MOVING FORWARD!!
2
Cooling Pond S/S Ponds Channels Coke Ovens Brook WTP Cutoff Wall GW Collection Tar Cell Cutoff Wall Landfill
3
Design at 95% ( Fall ’07 – Summer ’08) On Site Landfill
4
Channels in North and South Ponds (Fall ’07 – Fall/Winter ’09)
Design at 100% Channels in North and South Ponds (Fall ’07 – Fall/Winter ’09) Floating Navigational Barrier
5
(Fall ’07 Start) Access Road Ferry St. Containment Cells for Sediments
from Channels
6
Build Access Road Along Shoreline Infill for Access
7
Pile System Installation
8
New Channels By Spring of ‘10
9
Solidification and Stabilization
Auger Excavator Sheet Piles Solidification and Stabilization
11
Design at 75% Start Fall ’07 to 2014
12
Transport Brook Sediments
Design at 95% (Start Spring ’08) Transport Brook Sediments For S/S Treatment Tar Cell
13
Design at 75% (Spring ’08 to 2012) Capped Area
14
Design at 75% Cutoff Walls (Spring ’08 – Spring ’09)
15
Design at 50% WTP Fall ‘08 – Spring ‘10 Capping Ongoing
16
Design at 75% Tar Cell (2011 – 2012)
17
Cooling Pond S/S Ponds Channels Coke Ovens Brook WTP Cutoff Wall GW Collection Tar Cell Cutoff Wall Landfill