Single Phase test at CERN
6
Single Phase test at CERN
EHN1 Bridge Crane Single Phase Test cryostat WA105 cryostat Pit B Apr 9, 2015 Single Phase test at CERN
7
Crane clearance above cryostat
Current hook height above cryostat as modeled 7,609 mm top cap thickness included. It currently leaves 1,320 mm of clearance for rigging and handling of TPC panels). Hook height 9,900 mm above gallery floor Pit B depth 9,000 mm Apr 9, 2015 Single Phase test at CERN
8
Single Phase test at CERN
Plan view (From Ilias) Pit B Bridge Crane WA105 cryostat Possible alternative location Single Phase Test cryostat Apr 9, 2015 Single Phase test at CERN
9
Side view of cryostat w beam orientation
Top cap Liquid level Beam ~6° 11,291 Detector panels 5,000 mm Membrane Insulation Outer Structure Apr 9, 2015 Single Phase test at CERN
10
Top view of cryostat w beam orientation
Membrane Primary Orientation ~10° 10,082 10° Insulation Outer structure 12,322 Apr 9, 2015 Single Phase test at CERN
11
End view of cryostat w beam orientation
Beam entrance points on the upstream side of the cryostat: Primary location: at the center of the cryostat (North-South direction) and ~5,000 mm from the floor. Secondary location (if available): same height as the primary beam position, but with 1,500 mm offset to the North. 11,291 ~1,500 mm 5,000 mm North South Apr 9, 2015 Single Phase test at CERN
12
Cryostat Top Requirements – 1
Parameter Value Configuration Metal plate reinforced with profiles/beams anchored to the membrane cryostat support structure with several penetrations of different size including two hatches and a manhole. The hatches shall be designed to be removable. If welded, provisions shall be made to allow for removal and re-welding six (6) times. Dimensions To match the cryostat: 10,082 mm x 12,322 mm x 1,500 mm (thick) Plate/Trusses non-wet material Steel if room temperature. SS 304/304L or equivalent if at cryogenic temperature. Wet material SS 304/304L, 316/316L or equivalent. Other materials upon approval. Fluid Liquid Argon (LAr) Design Pressure 345 mbar (~5.0 psig) Design Temperature 77 K (liquid Nitrogen temperature for flexibility) Maximum allowable roof deflection (*) 0.003 differential between APA and CPA Pressure stability inside the tank No requirements, as long as the roof deflection is within le limit. Same for atmospheric pressure variations. Maximum static heat leak 15 W/m^2 (Greater than sides/bottom to allow for the penetrations) Max vibration No problem < 1 kHz Worst is 100 kHz All surfaces in the ullage during operations ≤ 100K Note (*): This may require decoupling the TPC support from the top. We are now looking at an external bridge over the top plate supported on the floor of the building. Apr 9, 2015 Single Phase test at CERN
13
Cryostat Top Requirements – 2
Parameter Value Hatch opening for TPC installation (*) 3,550 mm x 2,000 mm (in the current installation model) Secondary open for personnel 2,000 mm x 1,000 mm (in the current installation model) Grounding plate 1.6 mm thick copper sheet brazed to the bottom of the top plate. Lifting fixtures Appropriate for positioning the top and the different parts that constitute it. Cold penetrations Minimum 4. Location and design TBD. Lifetime / Thermal cycles Consistent with the LAr program TBD. All surfaces in the ullage during operations < 100K Additional design loads Top self-weight (including stiffening beams, membrane, insulation, etc.) TPC (5,400 Kg total) TPC anchors (TBD) Live load (488 kg/m^2) Electronics racks (400 kg in the vicinity of the feedthroughs) Services (150 kg on every feed through) Seismic load CERN requirement TPC anchors Capacity: 3,000 kg each anchor. Number and location TBD (Minimum 6). 1.6 mm thick copper sheet brazed to the bottom of the top plate (LBN proposed design – TO BE VERIFIED). Note (*): This may change depending on the TPC configuration. APA-CPA-APA requires a larger opening. Apr 9, 2015 Single Phase test at CERN
14
Cryostat Top Requirements – 3
Parameter Value Penetrations 1 LAr In 1 Purge GAr In 1 Vent GAr 2 Pressure Safety Valves 1 Vacuum Safety Valve 1 GAr boil off to condenser 1-2 Liquid level sensors 1-2? Instrumentation? Purity Monitors? Light pulsers?? 1 Temperature sensors feedthroughs ? 1 LAr for cool down 1 GAr for cool down TPC signal 12” CF Cold 3 TPC feed through each row (250mm CF) regardless of TPC configuration 1 Photon Detector for APA (10” CF) Cold Calibration ?? Lifetime Consistent with LAr program Thermal cycles 20 cool down and total warm-ups? Note: all feedthroughs need a purge port to ensure that the top flange is warm and no back diffusion brings contaminants back into the cryostat. The design is connected to the installation procedure. Since the design has to allow for CAC and ACA configurations, each row of TPCs will have the same ports. Apr 9, 2015 Single Phase test at CERN
15
Preliminary thinking on top design
Large hatch Large hatch Penetrations Reinforcements Beam Apr 9, 2015 Single Phase test at CERN
16
Detector Installation Plan
The current model is to install the detector panels by passing TPC components through a large hatch (dimensions depend on the TPC configuration) in the top cap of the cryostat and connect them to the bridge supported on the floor. The current plans for the LBNF Far Detector also feature an external support for the TPCs. Additional footprint: are there space limitations in the building? Needs to support both different detector configurations. Currently the plan is for the mechanical supports and feedthroughs to be the same for each row of planes. Apr 9, 2015 Single Phase test at CERN
17
TPC lowered inside Cryostat
Apr 9, 2015 Single Phase test at CERN
18
Cryostat Infrastructures Requirements
Parameter Value Current cryostat footprint (estimate). Need to estimate the TPC support bridge also. 12,322 mm (L) x 10,082 mm (W) Work area around the top of the cryostat (platform type) 2.0 m around the whole perimeter Lay down space TBD Clean Room space Class 10,000 where TPC components are assembled and installed. Size depends on installation technique. Crane coverage Over the cryostat and the lay down space Crane capacity 30-40 ton (needs feedback from the design of the top plate). Could be the current overhead crane, but how can we integrate it inside the Clean Room ?? Could use a floor mounted gantry ?? Minimum hook height above the cryostat for TPC installation 4.5 m + lifting fixture (TPCs are rotated prior to insertion) Lighting UV filtered lights are needed in all work areas where the photon detectors are exposed (if any). Ventilation Appropriate additional ventilation when working inside the cryostat. Scaffolding Up to 7.0 m in height inside the cryostat. Power outlets For portable tools and welding machines inside the cryostat Note: some of the requirements need input from the design of the top plate, the outer structure and the beam window. They also need to be integrated with the installation process. Apr 9, 2015 Single Phase test at CERN
19
Current electrical requirements (Preliminary)
The cryostat membrane and any supporting structure need to be isolated from any building metal or building rebar with a DC impedance greater than 300 kOhm. The cryostat, or “detector” ground, shall be separated from the “building” ground. A safety ground network consisting of saturated inductors to be used between detector ground and building ground. Apr 9, 2015 Single Phase test at CERN
20
Electronics, Computing, Power
Electronics Racks on top of the cryostat. Racks for computers. Info on Cables/Racks is being collected and should be available by end of April as requested by Guillaume Gros. Clean power with separate grounding for detector. How much ?? Normal power for all the rest. How much ?? Control room space for DAQ and detector monitoring. Apr 9, 2015 Single Phase test at CERN
21
Cryogenic System Requirements
Parameter Value Location Preferably not in front of the cryostat (on the beam line) LAr purity in cryostat 10 ms electron lifetime (30 ppt O2 equivalent) GAr Piston purge rate of rise 1.2 m/hr Membrane cool-down rate From manufacturer TPCs cool-down rate < 40 K/hr < 10K/m (vertically) Mechanical load on TPC The LAr or the gas jet pressure shall not apply a mechanical load to the TPC greater than 200 Pascal. Nominal LAr purification flow rate (filling/ops) 5.5 day/volume change (3.95 m^3/hr = 66 l/m) All surfaces in the ullage during operations < 100K GAr purge within insulation 1 volume change/day of the open space between insulation panels Cooling power Cool down: TBD Operations: 3.4 kW + TBD: Electronics heat load ?? Heat leak of cryo-piping ?? From cryo-piping design. Lifetime of the cryogenic system Consistent with the LAr program TBD Control system Integrated with the other neutrino projects (as much as possible) Apr 9, 2015 Single Phase test at CERN
22
Cryogenic Systems Requirements (Preliminary)
To the extend possible, we want to design a portable system that could be fabricated and tested in one place and installed at destination in another, with quick connections to/from cryostat. External Cryogenics can be located anywhere, will probably be outside of the building. Internal Cryogenics inside the cryostat. Proximity Cryogenics several locations: Condenser (and maybe LN2 dewar/phase separator) will have to be located above the roof of the cryostat or nearby, but higher than the roof of the cryostat. LAr circulation pump at the back of the cryostat, on the floor, as low as possible. Penetrations through the top of the cryostat, in the back region. GAr purge in the insulation two in and two out at a certain elevation with piping going to the rest of the system. The remaining can be located where space permits, preferably in the vicinity of the cryostat. LAr/LN2, GAr/GN2 piping will connect Proximity/External/Internal cryogenics. The design will inform on size and specific location. Apr 9, 2015 Single Phase test at CERN
23
Single Phase test at CERN
Outstanding Issues Detector configuration: CPA-APA-CPA or APA-CPA-APA ?? External trigger counters: do we need them ?? How many and where ?? How much space is required for installation (including cables to racks) and service ?? Photon detector: how many and where ?? The drift distance is currently 2.5 m. Is it confirmed ?? Design of TPC mechanical support: from bridge outside of the cryostat, supported on the floor of the building. May add requirements to the infrastructures (floor space, …). Size and type (cold/warm) of penetrations through the roof required for TPC operations and monitoring: calibrations? photo detection? purity monitors? Others? Instrumentation that need to go inside the cryostat (purity monitors, etc.). Confirmation of the weight of the TPC (5,400 kg total ??). If the detector configuration changes, this will change. Location and design of the cold penetrations. Location of TPC anchors (if preferred location exists). Grounding and isolation requirements. Electronics, computing and power. Apr 9, 2015 Single Phase test at CERN
24
Single Phase test at CERN
Summary Current internal dimensions: 7,282 mm (Transv) x 9,522 mm (Parallel) x 8,391 m (Height). Current external dimensions are: 10,082 mm (Transv) x 12,322 mm (Parallel) x 11,291 mm (Height). The cryostat is ~10 degrees rotated with respect to the beam, currently at the end of Pit B. Preliminary requirements for cryostat, cryogenics and infrastructure outlined. Several outstanding issues that may change dimensions and requirements. Need to be addressed asap. Apr 9, 2015 Single Phase test at CERN
25
Backup
26
Single Phase test at CERN
Outer Structure Parameter Value Configuration Self standing steel enclosure. Might include embedded heaters to prevent steel from freezing (Floor + Sides). Vapor barrier Stainless steel plates connected to the I-beams of the support structure. External dimensions 10,082 mm (Transverse) x 12,322 mm (Parallel) x 11,291 m (H) Design Pressure 345 mbarg (~5 psig) LAr + GAr load 949 ton (Bottom) 547 ton (Long side) 418 ton (Short side) Uplift force (top) - 239 ton (GAr) Additional loads Loads transferred from the top plate down to the support structure Grading at the top (TBD) External loads of counters (if any) Design code CERN regulation Seismic load Penetrations 1 side penetration from the inner membrane at the lowest possible/practical elevation for LAr circulation and purification. 2 Beam windows. See location on drawings. Dimensions TBD. 4 side penetrations for GAr purge in insulation (2 In, 2 Out). Location and size TBD. Maximum deflection towards outside TBD Apr 9, 2015 Single Phase test at CERN
27
Detector Installation Plan – 2
The second installation plan is to build the detector directly in the cryostat without the top cap using temporary supports. Once complete, attach to the underside of the top cap. Then lower the complete assembly. (See backup slides option 2 for some older conceptual slides). Potential problems with cryogenic installation. Apr 9, 2015 Single Phase test at CERN
28
Concept 1 Needs updating with new TPC configuration and Cryostat
Apr 9, 2015 Single Phase test at CERN
29
Manipulating the TPC components
Apr 9, 2015 Single Phase test at CERN
30
Manipulating the TPC components II
Apr 9, 2015 Single Phase test at CERN
31
Manipulating the TPC components III
Apr 9, 2015 Single Phase test at CERN
32
Concept 2 Needs updating with new TPC configuration and Cryostat
Apr 9, 2015 Single Phase test at CERN
33
Installation hardware with CPA support rail
Support rail length is shorter than top cap width. This rail will be fixed and supported from the underside of the top cap later. The rail is positioned close to the edge of the cryostat for allow personnel access to the hangers from the top edge of the containment vessel. Assume the top edge of cryostat can support load and that people can work there. Apr 9, 2015 Single Phase test at CERN
34
Moving CPA over Cryostat and rotation
Assume that there are 2 lifting devices from the crane bridge and they can be operated at the same time to rotate the TPC planes. The planes would be lifted on edge horizontally over the cryostat. One lifting device would be lowered while the other is stationary to perform the rotation of the object. Apr 9, 2015 Single Phase test at CERN
35
Positioning and attachment of CPAs to support rail
Once rotated the lower cable would be disconnected from the plane and the upper connection would be used to move the plane under the support rail. The plane would be connected to the support rail by personnel working from the top of the containment vessel. The second plane would be moved in and connected to complete the 1st CPA plane assembly. Apr 9, 2015 Single Phase test at CERN
36
Translate CPA plane assembly to opposite side of Cryostat
Once completed, we would translate the 1st CPA plane assembly to the opposite side of the cryostat. This could be done with rollers on the cryostat or using the overhead crane. Apr 9, 2015 Single Phase test at CERN
37
Install APA planes and translate
Install the APA rail and the two APA planes in a similar method. Then translate the APA planes to opposite end of the cryostat with the other CPA plane. Apr 9, 2015 Single Phase test at CERN
38
Install the 2nd set of CPA planes
Apr 9, 2015 Single Phase test at CERN
39
Position the 3 TPC planes
After positioning the 3 planes to their final positions with respect to the cryostat walls and each other, install the end field cages. These could be supported from the APA and CPA rails. How to deploy the upper field cages? When and how to cable the APA planes? The lower field cages could stored on the floor of the cryostat and connected at this point. Apr 9, 2015 Single Phase test at CERN
40
Single Phase test at CERN
Install Top Cap Bring the top cap over the 3 TPC planes and lower to the support rails. Connect the ends of the support rails to the hangers on the underside of the top cap. The HV probes could be installed through the top cap at this point into their receptacles on the CPAs. The APA cables could be “fished” through the service feed thru for connection later. Remove the installation hardware from the ends of the support rails. Lower the top cap and the TPC down in the cryostat. Apr 9, 2015 Single Phase test at CERN
41
Plan view (Cryostat rotated 10 degrees)
Bridge Crane WA105 cryostat Single Phase Test cryostat Pit B Note: the angle could change a little bit. Apr 9, 2015 Single Phase test at CERN
42
Single Phase test at CERN
Current assumptions Dimensions from EHN1 drawing: Hook height above floor of pit B: 18,900 mm. Hook clearance over top cap: 7,609 mm. Dimensions from detector design: Detector height: 6,289 mm. Clearance for detector installation (between height of detector and hook over cryostat): 1,320 mm. How much of this is needed for rigging and handling? Beam direction from interaction between Cheng-Ju and Ilias. Apr 9, 2015 Single Phase test at CERN
43
Example: Layout of LBNE 35 ton racks
Trig_Scint TPC_PD Purity Monitor Calibration DAQ_1 DAQ_2 RPS 1 Empty 2 Cable Dressing Ethernet Switch-2 NIM Bin Camera System Nova Timing Master 3 CCU4 Wire Manager 4 ANL Calibration Module Ethernet Switch-1 5 6 7 CCU3 Fan PC-1 8 8 x SSP 9 PM Multiplexer PC-2 10 11 Penn Trig board PC-3 12 SurgeX 13 14 Wiener MPOD-Wire/FC PC IU Calibration System PC-4 15 16 PC-5 17 Nova Timing Slave 18 PC-6 19 20 21 PC-7 22 23 PC-8 24 Wiener MPOD-LV 25 PC-9 26 27 28 ATCA Shelves 29 30 CCU2 31 Fan/Plenum 32 33 34 CCU1 Crate Power Supply 35 36 37 Impedance Monitor 38 AC Switch Box 39 40 41 42 Note: This is just an example from a smaller detector. Racks currently on top of Cryostat Apr 9, 2015 Single Phase test at CERN
44
Example: Current LBNF Rack Equipment
Preliminary List of Detector Electronics Rack types and contents-Per Detector # of racks Location Rack Name Rack Components Space (U) Quantity Power (VA) Power Tot (VA) Notes FD SiPM system HV Power Supply TBD 2 ps/port Caen 5740 ch32, 4 APAs Shaper Power Supply backplane 16 channels Splitter SiPM FE amplifier Computer Cold Electronics Wiener MPOD 80 8.1 648 2560ch/apa, 10mW/ch. (200W) (4MB/APA) (20APA) 40W/APA=65W*20=1300 1.5V/.6A,2.1V/1A,2.8V/1A,3.6V/.5A,5V/.1A Drift HV Power Supply 4 230 920 -115kV/1mA, Heinzinger PNChp neg/M 230V/1A (1-ph), 400V/1A (3-ph) other avail. TPC Wire Bias 20 7 140 Vg:-1kV,Vu:-1kV,Vx:+1.5kV all 2mA (20APA) Field Cage Bias 1 2 -1kV/2mA 1710 Computers 15 Rack Protection Smoke Sensor assume 15 racks per detector Rack Protection Mon 120V/<1A PDU (Power Dist. Units) Power requirement based on service. Slow Controls Intl'k Switch Hot Spares Rack 3 2400 43200 120V/20A service Total (kVA) 43.20 L. Bagby - FNAL Note: This is just an example from a much larger detector. Apr 9, 2015 Single Phase test at CERN
45
Example: Current LBNF Cavern Equipment
Preliminary List of Detector 10 kt Cavern Equipment Equip. Name-BLDG Quantity Power Unit Power (Tot) Generator Backup Power Source Notes Lighting-Cavern 1 35 kVA yes Lighting-Drifts 10 kW HVAC-Chiller 2 149.2 298.4 200HP HVAC-Circulating Pumps 4 22.38 89.52 30HP HVAC-Fan Coil Units 30 1.492 44.76 2HP HVAC-Air handler supply fan 14.92 20HP HVAC-Air handler exhaust fan Sump Pumps 6 3.73 5HP Vent Fans 8.952 Welding Outlets 41.57 166.28 no (480V/50A)..Millers David Matinary Monorail crane-10 ton-hoist(15)+trolly(1) 11.936 11.94 (work cell hoist) 16HP*746 Fire 1.5 Paul-SURF VESDA sniffer HSSD system in cryostat Halon Nitrogen Booster Compressors 111.9 447.6 150 HP each Liquid Argon Pumps 5.2 20.8 480V Heater Cables 12.6 25.2 Purification Skid (Blowers) 28 46 Purification Skid (Cooling) 21.1 21 Purification Skid (Heating) 63.6 64 System Controls 3.0 3 SLAC RCE System Test Area 1.8 7.2 3 racks + 1 table + 1 bench 15A service Temporary lighting in cryostat 1.3 1 W/ft^2 Temporary ventilation in cryostat: blower 0.746 0.75 3-ton, 1HP Temporary ventilation in cryostat: compressor 3.9 General air monitoring in cryostat TBD Hoist near hatch-3 ton-hoist(2HP)+trolly(.5HP) 1.865 1.87 (hoist in cryostat) 2.5HP*746 Power for potential battery charging station/powered carts HEPA filter blower units 0.336 3.36 similar to uboone clean room Total Power (kVA) L. Bagby - FNAL Note: This is just an example from a much larger detector. Apr 9, 2015 Single Phase test at CERN
46
Cryostat sizing Length
APA width 2300 mm (x 3). 12.5 mm of edge boards on each side of the center joint (x 4). 50 mm from the SS APA (active area boundary) frame to field cage (x 2). 76.2 mm diameter of CPA tube (x 2). 1,000 mm clearance to membrane for access and egress. 1,200 mm clearance for piping and instrumentation. 60 mm depth of corrugations (x 2). 9,522 mm total length of cryostat. 100 cm 100 cm Mar 20, 2015 Single Phase test at CERN Requirements
47
Single Phase test at CERN Requirements
Cryostat sizing Width 76.2 mm - APA thickness 3”. 4.76 mm height of wire layers on each side (x 2). 2,500 mm drift distance (x 2). 38.1 mm – Half the diameter of 3” CPA frame (x 2). 1,000 mm to membrane for access and egress (x 2). 60 mm depth of corrugations (x 2). 6,256.5 mm total width of cryostat. Mar 20, 2015 Single Phase test at CERN Requirements
48
Cryostat sizing Height for 6.6 m APA
6,638.7 mm - APA side tube length. 76.2 mm - Distance from top of the cross tube down to the beginning of active volume. 76.2 mm – Diameter of CPA tubing above active volume. 300 mm of liquid above CPA tube. 16 mm boards at bottom of frame. 76.2 mm – Diameter of CPA tubing below APA bottom boards. 300 mm of liquid below CPA tube. 100 mm of space reserved for piping at bottom of cryostat. 7,491 mm is liquid level height. 900 mm ullage based on far detector design. 60 mm depth of corrugations (x 2) Total height from floor to underside of top cap = 8,391 mm. Total inner volume 582 m3. Liquid Volume APA active volume APA CPA Bottom boards of APA Space for piping Mar 20, 2015 Single Phase test at CERN Requirements Floor of Cryostat
49
Cryostat Height sizing (6.0 m APA)
6,060.1 mm - APA side tube length 76.2 mm - Distance from top of the cross tube down to the beginning of active volume. 76.2 mm – Diameter of CPA tubing above active volume. 300 mm of liquid above CPA tube. 16 mm boards at bottom of frame. 76.2 mm – Diameter of CPA tubing below APA bottom boards. 300 mm of liquid below CPA tube. 100 mm of space reserved for piping at bottom of cryostat. 6,912 mm is liquid level height. 900 mm ullage based on far detector design. 60 mm depth of corrugations (x 2) Total height from floor to underside of top cap = 7,812 mm. Total inner volume 542 m3. Liquid Volume APA active volume APA CPA Bottom boards of APA Space for piping Mar 20, 2015 Single Phase test at CERN Requirements Floor of Cryostat
50
Cryogenic Systems Strategy
We, as a community, want to develop a common strategy to address LAr/LN2 cryogenic needs for: SBN-ND/FD (short term). Single/Double Phase test at CERN (short term). LBN (long term) and other future generation detectors to come. We want to minimize the effort and design and fabricate a standard system that could be “enlarged” and adapted for future short/mid/long term needs. To the extend possible, we want to design a portable system that could be fabricated and tested in one place and installed at destination in another, with quick connections to/from cryostat. We want to test all features that might be relevant and of interest for present and future detectors: external LAr pumps, cold roof (< 100 K), etc. and the possibility to turn them on/off to compare. Three parts are identified (for both LAr and LN2 systems): Proximity Cryogenics External Cryogenics Internal Cryogenics Apr 9, 2015 Single Phase test at CERN
51
PFD of LAr system (Preliminary)
Apr 9, 2015 Single Phase test at CERN
52
PFD of LN2 system (Preliminary)
Apr 9, 2015 Single Phase test at CERN
53
Cryogenic Systems Capabilities
To clean the cryostat GAr purging and venting GAr recirculation and purification. To cool down the cryostat and fill it with LAr. To continuously purify the LAr (filling and operations). To re-condense and purify the boil off gas. To handle the LAr/GAr and LN2/GN2 flows during all phases. To maintain the top of the cryostat at ≤ 100 K. To monitor and control internal and external pressure: Pressure Control / Vacuum Protection PSV, VSV, Auto/Manual venting. Make-up GAr. To handle the GAr purge inside the insulation. Instrumentation and diagnostics: T and P sensors, flow meters, liquid level sensors, etc., analytical instruments to measure the contamination, in-line Purity Monitors (??), etc. To sample GAr from the ullage and measure the concentration of contaminants. Control system. Flexibility: new features may be tested (cold roof, LAr external pump). To the extent possible, it is desired to have a flexible system where we can turn on/off the various features for comparison. Apr 9, 2015 Single Phase test at CERN
54
Cryogenic systems outstanding issues
Selection of the type of LAr filtration system (Mol Sieve/Copper VS Oxysorb/Hydrosorb) Portability/Scalability: studies on portability and how to design a portable/scalable system that can serve present and future generation detectors of any size. Studies on how to keep all surfaces at a Temperature lower than 100 K. LAr Pump (Outside): Need to see how to isolate the pump electrically and mechanically from the TPC. Issues with electronic noise and microphonics. Check grounding scheme. Apr 9, 2015 Single Phase test at CERN
55
Current cryostat schedule (DRAFT)
Preliminary Design: Jan-Jun 2015. Design Review: Jul-Sep 2015. Final Design/Procurement: Oct 2015-Sep 2016. Construction: Oct 2016-Jul 2017. Apr 9, 2015 Single Phase test at CERN
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.