1 FORSYTH COUNTY SCHOOLS 2014 CAPITAL PROGRAM TIMELINE LOCATION
LOCATION CONSTRUCTION PROJECT ARCHITECT A/E START GC/CM OPEN SUMMARY STATUS HIGH SCHOOL ADDITIONS AND MODIFICATIONS North Forsyth H.S. Stadium visitors concession and restroom BRPH Done Charles Black Certificate of Occupancy issued 8/14/14 Gymnasium and Cafeteria FSF Barton Malow Aug-16 steel, masonry, roof decking in progress Additions Renovations Aug-17 Forsyth Central H.S. CPL Parrish steel, masonry, roof, curbing in progress South Forsyth H.S. MSSA Balfour Beatty steel, masonry, roof in progress Lambert H.S. Additions- 19 classrooms , band Artificial Turf Field (IGA $ , not bond) Breedlove Shaw field complete, ready for play West Forsyth H.S. Additions - Performing Arts (Band,Choral) Started Apr-16 Apr-17 design in progress to be complete March 2016 Renov's (Art,Computer,Engineering Labs) High School #7 Denmark HS New Construction Mar-16 Jun-18 design in progress to be complete February 2016 Denmark H.S. General Contractor prequalification review in progress

2

3 North Forsyth High School

4 Forsyth Central High School

5

6 MIDDLE SCHOOL ADDITIONS AND MODIFICATIONS
Liberty M.S. Modify front entrance for security James Buckley Done Complete Modifications for performing arts Sep-15 Apr-16 Aug-17 design in progress to be complete February 2016 Expand Band Classroom Little Mill M.S. Modify front drive entrance McFarland Dyer Sep-16 Mar-17 North Forsyth M.S. Media center , performing arts, team room HVAC replacement / modification CGE Capital City Aug-15 HVAC completed Otwell M.S. Expand technology lab , drama Piney Grove M.S. Front Drive sidewalk Modify technology lab South Forsyth M.S. 23 Classroom Addition RaLin Aug-16 steel, masonry in progress Expand Media Ctr ,Cafeteria, Modify PA Riverwatch M.S. 24 Classroom Addition Expand band room Vickery Creek M.S. Expand Media Ctr , Technology Lab Middle School #10 MS #10 New Construction Evergreen masonry, roof, windows , MEP rough, paint, curbing in progress (DeSana Middle School) Middle School #11 MS #11 land purchase search, due dilligence options in progress

7

8

9 Riverwatch Middle School

10 South Forsyth Middle School

11 ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS
Brandywine ES Brandywine ES New Construction LPBC Done Charles Black Aug-16 masonry, roof, MEP rough, curbing in progress Midway ES Sanitary sewer service CEC Started Nov-16 Civil Engineer Consultants Inc design in progress Daves Creek HVAC replacement / modification CGE Waters Aug-15 HVAC substantially completed Settles Bridge Capital City HVAC completed General security,media ctr, partitions, parking TBD