2016/9/30 Yasuhiro Sugimoto @ILC Infra/CFS mini-ws
ILD assembly timeline 2016/9/30 Yasuhiro Sugimoto @ILC Infra/CFS mini-ws
2
Boundary conditions Detector assembly and commissioning should be completed in 9 years Assembly Hall (AH) on surface becomes available in Q3 (Aug.) of Y3 Platform over vertical shaft in AH becomes available in Q2 of Y4 Detector Hall (DH) underground becomes available in Q3 (Aug.) of Y7 SiD is lowered to DH in Y7-Q3 to Y8-Q1 ILD is lowered to DH in Y8-Q2 to Y8-Q3 after SiD (New assumptions) Magnet full current test should be done before barrel calorimeter installation Solenoid outer vacuum tank (OVT) is built outside YB0 yoke, and inserted to YB0 as a cylinder (Richard’s plan)
3
A possible solution
4
Comparison with previous plan
Shorter yoke construction period Earlier start of Muon/Endcap CAL installation Shorter Solenoid construction period Previous timeline New timeline
5
Timeline for each ring
6
Timeline for solenoid OVT and coil are assembled and installed using swiveling platform successively (CMS:OVT was assembled directly on the YB0) IVT is assembled aside the swiveling platform, and moved to the swiveling platform for installation Period for coil assembly on-site is shortened from 30 mo to 16 mo Starts 10 mo later due to tool preparation/test (ignored before) and OVT construction and installation Completed 4 mo earlier to make magnet full current test possible before barrel CAL installation The timeline is somewhat tight, but still looser (?) than that of CMS CMS: 5 modules, ILD: 3+4(DID) modules (?)
7
Longer term timeline
8
Swiveling platform ~14m ~4m (In case of ILD) ~14m
9
Swiveling platform
10
Swiveling platform
11
Garage in AH Size of the garage (alcove) of Assembly hall should be enlarged Swiveling platform requires large space during swiveling Position of the swiveling platform is shifted One more yoke ring exists before Coil/IVT installation YB0 with OVT has to be stored in the garage to keep enough space for other yoke assembly and detector installation Space for cryogenic system on surface YB0 in garage 15m 25m Before After 15m 10m
12
Open questions Iron yoke rings should be assembled in ~6 months/ring
Is it feasible? What is the size of pre-assembly hall needed for construction of iron blocks? DID options (No DID or integrated into 3 solenoid modules is favorable from mechanical point of view) Feasibility of DID manufacturing Is the timeline for solenoid (+DID) construction acceptable for manufacturer? Toshiba will study Space and time requirements for the cryogenic system for solenoid in Assembly Hall on surface Installation method for endcap muon detector (particularly bottom part) Do we need a pit for installation in AH (and DH)?
13
Backup slides
14
Step-1 Platform construction YB0 Yoke assembly OVT assembly
15
Step-2 YE+ Yoke assembly OVT install
16
Step-3 YE+ Yoke assembly YB0 Muon detector install Coil assembly
IVT assembly
17
Step-4 YE- Yoke assembly YE+ Muon detector install
YB0 Muon detector cabling Coil assembly IVT assembly
18
Step-5 YE- Yoke assembly YE+ HCAL install Coil assembly IVT assembly
19
Step-6 YB+ Yoke assembly YE+ ECAL install YE- Muon detector install
Coil assembly IVT assembly
20
Step-7 YB+ Yoke assembly YE+ Muon detector cabling YE- HCAL install
Coil assembly IVT assembly
21
Step-8 YB- Yoke assembly YE- Muon detector cabling
YE+ HCAL,ECAL cabling YB0 Coil install
22
Step-9 YB- Yoke assembly YE- HCAL cabling YB0 IVT install
23
Step-10 Disassemble swiveling platform Shuffle yoke rings
Cryogenic system construction in garage Cryo. Cryo. Cryo.
24
Step-11 YE- ECAL install YB0 Cryogenics install Coil cooling
25
Step-12 Close detector Magnet full current test Cryogenics
26
Step-13 Open detector YB+ Muon detector install YB0 CAL install
YE- ECAL cabling Cryogenics
27
Step-14 YB- Muon detector install YB0 CAL install Cryogenics
28
Step-15 Close detector Field mapping Cryogenics