Quick Changeover Single Minute Exchange of Dies

Similar presentations


Presentation on theme: "Quick Changeover Single Minute Exchange of Dies"— Presentation transcript:

1 Quick Changeover Single Minute Exchange of Dies
Lean Manufacturing Series

2 Outline Changeover and Changeover Time Traditional Setup SMED
SMED Process Steps Ideas for Improvement

3 Traditional Setup Practices
Material movement occurs after the machine is turned off. Completed products are transferred to next operation. Raw material is moved after the machine is stopped. Detection of defects or missing equipment is noticed when the machine is running. Setup tooling delivered after the changeover has begun. Defective product identified after internal setup has begun. Defective tooling, fixtures, setup instruments are noticed after the machine is turned on. The operator notices that equipment is missing after internal setup has begun.

4 Setup reduction methodology
Many key ideas developed by Shigeo Shingo Shingo called it SMED Single minute exchange of dies Means single digit, i.e. Less than 10 minutes Example: ton press Before: 4 hr After: 3 min Improvement: 98.7%, or a factor of 80

5 One Step Fastening Bolt attachments requires 32 complete turns for each bolt or screw (1 for each thread) to fasten this bolt and die to a machine. This clamp attachment requires one step to attach the die to a machine.