Downtown Midland Downtown Streetscape Redevelopment Update April 10, 2017
2
Downtown Midland Streetscape Redevelopment
June-September 2016 community input and design October streetscape approved began engineering design November - January four-way stop trial permanent approval
3
Downtown Midland Streetscape Redevelopment
April construction contract out for bid May 22 Hire construction contractor June week construction process begins
4
Downtown Midland Streetscape Redevelopment
Work Estimated Cost Anticipated Funding Base Streetscape construction -earthwork, pavement, electrical, curb & gutter, sidewalk, crosswalks, accent areas, planters, trees, decorative lighting, construction administration and contingencies, etc. $7.2 million Commitment $7M – Foundations Public Engagement/Draft Design Engineering Design Work City Construction Management $150,000 $600,000 $250,000 DDA Reserves Engineering Priorities TOTAL $8.2 million Amenities $500,000 Community Match Heated Sidewalks / Snowmelt System $1.2 million
5
Downtown Midland Streetscape Redevelopment
Work At Hand Construction timeline / strategies Infrastructure Review Construction communications Heated Sidewalks/Snowmelt Event Planning 2017 Amenities
7
Downtown Midland Streetscape Redevelopment
Work At Hand Construction timeline / strategies Infrastructure Review Construction communications Heated Sidewalks/Snowmelt Event Planning 2017 Amenities
8
Infrastructure Lining Sanitary Sewer leads
Small section of water main improved Hydrant relocations Coordination with MDOT to tie in Main Street / Jerome intersection with 2018 bridge construction
9
Downtown Midland Streetscape Redevelopment
Work At Hand Construction timeline / strategies Infrastructure Review Construction communications Heated Sidewalks/Snowmelt Event Planning 2017 Amenities
10
Downtown Midland Streetscape Redevelopment
Dedicated website E-Newsletter Print materials Social media / digital promotion On-street signage
11
Downtown Midland Streetscape Redevelopment
Promotional Tool Kit for businesses Downtown ambassador program Celebration event(s)
12
Downtown Midland Streetscape Redevelopment
Work At Hand Construction timeline / strategies Infrastructure Review Construction communications Heated Sidewalks/Snowmelt Event Planning 2017 Amenities
13
Downtown Midland Streetscape Redevelopment
Heated Sidewalks/Snowmelt The recommended plan utilizes a gas-fired boiler plant. Total cost to construct: $3.6 million Annual energy cost: $80,000 Anticipated annual system maintenance/operations: $40,000
14
Downtown Midland Streetscape Redevelopment
Heated Sidewalks/Snowmelt Assessments developed per ff of benefitting property, average ~ $90,000/property.
15
Downtown Midland Streetscape Redevelopment
Heated Sidewalks/Snowmelt 27 Main Street property owners notified; Received responses from 14 of those property owners contacted (63%); Represents 60% of the total assessable property for this project.
16
Downtown Midland Streetscape Redevelopment
Heated Sidewalks/Snowmelt All respondents indicated that the assessment was too costly Many suggested a more cost-effective snow removal plan should be considered
17
Downtown Midland Streetscape Redevelopment
Heated Sidewalks/Snowmelt DDA voted in March to remove the snowmelt system construction from consideration
18
Downtown Midland Streetscape Redevelopment
Work At Hand Construction timeline / strategies Infrastructure Review Construction communications Heated Sidewalks/Snowmelt Event Planning 2017 Amenities
19
Downtown Midland Streetscape Redevelopment
Event Planning Downtown Story Day – April 22 Memorial Day Parade – May 29
20
Downtown Midland Streetscape Redevelopment
Event Planning Tapped, June 17 moved to Larkin & Townsend Riverdays AfterParty, July 14 moved to Ashman Street, outdoor service WhichCraft, Diamond Jim’s “Summer Sales”, July back doors/parking lots
21
Downtown Midland Streetscape Redevelopment
Event Planning Taste of Downtown cancelled for 2017 Gus Macker Tournament Northwood Campus Cruise n Car Show, Sept Farmers Market area
22
Downtown Midland Streetscape Redevelopment
Event Planning Chili & Salsa – Sept. 23 ??? Festifall, Oct. 7 Larkin, Townsend Mannequin Night, Oct. 19 ???
23
Downtown Midland Streetscape Redevelopment
Event Planning Outdoor dining – allowed until block street construction begins
24
Downtown Midland Streetscape Redevelopment
Work At Hand Construction timeline / strategies Infrastructure Review Construction communications Heated Sidewalks/Snowmelt Event Planning 2017 Amenities
25
Downtown Midland Streetscape Redevelopment
Amenities Fire pit Water feature Swing-type seating Gateway features
26
“… I decided the downtown of any town is the heart of the town, and you can’t grow a new one. The downtown is one of the most important parts of any town.” Carl A. Gerstacker, charter member of the Midland Downtown Development Authority
27
Questions?