5/17/2017
2
Work Party Status Task Summary: Repair torch Fabricate Yaw probe
Fabricate main engine Ignitors Install Servo power supply in housing Fin sample layup Avionics system test Mix fuel
3
SE: CG Model Dev. 4/29-30 4/29-30 SE: Composite Layup GSE: Torch Rebuild 4/29-30 PL: Probe Fab PL: Probe Design PL: Payload Mass Est. SE: Fin Sizing SE: Fin Fab EVERYONE: Rocket Assembly PL: Payload Procedure Dev. SE: Dynamic Flt Characteristics PL: Pduce Selection PL: Probe Elec Design & Fab PL: Payload Checkout TBD GSE: Refurbish & checkout Ground Support Equipment GSE: Rocket Install Procedure Dev GSE: Launch Procedure Review EVERYONE: Launch Rehearsal AV/GSE: Integrate Servo Pwr Supply Prop/AV: Checkout Servo PWR supply with Servo Prop: Upgrade Servo Valve Prop: Install new servo Prop: Leak Check System Prop: Fueling Procedure Dev. AV: TLM System Familiarization AV: TLM System Procedure Dev. Prop: Finalize Solid Ignitor design 4/29-30 Prop: Fab Liquid Eng. Ignitors PM: Complete COA Application PM: Establish Launch Date PM: Organize Equipment List PM: Parent Meeting PM: Manage Travel & Launch Logistics ACTIONS: Order Oxidizer (LOX), 50 PSI Relief Valve Phone Fire Dept Notification PM: Letter to Mansfield Mayor Prop: Prepare Fuel
4
Action Items (Rev 5/17/2017) Page 1 of 2 No. Status Description
Due Date POC 1 OPEN Probe transducer selection (part number and supplier) 5/10 Ved 2 Probe data acquisition system selection 3 Payload battery sizing Gregory 4 Payload mass estimate and CG location 5/17 5 CLOSED Fin Sizing Ben 6 Prepare parent meeting briefing for review PM / Ann 7 Order ground anchors Mr. Charles 8 Order helium valve servo 9 TLM system Familiarization Stevie 10 Draft Procedure Review 5/17 (class next week) ALL / Mr. Charles 11 Draft answers to FAA COA question PM Team / Ann 12 Draft Equipment list ALL 13 Aerojet Grant Request Submission 5/5 Mr Saxby 14 Finalize CG Model Maheck / Kevin 15 Finalize Solid motor ignitor 5/24? Mr. Charles 16 Identify owner equipment list PM Team? 17 Put Equipment list on website Mr. Saxby 18 Order pressure transducers 5/18 Mr. Masse 20 Order payload avionics 21 Schedule parent meeting Carolyn 22 Place Action Item file where we can access each week 23 Get main engine ignitor transformer Charles 24 Purchase more carbon fiber 5/31/17 B.O.P. 25 Print 10 copies of procedures used for Mansfield launch 26 Coordinate Mansfield fire dept. support for launch Before Parent Meeting PM 27 Trip to Aerojet Sometime
5
Action Items (Rev 5/17/2017) DRAFT
Page 1 of 1 No. Status Description Due Date POC 1 OPEN Probe transducer selection (part number and supplier) 2 Probe data acquisition system selection 3 Payload battery sizing 4 Payload mass estimate and CG location 5 Fin Sizing 6 Prepare parent meeting briefing for review PM / Ann 7 Order ground anchors 8 Order helium valve servo 9 TLM system Familiarization 10 Draft Procedure Review 5/17 (class next week) ALL / Charles 11 Draft answers to FAA COA question PM Team / Ann 12 Draft Equipment list 5/10 ALL 13 CLOSED Aerojet Grant Request Submission 5/5 Mr Saxby 14 Finalize CG Model ? / Kevin 15 Finalize Solid motor ignitor / Charles 16 Identify owner equipment list 17 Order pressure transducers 18 Order payload avionics 20 Schedule parent meeting 21 Place Action Item file where we can access each week 22 Get main engine ignitor transformer Charles 23 24 25
6
Tasks Today SRM ignitors fab Mix Fuel (water / alcohol)
Check fin sample for proper thickness (0.125”) Define Max Fin Size Parent coordination meeting brief Probe mounting structure profile Document battery requirements for Payload Avionics checkout Integrated Avionics / Ignitor checkout? Launch team assignments Launch control box checkout Open Action Items from last week
7
Launch Assignments (1 of 2)
POC CONTACT INFO LAUNCH DIRECTOR Primary Backup RANGE SAFETY RECOVERY TEAM LEAD PAYLOAD OPERATIONS LEAD TELEMETRY / AVIONICS LEAD GROUND SUPPORT EQUIP LEAD ROCKET INSTALLATION LEAD SRM LOADING MAIN ENGINE IGNITOR
8
Launch Assignments (2 of 2)
POC CONTACT INFO FUEL LOADING LEAD Primary Backup GHE / LOX LOADING LAUNCH CONSOLE Main Engine Observer PHOTOGRAPHY SPECTATOR COORDINATION COA COORDINATOR AIRCRAFT OBSERVERS (4) Primary (4) Backup (2) ROAD TRAFFIC OBSERVER (2) Primary (2) Backup (1)
9
Fuel Properties
10
P-reg (REG1) Set Point
11
MANSFIELD LAUNCH OPERATIONS REFERENCE BOOK
LAST YEARS LAUNCH PROCEDURE BOOK Rev: Org Date: 8/11/2016
12
Launch Tower Setup
13
Launch Rail Setup Notes:
Reference azimuth orientation on next slide Use tool to spread rail adjacent to fastener holes during tightening of fasteners
14
Orientation North 50 ft radius keep out zone
400 lbs nominal pull required Track Side Tower Base 50 ft radius keep out zone North
15
Command System
16
Prop Valve Power supply
Launch Control System To GHe Valve To SRM #1 & #2 To Ignitor Valve To Prop Valve Ignition Transformer Gas Solenoid Valves Launch Control Box Propellant valve (open/close, on/off) GHe valve (open/close, on/off SRM ignition SRM shunt Igniter (on/off) Gas (on/off) Launch Pad Box 400 FEET Pad Control Box Prop Valve Power supply GHe Valve Power Supply 120 VAC Generator SRM Power Supply 120 VAC Generator
20
Launch Procedures
21
Launch Procedures Rocket Installation on Rail Procedure
Rocket Checkout & Fuel / SRM Loading Procedure LOX Loading Procedure Launch Ready Procedure Launch Script
22
Rocket Install On Rail Configuration
Ladder Dewer Table 400ft away from Launch Rail
23
Rocket Installation on Rail Procedure
Verify Shunt Recovery Shunt Plug Installed Verify TLM computer operational Verify bottom 5 feet of aluminum guide rail fasteners are remover from one side of rail Verify SRM carriage is installed on launch rail Place rocket in horizontal position Power up TLM system and confirm operation Install nose cone Gently place rocket on rail Install guide rail fasteners Verify TLM system status Start Generator – for ignitor checkout Set gas flow on Main Engine ignitor and install in engine
24
Launch Procedures Rocket Installation on Rail Procedure
Rocket Checkout & Fuel / SRM Loading Procedure LOX Loading Procedure Launch Ready Procedure Launch Script
25
Rocket Checkout & Fuel / SRM Loading Config.
Ladder Dewer Tower Base Table 400ft away from Launch Rail
26
Rocket Checkout & Fuel / SRM Loading Procedure
Verify Generator ON (needed for prop vale actuation & ignitor setup) Verify fuel bucket bracket installed on launch rail – (support for GHe line) Open propellant loading access door Install GHe valve motor power connector Verify GHe motor direction Hook up GHe line to rocket Open (MV1) LOX tank pressurization Isolation Valve Purge system (25 PSI) through injector for ~ 1 min (manual operation of prop valves) Shut off GHe supply Close Prop Valve (manual operation) Verify prop valve direction is correct (electrical operation of prop valve) and mark on plume shield Remove fuel fill port plugs Put thread sealant on fuel port plugs Load Fuel Load SRMs (verify both SRM shunts installed prior to handling ignitors)
27
Launch Procedures Rocket Installation on Rail Procedure
Rocket Checkout & Fuel / SRM Loading Procedure LOX Loading Procedure Launch Ready Procedure Launch Script
28
LOX Loading Configuration
Ladder Dewer Tower Base Control Box Table 400ft away from Launch Rail MOVE CONTROL BOX
30
LOX Loading Procedure Move Launch Control Box to Launch Control Site
Verify Ignitor Arc operation (on for 1 sec & verify by listening) Contact ATC for launch clearance (45 min to launch) Verify LOX tank cooling jacket installed Install transfill line Close (MV1) LOX Tank Pressurization Isolation Valve Install LOX overflow tube Begin LOX flow Approximate 30 min chill-in required
31
Launch Procedures Rocket Installation on Rail Procedure
Rocket Checkout & Fuel / SRM Loading Procedure LOX Loading Procedure Launch Ready Procedure Launch Script
32
Launch Ready Procedure
Confirm Participants are in proper location (all together, at assigned location) Confirm Avionics – Go Confirm that Range is GO - (Aircraft & Traffic Spotters) Confirm Launch Control Box SRM Shunt INSTALLED Disconnect GHe fill line Disconnect LOX transfill line Open (MV1) LOX tank pressurization Isolation Valve (inside access door) Install propellant loading Access Door Remove LOX cooling jacket Verify GHe Valve Electrical Connector installed Verify Prop Valve power supply - ON & Set to correct voltage Move LOX Dewer START cameras Close LOX Vent Remove Recovery Shunt Plug Remove SRM Shunt at Launch Rail box Move to control area
33
Launch Procedures Rocket Installation on Rail Procedure
Rocket Checkout & Fuel / SRM Loading Procedure LOX Loading Procedure Launch Ready Procedure Launch Script
34
Launch Script Confirm Range - GO (Traffic & Aircraft Spotters)
Move to Launch Control Area Following actions Must occur in rapid succession or LOX tank pressure will increase to point that relief valve will start venting LOX tank Confirm Range - GO (Traffic & Aircraft Spotters) Confirm Avionics - GO GHE Pressurization Valve - OPEN Ignitor - ON Ignitor Gas Flow - ON Verify Avionics - Go Prop Valve Open – Ignition Verify (observation/sound) - Go SRM Shunt Removal Fire SRM
35
Contingency Procedures
36
Example “Recovery” tasks that get inserted into specific Procedures
Preflight Checkout Procedure - Recovery System: Need to verify Avionics is working correctly (battery charge level, …) Main chute packing procedure Verify squib resistance What position is rocket in when performing above Disarm after hang-fire, no recycle (no future flight planned): PPE - Safety glasses, gloves, hearing protection Obtain approval from Safety that its "safe to approach the rocket and conduct the Recovery pyro safing operation Install the pyro shunt – never get in line of sight of pilot chute chamber {do we remove the rocket from the stand at this point?} Verify Recovery pyro shut plug installed Remove nosecone Unplug pyro connector Remove recover section from rocket Place recover section containing pyro charges in storage container Disarm after nominal flight (intact rocket, main canopy deployed): PPE - Safety glasses, gloves, hearing protection, three people recover team Secure main chute, have one person continue to hold chute so does not inflate due to wind Photo documentation Approach / reposition rocket so pilot chute chamber is facing perpendicular to line of sight Install Recovery shunt plug Remove payload section from pilot chute section Disconnect parachute bridle from pilot chute section Provide to designate mentor to verify status of pyro charges Disarm after off-nominal flight (Main canopy/pilot chute did NOT deploy): PPE - Safety glasses with side protection, gloves for all personal performing recovery operation. Safety glasses with side protection for all observers within 25ft. Extract remaining recover components - we must recover the cable cutter which should remain intact / verify status of pyro charges
37
Flight Feed System
38
Flight Feed System GHe Fuel Tank LOX Tank P1 Vent SV3 Relief Valve BV2
REG1 SV1 Relief Valve (600 psid) RV1 MV1 Fill Port Vent Fill BV1 BV2 SV4 SV5 SV3 SV2 CV1 CV2 Fuel Tank LOX Tank
39
LOX Load (Rev Org 6/1) LOX Vent Tube LOX DEWAR
40
Propellant Data
41
Fuel Properties
42
LOX Properties Table 1: Liquid Oxygen Physical and Chemical Properties
Molecular Formula O2 Molecular Weight Boiling 1 atm –297.4°F (–183.0°C) Freezing 1 atm –361.9°F (–218.8°C) Critical Temperature –181.8°F (–118.4°C) Critical Pressure psia (49.6 atm) Density, BP, 1 atm lb/scf (1141 kg/m3) Density, 68°F (20°C), 1 atm lb/scf (1.33 kg/m3) Specific Gravity, Gas 68°F (20°C), 1 atm 1.11 Specific Gravity, Liquid 68°F (20°C), 1 atm 1.14 Specific 68°F (20°C), 1 atm scf/lb (0.754 m3/Kg) Latent Heat of Vaporization at BP 91.7 Btu/lb (213 Kj/Kg) Expansion Ratio, Liquid to Gas, BP to 68°F (20°C) 1 to 860 Solubility in 77°F (25°C), 1 atm 3.16% by volume
43
LOX Info
44
Injector Data
45
P-reg (REG1) Set Point P-reg = = 395 psig
46
LOX Injector Water Flow Test Data
47
LOX Injector Water Flow Test Data
48
Fuel Injector Water Flow Test Data
49
Fuel Injector Water Flow Test Data
50
Fuel Trim Valve Set Data – (used 25/75 fuel mix)
51
Fuel Trim Valve Set Data – (used 25/75 fuel mix)
52
Injector Design Data