1 Next Phase Solar Project Update
Dan Howell, C.P.M. November 2, 2016

2 Background 5.5 MW’s Currently Installed Anticipated Production
12.4 million Kwh’s per year Renewable Capacity > 50% at Installed Facilities Nearly 20% of total Electrical Needs

3 Next Phase Solar Opportunities
Feasibility Assessment: TerraVerde Renewable Partners Approved by Board on August 17, 2016 30-Week Project Assessment

4 Project Schedule Project Phase Time Frame
Phase 1 – Due Diligence Data Gathering 9 Weeks Phase 2 – Feasibility Analysis 7 Weeks Phase 3 – Financial Viability 5 Weeks Phase 4 – Develop Report and Review Phase 5 – Implementation Plan 4 Weeks

5 Scope of Work RES – BCT (Renewable Energy Self-Generation Bill Credit Tariff Program) Up-to 5 MW’s per Installation Transfer $ Credit to “Benefitting Accounts” Limited to Local Government Entities NEM (Net Energy Metering ) 2.0 Program Removes MW Size Limit Provides $ Benefit Covering both Generation and Transportation

6 Additional Research – Floating Solar
Floating Solar - Benefits Increasingly Feasible Minimizes Property/Land Use Reduces Evaporation Controls Algae Preliminary Assessment – Winchester and Trumble Road Ponds Higher Capital Cost Lower Energy Production Efficiency (non-tracking arrays) Operational Challenges Substantially Fluctuating Water Levels Pond Maintenance Constraints Routine Maintenance of Floating Array

7 Preliminary Cost Comparison 5 MWD RES-BCT Basis
Floating vs. Ground Mount Solar Systems Preliminary Cost Comparison 5 MWD RES-BCT Basis Capital Cost Present Value Saved Recycled Water (*) Present Value $.07/kwh (*) Payback Ground Mount Tracker System $9,250,000 $0 $11,455,000 15 Years Floating Mount Fixed System *20 Years at 3% $11,900,000 $498,400 $8,592,000 30 Years

8 Floating Solar – Not Recommended
Not Recommended to Pursue at this Time District has Available Land Avoids Operational Challenges Evolving Technology Cost

9 Current Status Phase 1 – Due Diligence and Data Gathering Underway
Energy Use/Billing Data NEM Sizing Analysis RES – BCT Benefitting Account Selection Proposed Siting Analysis Interconnection Assessment Proposed Completion – April/May 2017

10 Contact Information Dan Howell, C.P.M. Senior Director of Administrative Services (951) Ext. 6246