Download presentation
Presentation is loading. Please wait.
Published byFelicity McCormick Modified over 6 years ago
1
Research and development for future LHC Superconducting Magnets WP status
J.M. Rifflet – Steering committee –January 09th 2015
2
Les 7 Work-packages Description CERN CEA WP1
Coordination and monitoring of activities L. Bottura J.M. Rifflet WP2 Design and prototyping of a new Nb-Ti Q4 pour HL-LHC E. Todesco M. Segreti WP3 Completion of the Nb3Sn magnet FRESCA2 and participation to the tests P. Ferracin F. Rondeaux WP4 Support in the Nb3Sn technology R&D J.C. Perez M. Durante WP5 Completion of the HTS insert winding for FRESCA2 G. De Rijk WP6 Study of HTS magnets at high field Ph. Fazilleau WP7 Mechanical study of Rutherford cable L. Oberli P. Manil Merci à eux pour les infos contenues dans cette présentation CERN-CEA collaboration – Steering committee -09 janvier 2015
3
WP2 : Q4 Magnets for LHC Upgrade
CERN-CEA collaboration – Steering committee -09 janvier 2015
4
Q4 Magnets : Contenu de la tâche
Sur la base de l’étude de la design study Hilumi WP3.5: 1) Study, realization and cold test of one single aperture magnet short model: Conceptual & CAD studies Manufacture zone adaptation Specifications and call for tenders, Follow-up of tooling and components realization Coil 0 manufacture collaring test 4 coils manufacture, instrumentation, collaring Cold test facility adaptation Cold test of the single aperture short model Winding of 2 additional sets of coils 2) Study of the cold mass (quad + correctors) and integration in accelerator (CM conceptual & CAD studies, interfaces and tooling definition, assembly procedure of the cold mass). CERN-CEA collaboration – Steering committee -09 janvier 2015
5
Magnetic design WP2 - Q4 magnets for HL-LHC
Little change of the hole position in the iron yoke for the heat exchanger Meeting Collaboration, Steering Committee CERN-CEA | | P 5
6
Magnetic design WP2 - Q4 magnets for HL-LHC
Heat exchanger and cold bore are farther now this gives more space for the welding and cutting machine b3 coming from cross-talk is now minimized by means of 20 mm diameter holes near the magnet center this change for heat exchanger position in the corrector magnets for Q4 has tro be taken into account for correctors design Meeting Collaboration, Steering Committee CERN-CEA | | P 6
7
Hilumi WP2 interaction WP2 - Q4 magnets for HL-LHC
Demand for cycling at low current to investigate the effects on the field quality Meeting Collaboration, Steering Committee CERN-CEA | | P 7
8
Coil ends WP2 - Q4 magnets for HL-LHC
3D calculations realized again, but with the last version of ROXIE some change needed to smooth the curves Optimization by minimizing: the strain energy of the cable b6 integrated at lead-end and return-end the peak field One of the challenges is the specific cable output Meeting Collaboration, Steering Committee CERN-CEA | | P 8
9
Drawing office WP2 - Q4 magnets for HL-LHC
Work at drawing office started only on September 2014 (no availability before) People from the drawing office affected to the Q4 project: 1 engineer (30%) 1 designer (50%) 1 other designer is planned for the beginning of 2015 Meeting Collaboration, Steering Committee CERN-CEA | | P 9
10
Winding trial WP2 - Q4 magnets for HL-LHC
A winding trial will validate the geometry of the end-spacers 40 m of insulated cable were sent from Cern. This length is sufficient to make two 700-mm-long mockups Drawings for the winding trial of a 700-mm-long mockup is finished. It includes: The components (cable, end-spacers, wedges and the special support of the specific cable output). The tooling (mandrel, accessories) Meeting Collaboration, Steering Committee CERN-CEA | | P 10
11
Winding trial WP2 - Q4 magnets for HL-LHC
The Cern routine allowed to obtain rapidly the CAD of end-spacers from ROXIE output files A first set of end-spacers was 3D printed in plastic material at the design office A second set is printed at Cern with Bluestone composite material which can survive to the curing temperature The tooling and accessories for the winding trial are entirely realized The winding trial will be performed on first half of January 2015 Meeting Collaboration, Steering Committee CERN-CEA | | P 11
12
No budget planed for test station adaptation
WP2 - Q4 magnets for HL-LHC Cold test of the single aperture short model The baseline is that the test of the single aperture short model will be done at CEA-Saclay The solution could be to use the 8 m vertical cryostat Verification is still in course, but the biggest issue is that for now, no current leads are available for a test at 20 kA at Saclay No budget planed for test station adaptation Philippe BREDY will give the technical characteristics of the needed current leads In any cases, Cern should provide the entire measurements system Meeting Collaboration, Steering Committee CERN-CEA | | P 12
13
Milestones and deliverables
WP2 - Q4 magnets for HL-LHC Milestones and deliverables No change since the kick-off of July 2014 N° Description Actual collaboration agreement Today 2.1 Complete design of the single aperture magnet short model December 2014 April 2015 2.2 Winding and polymerization of short coil 0 August 2015 January 2016 2.3 Completion of all coils (3 sets in total) July 2016 2.4 Single aperture magnet short model assembly February 2016 September 2016 2.5 Assembly procedure end of cold mass (quad + correctors) December 2016 Meeting Collaboration, Steering Committee CERN-CEA |
14
Planning WP2 - Q4 magnets for HL-LHC
Meeting Collaboration, Steering Committee CERN-CEA |
15
WP3 : FRESCA2 Magnet CERN-CEA collaboration – Steering committee -09 janvier 2015
16
Fresca2 Magnet: Contenu de la tâche
Fabrication d’une bobine Cu type 3-4 avec outillage modidié Fabrication de 2 bobines Nb3Sn type 1-2 Assemblage et test, dans la structure des 2 bobines Nb3Sn type 1-2 avec 2 bobines Cu type 3-4 Fabrication de 2 bobines Nb3Sn type 3-4 pour le dipôle FRESCA2 Assemblage et test du dipôle FRESCA2 CERN-CEA collaboration – Steering committee -09 janvier 2015
17
Status 2 copper coils already partially done : CC3401 (type 3-4):
winding OK, sent to CERN (25/06/2013) heat treatment OK impregnation OK CC1201 (type 1-2) winding OK, sent to CERN (07/01/2014) CERN-CEA collaboration – Steering committee -09 janvier 2015
18
Modified winding / reaction tooling
We have received the modified winding / reaction tooling (in 3 parts) for type Test on coil (4+4 turns of RRP cable) with modified tooling + large gaps (DR3401) : OK, cf. next slide Test on coil (4+4 turns) with modified tooling + adjusted gaps (DR3402) : winding OK, waiting for the new guiding rings Procurement of the modified tooling for type 1-2: delivery in early April CERN-CEA collaboration – Steering committee -09 janvier 2015
19
DR3401 It moved! 1,9 mm sym side + 1,3 mm asym side
¾ ceramic guiding rings broken will be modified CERN-CEA collaboration – Steering committee -09 janvier 2015
20
Milestones 2 options: 1) strategy maintained with intermediate test.
2) without intermediate test (and CC3402). Option 1 Kick-off meeting Today 3.1 : 1 Cu coil type 3-4 with modified tooling March 2015 June 2015 3.2 : 2 Nb3Sn coils type 1-2 for FRESCA 2 magnet delivered September 2015 December 2015 3.3 : 2 Nb3Sn coils type 1-2 tested with 2 Cu coils February 2016 May 2016 3.4 : 2 Nb3Sn coils type 3-4 for FRESCA 2 magnet delivered 3.5 : FRESCA 2 magnet tested August 2016 November 2016 Option 2 Kick-off meeting Today 3.2 : 2 Nb3Sn coils type 1-2 for FRESCA 2 magnet delivered September 2015 November 2015 3.4 : 2 Nb3Sn coils type 3-4 for FRESCA 2 magnet delivered February 2016 3.5 : FRESCA 2 magnet tested August 2016 June 2016 CERN-CEA collaboration – Steering committee -09 janvier 2015
21
We are in favour of option 2. Does the committee confirm this option?
Pro: Validation and adjustment of assembly procedure Detection of big problem on 1-2 Nb3Sn coils Cons: Risk of damage 1-2 Nb3Sn coils during assembly with dummy Cu coils and desassembly Etienne Rochepault study : with the same level of stress, only 10.5 T central field (do we detect problems ?) coils 3-4 in Nb3Sn not tested Time lost because test and desassembly for intermediate test are on the critical path Option 2 Pro Planning Cons: First real assembly with Nb3Sn Risk of assemble Need of Nb3Sn cable in March We are in favour of option 2. Does the committee confirm this option? CERN-CEA collaboration – Steering committee -09 janvier 2015
22
Option 1 Option 2 CERN-CEA collaboration – Steering committee -09 janvier 2015
23
WP4 : Nb3Sn Technology development
CERN-CEA collaboration – Steering committee -09 janvier 2015
24
Nb3Sn Technology development : Contenu de la tâche
Tests de dilatation pendant la réaction thermique de formation du supra Mesures dimensionnelles sur « ten-stack » imprégné ou non, avant et après réaction) Mesures de rétreint thermique . CERN-CEA collaboration – Steering committee -09 janvier 2015
25
Dilatation tests 1 full scale dilatation test (2 x 4 turns on 3-4 tool) has been performed Second full scale dilatation test: Winding finished Will be send to CERN for heat treatment very soon. Sym Gauche Sym Droit Asym Gauche Asym Droit After winding 9,7 9,75 5,93 Sortie du four 7,84 7,79 4,57 4,58 Ecart -1,86 -1,96 -1,36 -1,35 moyenne -1,91 CERN-CEA collaboration – Steering committee -09 janvier 2015
26
Total gap (central - lateral)
Dilatation tests 2 reduced scale dilatation tests with insulated RRP Nb3Sn cable have been performed Titanium mandrel Iron mandrel There are still discrepancies to understand (Iron – Titanium) Mandrel material C1 Gap reduction L SS = 600 mm L TOT = 690 mm L cable = mm 1 central gap % L SS % L TOT (head to head) % L cable Titanium Bare cable HT10 Central gap 4.89 mm 0.8% 0.7% Total gap (central - lateral) 3.97 mm 0.6% 0.5% Insulated cable HT11 4.85 mm 4.45 mm Iron Insulated cable “free” 3.62 mm 0.76 mm 0.1% CERN-CEA collaboration – Steering committee -09 janvier 2015
27
Milestones N° Description Kick off meeting Today 4.1
Mechanical test facilities design September 2014 4.2 Mechanical test facilities ready December 2014 4.3 Dilatation tests report – preliminary July 2014 To be sent 4.4 Dilatation tests report - final April 2015 4.5 Report on Mechanical tests at Saclay December 2015 CERN-CEA collaboration – Steering committee -09 janvier 2015
28
WP5 : HTc Insert CERN-CEA collaboration – Steering committee -09 janvier 2015
29
HTc Insert : Contenu de la tâche
Bobine prototype de 270 mm de long : Etude de la dépendance de YBaCuO selon l’orientation du champ. Tests au LNCMI Grenoble Réalisation de l’insert Htc: Test de l’insert seul (à bas courant : ~100 A) Test de l’ insert en champ externe (FRESCA2) CERN-CEA collaboration – Steering committee -09 janvier 2015
30
Design review – first design
B0 = 6 T Je= 250 A/mm2 Bpeak= 5,87 T Inom = 2400 A Electron-beam welding CERN-CEA collaboration – Steering committee -09 janvier 2015 External pads, 316L 8/9 parts Electron-beam welded External tube, Nitronic 40 - 8 parts, - Thermal shrinkage - TIG welding 3 double layers coils Glass epoxy inter-coil and external insulation Iron pole Compression plates, 316L
31
Pad is a structural component Pad is a filler
Design review Proposal in order to decrease the stress in the pad : Do not weld the pad Pad welded Pad free CERN-CEA collaboration – Steering committee -09 janvier 2015 welding Pad is a structural component 429 MPa Pad is a filler 160 MPa Von Mises stress
32
Pad not welded stress in the coil significantly lower
Design review Pad not welded stress in the coil significantly lower Pad welded Pad not welded CERN-CEA collaboration – Steering committee -09 janvier 2015 1160 MPa 636 MPa Von Mises stress in the coils
33
Updated design in 13 T background field
Tube thickness : 5.5 mm (against 3 mm in the former design) VM stress (Pa) 822 Mpa < 1400 × 2/3 (900 Mpa) CERN-CEA collaboration – Steering committee -09 janvier 2015 Material: Nitronic 40 Yield stress at 4 K: 1400 MPa (1000 Maximum deflection in x: mm
34
Updated design in 13 T background field
Coil 1 Coil 2 Coil 3 Old design New design Tube thickness (mm) 3 5.5 # turn coil 1 36 (73 total) 33 # turns coil 2 30 (61 total) 26 # turns coil 3 17 (35 total) 11 Joverall (A/mm2) 250 In (A) 2760 B0 (T) 6.0 5.4 -3 turns -4turns -6 turns CERN-CEA collaboration – Steering committee -09 janvier 2015
35
Mechanical Structure Stand-alone mode
Phase I, stand-alone test : we will use a demountable mechanical structure (assembly less risky and faster, possibility to adjust the pre-stress, possibility to quickly and easily open the magnet) Phase 2, test in Fresca 2 : demountable structure replaced by a tube (heat-shrink method) CERN-CEA collaboration – Steering committee -09 janvier 2015 Phase 1 Phase 2
36
CAD detailed design ongoing
Magnet fabrication CAD detailed design ongoing New pads design End saddles design taking into account new coil dimensions Mechanical structure for standalone tests Coil handling tooling (for magnet assembly) Interface with the test station CERN-CEA collaboration – Steering committee -09 janvier 2015 Row Material Fabrication status Delivery Pole pieces Procured Completed Delivered End saddle Pending - Pad Coil Insulation (G10) External tube
37
Cable Magnet fabrication CuBe2 Stabliizer:
880 m of CuBe2 tape annealed at CEA (3h at 300 °C in Argon). The order for the insulation of the CuBe2 tape has been placed Insulation foreseen in January HTS tape: We have 2 unit lengts (UL) of 40 m. We still miss the two 110 m UL and two 40 m UL (check with Amalia in course) Dummy SS tape to be delivered very soon (sent) dummy winding end of January) CERN-CEA collaboration – Steering committee -09 janvier 2015
38
Winding tooling Magnet fabrication
Modification of the winding table is done Use of small magnetic brakes partially validated with CuBe tape Four more magnetic breaks (6 needed) ordered, to be delivered this week Tape supports and guides during winding ordered, to be delivered by end of January 12 winding reels for the 6 tapes delivered CERN-CEA collaboration – Steering committee -09 janvier 2015
39
Milestones N° Description Collaboration contract Kick off meeting 5.1
Test of the prototype at LNCMI February 2014 September 2013 Test of a second prototype at LNCMI March 2015 5.2 Construction of the insert March 2014 June 2015 5.3 Test report of the insert inside FRESCA2 July 2016 September 2016* CERN-CEA collaboration – Steering committee -09 janvier 2015 No change since kick-off meeting *depending of FRESCA2 schedule
40
WP6 : High field magnet studies
CERN-CEA collaboration – Steering committee -09 janvier 2015
41
WP6: HIGH FIELD STUDIES The work package deals with 20 T field accelerator-type configurations and its consequences on mechanics and materials: The purpose of this work package is to study materials under the large stresses generated in such new configurations, Which are the mechanical properties needed, depending on the layout configurations (figure below) and on the location inside the magnet, Which materials are suitable for these properties ? Do they exist ? We may need some measurements to find out the appropriate materials. CERN-CEA collaboration – Steering committee -09 janvier 2015
42
WP6: HIGH FIELD STUDIES 0. Starting from J. von Nugteren study, 1. Selection of a limited number (3-4) of adequate configurations to study, 2. Mechanical study for each configuration: parametric analysis and FEM analysis, 3. Selection of appropriate materials and if needed, qualifications tests to perform, 4. Report CERN-CEA collaboration – Steering committee -09 janvier 2015
43
WP6: HIGH FIELD STUDIES The delivery of this work package is a report on mechanical studies, The work estimated as 3 person.month has not started yet, Chhon Pes, mecanical engineer, will perform the mechanical computations (CAST3M), Small qualification tests could be foreseen: 1 engineer and 1 technician are estimated for this part of the duty. Meeting at Saclay in January with J. von Nugteren to select the adequate configurations to study, CERN-CEA collaboration – Steering committee -09 janvier 2015
44
WP7 : Mechanical studies of rutherford cable
CERN-CEA collaboration – Steering committee -09 janvier 2015
45
WP goals and deliverables
Deliverable (Dec. 2015): Finite Elements Model of cable samples lifecycle Steps: 1| Identification of several types of cables of interest for CEA and CERN (SMC, FRESCA2…). For each type of cable: 2| Identification of the strand(s) behaviour law 3| Modeling of the cabling process → validation on the base of tomographic analysis 4| Geometrical reconstruction of insulated cables 5| Modeling of the cable under mechanical solliciation → comparison with experimental results on stacks CERN-CEA collaboration – Steering committee -09 janvier 2015
46
2 mechanical models / 3 cable geometries
① Cable forming With major simplifications (≠ CERN approach) ② Cable in service Stack test modeling. Standby, waiting for a postoc (Feb. 2015?) CERN-CEA collaboration – Steering committee -09 janvier 2015
47
Samples inventory 9-strand cable: NbTi strand from Iseult magnet => setup model Tomographic and mechanical data already available 18- and 40-strand cable: Nb3Sn, Ø 1 mm strands PIT, RRP or copper Reacted or not Data is currently being collected CERN-CEA collaboration – Steering committee -09 janvier 2015
48
On-going: mechanical characterization
Work performed by MSSMAT Monotone traction up to rupture Traction with load/unload cycles No cycling => Behaviour laws for ‘cable in service’ model ② unreacted reacted strand alone (no cable) Ø 1 mm copper COCA/IRFU/S/CUXX RRP COCA/IRFU/S/RRPXX 10 m delivered to ECP (2013) 1 m under reaction PIT COCA/IRFU/S/PITXX 1.5 m delivered to ECP (07/2014) CERN-CEA collaboration – Steering committee -09 janvier 2015
49
On-going: tomography and SEM
SEM on strands (reacted or not) Tomography on cables (reacted or not) Geometrical data for validation of the ‘cable forming’ model ① CERN-CEA collaboration – Steering committee -09 janvier 2015
50
Status 2014 status Little modeling progress in 2014 due to lack of resource Delay in hiring a postdoc (5 shortlisted candidates; expected start: Feb./March 2015) Collection of raw data that will serve for the postoc Interaction with CERN Exchanges with CERN should be resumed on a regular basis Copper strand from CERN would be useful (10 m?) if available Maybe some more samples (TBC) CERN-CEA collaboration – Steering committee -09 janvier 2015
51
Conclusions CERN-CEA collaboration – Steering committee -09 janvier 2015
52
Merci pour votre attention !
Conclusions Le respect du planning , en particulier pour Q4 (HL-LHC) et pour le dipôle FRESCA2 doivent rester notre priorité absolue. En particulier, 3 embauches (1 Ingénieur projet et 1 technicien bobinage et 1 projeteur) sont prévues pour Q4. La collaboration se fait dans un très bon esprit. Il nous faut maintenir et renforcer ce bon climat Merci pour votre attention ! CERN-CEA collaboration – Steering committee -09 janvier 2015
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.