Electric Power Industry Reform Act (EPIRA)

Similar presentations


Presentation on theme: "Electric Power Industry Reform Act (EPIRA)"— Presentation transcript:

1 Electric Power Industry Reform Act (EPIRA)
Republic Act No. 9136 Electric Power Industry Reform Act (EPIRA) Signed: 8 June 2001 Effectivity: 26 June 2001 Implementing Rules & Regulations Signed: 27 February 2002

2 ACCESS & RETAIL COMPETITION The BLUEPRINT of the electricity industry.
Objective of EPIRA OPEN ACCESS & RETAIL COMPETITION RESTRUCTURING R.A (EPIRA) The BLUEPRINT of the electricity industry. PRIVATIZATION

3 RESTRUCTURING Before the reforms… DISTRIBUTION TRANSMISSION POWER
PLANTS & IPPs END USERS SYSTEMS OPERATIONS NATIONAL POWER CORPORATION 18 PRIVATE UTILITIES 2 LOCAL GOVERNMENT UNITS 120 ELECTRIC COOPERATIVES OTHER IPPs

4 RESTRUCTURING After the reforms… GENERATION DISTRIBUTION TRANSMISSION
POWER PLANTS & IPPs END USERS SYSTEMS OPERATIONS NATIONAL CORPORATION 18 PRIVATE UTILITIES 2 LOCAL GOVERNMENT UNITS 120 ELECTRIC COOPERATIVES OTHER IPPs MARKET OPERATOR SUPPLY GENERATION

5 Competition at the wholesale & retail level
RESTRUCTURING Performance Based Regulation Benchmarking Competition at the wholesale & retail level

6  RESTRUCTURING Existing contractual arrangements Generators TRANSCO
Distribution Utility End-users

7   RESTRUCTURING Transaction flow under Open Access Regime WESM RES
Generators TRANSCO Distribution Utility End-users

8 Our MANDATE Sec. 38 of EPIRA “There is hereby created an
independent, quasi-judicial regulatory body to be named the Energy Regulatory Commission (ERC).”

9 Our MAJOR FUNCTIONS Promote competition Monitor the Market
Encourage market development Ensure customer choice Penalize abuse of market power

10 Our MAJOR FUNCTIONS Generation Transmission Distribution Supply
Tariffs of TRANSCO Philippine Grid Code CAPEX plans Ancillary services Certificate of Compliance Generation tariffs (prior to WESM and full NPC privatization) SPUG (Missionary Electrification) WESM monitoring Competition Rules Distribution Supply Tariffs of distribution utilities Philippine Distribution Code Lifeline rate Franchise for consortium of sub- transmission assets Stranded contract cost Systems loss CPCN Spot inspections/ audits Bilateral power supply contracts CAPEX plans Magna Carta and DSOAR enforcement Suppliers’ licenses Issuance of needed rules for retail competition Declaration of open access and retail competition Competitive Natural Monopolies

11 Chief Executive Officer Administrative Service Regulatory Operations
Our ORGANIZATION COMMISSION Chair Commissioner General Counsel & Secretariat of the Commission Chief Executive Officer (Chair) Internal Audit Unit Investigation & Enforcement Division Executive Director Field Offices Financial and Administrative Service Legal Service Planning and Information Service Regulatory Operations Service Market Operations Service Consumer Affairs Service

12 Open Access and Retail Competition Transfer of NPC-IPP Contracts
The Journey Open Access and Retail Competition Transfer of NPC-IPP Contracts Privatization of NPC Establishment of WESM Cross Subsidy Removal Unbundling of Rates Title of Presentation

13 Retail Competition Timeline
LUZON GRID 750 kW – 999 kW Aggregation within contiguous area allowed 1 MW & above Household level Year 1 2 Year 3 Year 10